# What Is a Build-to-Suit Data Center? How the Deal Works, and Who Gets Paid When
- URL: https://www.sotkn.com/explained/build-to-suit-data-center-explained/
- Published: 2026-11-28T01:43:16.000Z
- Updated: 2026-11-28T01:43:16.000Z
- Description: A build-to-suit data center is designed and built for one tenant that signs the lease before construction starts. The developer and its lenders pay for the building first. The tenant starts paying only at handover, once the power is on.
- Author: Sean
- Tags: Mechanism, #desk-explained

EXPLAINED · Mechanism · Last reviewed: 28 Nov 2026 · Next review: after Meta, Alphabet, Microsoft and Amazon file their 2026 annual reports (early 2027), or when Fermi signs a definitive lease at Project Matador

A build-to-suit data center is a data center designed and built for one specific tenant, which signs a long lease before construction starts. A developer or landlord pays for the land, power and building, and the tenant starts paying only when the finished, powered building is handed over.

**In short.** A build-to-suit data center is built for one tenant that signs before construction starts. The developer and its lenders pay for the land, the power hook-up and the building first. The tenant, often a cloud company, starts paying only once the finished building is powered and handed over. That is why the deal has two clocks: the date the lease is signed and the date it starts. Digital Realty’s new leases in the third quarter of 2026 had a 17-month average gap between the two. Our read: the stuck step is handover. A signed build-to-suit lease is a promise; the money starts when the power is on.

Why an investor cares: the biggest cloud companies now sign for buildings years before they exist. Microsoft, Meta, Amazon and Alphabet together reported about US$1.02 trillion of leases signed but not yet started at 30 September 2026, by our arithmetic, much of it for data centers. Build-to-suit is one of the main ways those buildings get made. This page sits in our [Hyperscalers](https://www.sotkn.com/stack/hyperscalers/) layer. Our [leases not yet commenced explained](https://www.sotkn.com/explained/leases-not-yet-commenced-explained/) page covers the footnote that holds those numbers. This page covers the deal behind them: who builds, who pays first, and when the money starts.

## What is a build-to-suit data center?

Think of it as a custom house built for a buyer who has already signed. The tenant says what it needs: how many megawatts, how much cooling, how heavy the floors must be, where the network cables come in. A developer finds the land, lines up the power and puts up the building to that design.

The tenant signs a long lease before construction starts. That signature is what makes the project possible. Without it, few lenders would fund a building worth billions that is designed for one company’s servers.

The tenant does not pay while the building goes up. Payments start at commencement, which in most data center leases means the day the finished, powered building is handed over. Until then the developer is spending money, not earning it.

In plain words: the developer is paid to take the building risk, and the tenant is paid in speed and certainty. The tenant gets a site made for it without tying up its own cash in concrete and steel during the build. Our [data center lease explained](https://www.sotkn.com/explained/data-center-lease-explained/) page covers how a single lease is priced. This page is about the build-to-suit path that comes before the lease starts.

## How does a build-to-suit deal work, step by step?

Most build-to-suit data center deals follow the same six steps. The order matters, because it decides who pays first and who waits.

![Build-to-suit data center infographic: six steps from tenant signature to first payment, with power on and handover as the stuck step](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/build-to-suit-six-steps.png)

How a build-to-suit data center deal works, from signature to first payment. Infographic by Second Order.

- **1\. The tenant signs first.** The tenant agrees the design and signs a lease, often for 15 years. Applied Digital signed an approximately 15-year lease on 5 June 2026 for a single 210 MW building that was still under construction.
- **2\. The developer lines up land and power.** Power is the hard part. A big AI building can need hundreds of megawatts, which may mean new grid lines, a new substation or power made on site.
- **3\. Lenders fund the build.** Construction loans and equity pay for the work. Lenders lend against the signed lease, and sometimes against a guarantee from the tenant or its parent.
- **4\. Builders and suppliers get paid.** Contractors, and the makers of transformers, switchgear, generators and cooling, are paid as the work is done.
- **5\. Power on and handover.** The building is finished, energised, tested and accepted by the tenant.
- **6\. The lease commences.** Payments start and usually run for the full lease term. The developer starts earning on what it spent.

Step five is where deals slip. A building can be ready while the power is not, or the power can arrive before the cooling is tested. Our [how long does it take to build an AI data center](https://www.sotkn.com/explained/how-long-does-it-take-to-build-an-ai-data-center/) page sets out the build clock, and [how much it costs to build an AI data center](https://www.sotkn.com/explained/how-much-does-it-cost-to-build-an-ai-data-center/) covers the bill that the developer carries while it waits.

## Build-to-suit vs powered shell, powered land and colocation

Build-to-suit is one of several ways a cloud or AI company can get data center space. The difference is how much the landlord builds and how much the tenant does itself.

| Deal type                | What the landlord delivers                                                                 | What the tenant does                                                     | Who it suits                                                                  |
| ------------------------ | ------------------------------------------------------------------------------------------ | ------------------------------------------------------------------------ | ----------------------------------------------------------------------------- |
| **Build-to-suit**        | A finished building made to the tenant’s design, with power and cooling sized for its load | Signs a long lease before construction; moves in its servers at handover | Cloud firms and large AI tenants that want a whole building to their own spec |
| **Powered shell**        | Land, structure and the grid connection                                                    | Fits out the inside itself: power rooms, cooling, halls                  | Tenants with their own data center design teams                               |
| **Powered land**         | A site with power promised, but no building                                                | Builds the whole data center itself                                      | The largest buyers, when power is the scarce part                             |
| **Wholesale colocation** | A ready hall or building in a campus the landlord designed                                 | Leases whole halls, often one megawatt or more                           | Cloud and AI firms that need space faster than a custom build                 |
| **Retail colocation**    | Cabinets and cages in a shared building                                                    | Leases small amounts of space and power                                  | Enterprises, networks, smaller users                                          |

The lines blur in practice. Developers mix these on one campus, and a single deal can change type. Fermi’s first lease at Project Matador was a turnkey build-to-suit; its next customer signed a letter of intent for powered land instead.

The trade-off is control against speed. Build-to-suit gives the tenant a building made to its design, but it waits for the whole build. Wholesale colocation is faster if a hall is already standing. Our [hyperscale vs colocation data center](https://www.sotkn.com/explained/hyperscale-vs-colocation-data-center/) and [retail vs wholesale colocation](https://www.sotkn.com/explained/retail-vs-wholesale-colocation/) pages cover the other paths.

## Who pays for the building before it is finished?

The developer pays first. That is the core of the deal. The developer puts in equity, borrows the rest through construction loans, and carries the cost until the tenant starts paying.

The cloud companies are now changing that pattern. Instead of leaving the whole bill to an outside developer, some take a slice of the building owner themselves.

Meta is the clearest case in the filings. Its quarterly report for the quarter to 30 September 2026 describes two ventures that are building data center campuses: one in Louisiana, formed in October 2025, and one in Texas, formed in July 2026\. Meta holds 20% of each. The partners agreed to fund their share of about US$27 billion of estimated development costs in Louisiana and about US$14 billion in Texas.

Meta then signed leases with both ventures. The Texas lease starts in 2028 and the Louisiana lease in 2029\. Each has a four-year first term, with renewal options that can take it to 20 years in total. Meta also runs the construction, administration and property management for the ventures.

So Meta is both a part-owner and the tenant. Its 20% share of the two development budgets comes to about US$8.2 billion, by our arithmetic. The rest is funded by its partners. Because Meta says it does not control the ventures, it does not put them on its own balance sheet.

This is still build-to-suit at heart: a campus built for one tenant, with a lease signed long before it starts. What changes is who stands behind the building. Our [Wire on the bond that funded Meta’s Hyperion campus](https://www.sotkn.com/wire/meta-hyperion-data-center-bond-91-cents-wire/) shows how lenders price that kind of deal when it trades. Our [data center financing explained](https://www.sotkn.com/explained/data-center-financing-explained/) page covers the wider toolkit.

## Who carries the risk if the tenant walks away?

A build-to-suit building is made for one tenant. If that tenant leaves, the landlord owns a very large, very specific building and must find someone else to fill it. Lenders know this. So the strongest deals come with a promise from the tenant, or from someone stronger than the tenant, to cover the gap.

Two kinds of promise show up in the latest filings.

The first is a residual value guarantee. Meta has given these to both of its data center ventures. If Meta chooses not to renew or ends a lease, and certain other conditions are met, Meta pays the shortfall between what the property is then worth and an agreed threshold. Meta says such payments are not probable, so it has booked no liability for them.

The size is still worth knowing. Meta’s maximum residual value guarantees to the two ventures were US$41.5 billion at 30 September 2026, up from US$28.1 billion at the end of 2025\. That is a rise of 47.7%, by our arithmetic. Its total maximum exposure to the two ventures, including lease commitments and future funding, was US$68.4 billion.

The second is a credit backstop. Alphabet says in its quarterly report that it has agreed with certain third parties to backstop payment obligations related to data centers, including data center lease payments and, in some agreements, the related energy costs. If a covered party defaults, Alphabet pays, and it keeps the right to take over the leases for its own use or to sublease them.

Alphabet books these as credit derivatives. Their notional value, its own measure of maximum potential exposure, was US$48.0 billion at 30 September 2026, against US$16.9 billion at the end of 2025\. That is 2.83 times as much in nine months, by our arithmetic. The agreements run for up to 15 years, and Alphabet notes a further US$10.0 billion of potential backstops tied to its investment in the Crux AI joint venture.

![Build-to-suit data center chart: Meta’s maximum residual value guarantees rose from US$28.1bn to US$41.5bn and Alphabet’s data center backstops from US$16.9bn to US$48.0bn between 31 Dec 2025 and 30 Sep 2026](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/build-to-suit-backstops-chart.png)

Meta’s maximum residual value guarantees and Alphabet’s data center backstops, US$ billions. Data: Meta and Alphabet Form 10-Q filings, October 2026.

Our read: a backstop turns a weaker tenant’s lease into something lenders will fund, because the money behind it is Google’s. Our [Wire on Alphabet’s US$48 billion of backstops](https://www.sotkn.com/wire/alphabet-48b-data-center-backstops-wire/) covers the filing in detail.

## How do hyperscalers use build-to-suit?

The four biggest cloud spenders all report large leases that have been signed but not started. These are not all build-to-suit. They include colocation space, energy contracts and network links. But the size shows how much building is being done for them by others.

At 30 September 2026, Microsoft reported US$364.6 billion of leases, primarily for datacenters, that had not yet commenced, with some subject to certain contractual conditions being met. They start between fiscal 2027 and fiscal 2034\. Meta reported about US$355.73 billion of operating and finance leases not yet commenced, covering data centers, energy-related infrastructure, colocations and network infrastructure.

Amazon reported US$164.9 billion of leases not yet commenced. Of that, 69.6% falls due after 2030, by our arithmetic. Amazon’s commitments table also names the deal type directly: its other commitments include the expected payments for rent and tenant improvements on build-to-suit lease arrangements that are under construction.

Alphabet reported US$130.5 billion of leases not yet commenced, mostly for data centers and energy infrastructure, starting between 2026 and 2031\. It also made US$994 million of lease prepayments in the first nine months of 2026 for leases not yet commenced, which it expects to treat as finance leases.

Why would a company with this much cash lease rather than build? Our read: speed and spread. Leasing lets a cloud firm add capacity in many places at once while specialist developers handle land, permits and power. It also moves part of the cash spending onto someone else’s balance sheet until the building is handed over. Our [who are the hyperscalers](https://www.sotkn.com/explained/who-are-the-hyperscalers/) page and the Stack pages for [Microsoft](https://www.sotkn.com/stack/hyperscalers/what-does-microsoft-do/), [Meta](https://www.sotkn.com/stack/hyperscalers/what-does-meta-do/), [Amazon](https://www.sotkn.com/stack/hyperscalers/what-does-amazon-do/) and [Google](https://www.sotkn.com/stack/hyperscalers/what-does-google-do/) cover each firm’s model.

## Build-to-suit for neoclouds and AI tenants

Build-to-suit is not only for the giants. Developers also build for neoclouds, the newer firms that sell AI computing by the hour. Here the deal is the same, but the tenant is smaller and the risk is higher, and the filings show both sides.

Applied Digital is building for a top-rated tenant. Its quarterly report for the quarter to 31 August 2026 says it signed an approximately 15-year lease on 5 June 2026 with a high investment-grade hyperscaler for the full 210 MW of a single building under construction at its Delta Forge 2 campus. The company put the value at about US$5.2 billion over the base term, with delivery expected in the first half of 2028.

That works out to about US$347 million a year, or about US$1.65 million per megawatt per year, by our arithmetic, if payments were spread evenly. The real schedule is not public. What is clear is the wait: the lease was signed in June 2026 and the building is due in the first half of 2028.

Fermi shows what can go wrong. On 9 August 2026 its subsidiary signed a lease with a unit of TensorWave, an AI cloud provider, for a build-to-suit data center at Project Matador in Texas. Fermi’s press release the next day said the first phase covered 222 MW from the second half of 2027 and about US$6.5 billion over a 15-year initial term.

The lease had a closing date of 31 October 2026, which could have been pushed back to 31 December. It passed without an extension, and the lease ended on 10 November 2026, 93 days after it was signed, by our arithmetic. The same day, Fermi signed a non-binding letter of intent with an investment-grade hyperscaler for about 600 MW of powered land, backed by a US$200 million prepayment agreement and a US$15 million early construction and site development agreement. The letter is subject to negotiating and signing definitive documents.

Notice the swap. The megawatts went up, but the deal moved from a signed build-to-suit lease to a letter of intent for powered land, where the customer builds its own halls. Our read: the bigger buyer wanted the power, not the building. Our [Catalyst note on the Fermi lease](https://www.sotkn.com/catalyst/fermi-222-mw-lease-ends-200m-hyperscaler-prepayment/) and the Stack pages for [Fermi](https://www.sotkn.com/stack/ai-data-centers/what-does-fermi-america-do/), [TensorWave](https://www.sotkn.com/stack/neoclouds/what-does-tensorwave-do/) and [Applied Digital](https://www.sotkn.com/stack/ai-data-centers/what-does-applied-digital-do/) follow each side.

## When does a build-to-suit lease start paying?

At commencement. In most data center leases that means the day the building is finished, powered and handed over to the tenant. A signed lease is a promise to pay later. It is not cash today.

The gap can be long. Digital Realty, one of the largest data center landlords, reported that its new leases signed in the third quarter of 2026 had a weighted-average lag of 17 months between signing and contractual commencement. At 30 September 2026 it had US$2.5 billion a year of signed-but-not-commenced leases at 100% share, and US$1.8 billion at its own share.

Iron Mountain shows how much of a pipeline is spoken for before it is built. It defines pre-leased as a lease on data center capacity signed before construction has completed. At 30 September 2026 it had 317.1 MW in development, of which 197.3 MW, or 62.2%, was pre-leased. The other 119.8 MW had no tenant yet, by our arithmetic.

For a landlord, pre-leasing cuts the risk of building empty halls. For an investor, it means a large share of future income depends on finishing on time. Our [Markets note on Digital Realty’s signed-not-billed backlog](https://www.sotkn.com/markets/us/us-digital-realty-q3-signed-not-billed-october-2026/) and the Stack pages for [Digital Realty](https://www.sotkn.com/stack/ai-data-centers/what-does-digital-realty-do/) and [Iron Mountain](https://www.sotkn.com/stack/ai-data-centers/what-does-iron-mountain-do/) track that gap.

## How does build-to-suit show up in the accounts?

Mostly, it does not show up until the lease starts. Under US lease accounting, a tenant usually records a lease on its balance sheet at commencement. Before that, the lease sits in a footnote as a lease not yet commenced. That is why the trillion-dollar figures above are in the notes, not in the main tables.

There is an exception. If a tenant controls the building while it is being built, it may have to record the building as its own asset during construction. GDS Holdings, a Chinese data center operator, describes this in its 2025 annual report. It records an asset and a financing obligation for the estimated construction costs under build-to-suit lease arrangements where it controls the asset during construction.

After construction, GDS checks whether the deal counts as a sale and leaseback. If it does not, GDS stays the deemed owner of the building in its accounts, and the lease is treated more like a loan. The point for readers: the same building can look like a lease, a loan or an owned asset depending on who controls it during the build.

Our [finance lease vs operating lease](https://www.sotkn.com/explained/finance-lease-vs-operating-lease/) page covers how a commenced lease is booked, and [sale-leaseback explained](https://www.sotkn.com/explained/sale-leaseback-explained/) covers the deals where an owner sells a building and leases it back.

## Who gets paid in a build-to-suit deal, and when?

The money moves in a set order. Those who build get paid first. Those who own get paid last, and only if the building is handed over.

| Who                                  | When they get paid                                                          | What they risk                                                             |
| ------------------------------------ | --------------------------------------------------------------------------- | -------------------------------------------------------------------------- |
| **Builders and equipment suppliers** | During construction, as work is done and gear is delivered                  | Little once paid; the risk is delays and cancelled orders                  |
| **Construction lenders**             | Interest during the build; repaid or refinanced after handover              | That the building is late, or the tenant does not take it                  |
| **The developer or landlord**        | From lease commencement, for the length of the lease                        | Spending first and waiting; a tenant that walks before handover            |
| **The tenant**                       | Pays from commencement; earns when its own customers use the servers inside | Long payments on a building it may not need later; guarantees it has given |
| **A guarantor (if any)**             | Sometimes paid with fees, warrants or equity                                | Must pay if the tenant defaults, up to a stated maximum                    |

Our read, based on how the filings below describe each role. Terms differ deal by deal and most leases are not public.

This order explains a pattern in the filings. Builders and equipment makers can report strong sales during a building boom, even while landlords wait for leases to start. If a tenant walks away before handover, the builders have already been paid; the developer and its lenders carry the loss.

## Where is the stuck step?

The stuck step is handover: getting a finished building energised and accepted so that a signed lease can start.

Every number on this page points the same way. Applied Digital’s 210 MW building was signed in June 2026 and is due in the first half of 2028\. Meta’s two venture leases do not start until 2028 and 2029\. Microsoft’s unstarted leases begin as late as fiscal 2034\. Digital Realty’s new leases wait 17 months on average.

Power sets much of that clock. A building can be finished and still wait for a substation, a grid upgrade or a power-rate decision. Fermi’s new customer chose to take powered land and build itself, which suggests the power was the part it valued most.

Our read: in a build-to-suit deal, demand is signed early and paid late. The developer wins only if it can turn the signature into a powered, accepted building on time. That is the same gap our [contracted power explained](https://www.sotkn.com/explained/contracted-power-explained/) page tracks from the power side.

## How to read build-to-suit numbers

No company reports a single line called build-to-suit. The deal shows up in several numbers spread across tenants’ and landlords’ filings. Here is what to look for, with a dated example of each.

| Number to look for               | What it tells you                                                           | Example, as reported                                                                                     |
| -------------------------------- | --------------------------------------------------------------------------- | -------------------------------------------------------------------------------------------------------- |
| **Leases not yet commenced**     | Lease payments a tenant has signed for that have not started                | Microsoft US$364.6bn; Meta about US$355.73bn; Amazon US$164.9bn; Alphabet US$130.5bn, all at 30 Sep 2026 |
| **Pre-leased share**             | How much of what a landlord is building already has a tenant                | Iron Mountain 197.3 MW of 317.1 MW in development, 62.2%                                                 |
| **Signing-to-commencement lag**  | How long signed leases wait before they pay                                 | Digital Realty 17 months, new leases in Q3 2026                                                          |
| **Signed-not-commenced backlog** | The landlord’s queue of signed but unstarted payments                       | Digital Realty US$2.5bn a year at 100% share                                                             |
| **Guarantees and backstops**     | How much risk a tenant or parent has taken on for buildings it does not own | Meta US$41.5bn of maximum guarantees; Alphabet US$48.0bn of backstops                                    |
| **Expected delivery date**       | When the lease should start paying                                          | Applied Digital’s 210 MW Delta Forge 2 building: first half of 2028                                      |

Figures are as each company reports them. Definitions differ between companies, so compare a company with itself over time before comparing across companies.

The most useful pair is signed against started. When signed-but-unstarted leases grow much faster than started ones, the buildings are still to come. When starts catch up, cash catches up too.

## The clocks

- **Now.** Fermi’s letter of intent for about 600 MW of powered land is subject to negotiating and signing definitive documents; until then it is not a lease.
- **Early 2027\.** Meta, Alphabet, Microsoft and Amazon report year-end figures for unstarted leases, guarantees and backstops; Digital Realty and Iron Mountain report fourth-quarter signings and starts.
- **Second half of 2027\.** When the first phase of Fermi’s ended TensorWave building was due to start delivering.
- **First half of 2028\.** Expected delivery of Applied Digital’s 210 MW Delta Forge 2 building.
- **2028 and 2029\.** Meta’s leases with its Texas and Louisiana ventures commence.
- **Fiscal 2034\.** Latest start date for Microsoft’s leases not yet commenced at 30 September 2026.

## What would change the view?

- **The lag shortens.** If Digital Realty’s signing-to-commencement gap falls well below 17 months, buildings are being handed over faster and the stuck step is easing.
- **Unstarted leases stop growing.** If the hyperscalers’ leases not yet commenced flatten or fall while started leases rise, the build-to-suit wave is turning into paid occupancy.
- **More deals end before handover.** Another lease like Fermi’s TensorWave deal ending would show that signatures from smaller tenants are less firm than they look.
- **Guarantees get called.** Any payment under Meta’s residual value guarantees or Alphabet’s backstops would show the risk moving from landlords back to the cloud firms.

## Common misconceptions

- **People assume a signed build-to-suit lease means money now.** Actually, payments usually start only at commencement, after handover. Applied Digital’s June 2026 lease is due to deliver in the first half of 2028.
- **People assume the hyperscaler pays for the building.** Actually, the developer and its lenders usually pay first. The tenant pays over the life of the lease, though some, like Meta, now take a stake in the owner.
- **People assume build-to-suit and powered shell are the same.** Actually, a powered shell leaves the fit-out to the tenant. Build-to-suit delivers a finished building made to the tenant’s design.
- **People assume leases not on the balance sheet carry no risk.** Actually, unstarted leases, guarantees and backstops are real promises. Meta’s maximum exposure to its two ventures was US$68.4 billion at 30 September 2026.

## FAQ

**What is a build-to-suit data center?**  
It is a data center designed and built for one tenant that signs a long lease before construction starts. A developer pays for the land, power and building. The tenant starts paying when the finished, powered building is handed over.

**What does build-to-suit mean?**  
Build-to-suit means a landlord builds a property to one tenant’s exact needs, and the tenant agrees to lease it before it is built. In data centers the needs are mostly about power, cooling and floor loads, set by the tenant’s own design.

**What is the difference between build-to-suit and a powered shell?**  
In a build-to-suit deal the landlord delivers a finished building made to the tenant’s design. In a powered shell the landlord delivers the land, the building and the grid connection, and the tenant fits out the inside itself. A turnkey hall goes one step further and is ready to plug in.

**Who pays to build a build-to-suit data center?**  
The developer or landlord pays first, usually with equity and construction loans. Some hyperscalers now share the bill. Meta holds 20% of two ventures building campuses in Louisiana and Texas, with total estimated development costs of about US$27 billion and US$14 billion.

**When does a build-to-suit lease start paying?**  
At commencement, which is usually when the building is finished, powered and handed over. Digital Realty’s new leases in the third quarter of 2026 had a weighted-average 17-month wait between signing and commencement.

**What happens if the tenant walks away before the building is finished?**  
It depends on the contract. Fermi’s 222 MW build-to-suit lease with TensorWave ended on 10 November 2026 after a closing date passed, about three months after signing. Some tenants offer guarantees: Meta has given residual value guarantees to its two data center ventures.

**What is a residual value guarantee?**  
It is a promise by a tenant to cover a shortfall in the value of a building if the tenant leaves at the end of a lease. Meta’s maximum residual value guarantees to its two data center ventures were US$41.5 billion at 30 September 2026.

**Is build-to-suit the same as a hyperscale data center?**  
Not quite. Hyperscale describes the size and the tenant. Build-to-suit describes the deal. Many hyperscale data centers are built-to-suit for one cloud company, but a hyperscaler can also build and own its halls itself, or lease space in a shared colocation building.

Related: [leases not yet commenced explained](https://www.sotkn.com/explained/leases-not-yet-commenced-explained/); [data center lease explained](https://www.sotkn.com/explained/data-center-lease-explained/); [who builds AI data centers](https://www.sotkn.com/explained/who-builds-ai-data-centers/); [prepayment explained](https://www.sotkn.com/explained/prepayment-explained/); [bridge facility explained](https://www.sotkn.com/explained/bridge-facility-explained/); [neocloud explained](https://www.sotkn.com/explained/neocloud-explained/).

## Stack doors

Layer: [Hyperscalers](https://www.sotkn.com/stack/hyperscalers/). Landlords and developers sit in [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/). For the tenant side of the trillion-dollar footnote, see our Wire on [Meta’s US$356 billion of unstarted leases](https://www.sotkn.com/wire/meta-356b-data-center-leases-not-started-wire/), and for a developer waiting on a power decision, our Markets note on [Applied Digital’s Louisiana bridge loan](https://www.sotkn.com/markets/us/us-applied-digital-delta-forge-bridge-loan-louisiana-november-2026/).

[Get the Wire](https://www.sotkn.com/#/portal/signup) — short daily notes on where AI computing gets built and who pays for it.

Not investment advice. Do your own research.

**How we check this**

Meta, Alphabet, Microsoft and Amazon figures come from their quarterly reports on Form 10-Q for the quarter to 30 September 2026, filed with the US Securities and Exchange Commission between 22 and 30 October 2026\. Applied Digital figures come from its Form 10-Q filed on 7 October 2026\. Fermi figures come from its press release of 10 August 2026 and its Form 10-Q filed on 12 November 2026\. Digital Realty figures come from its third-quarter results filed on 29 October 2026, and Iron Mountain figures from its third-quarter supplemental report of 5 November 2026\. The accounting example comes from GDS Holdings’ annual report filed on 29 April 2026\. All were read again on 28 November 2026\. Each company defines its terms in its own way, so we quote each as reported and say whose measure it is. Maximum guarantee and backstop amounts are the companies’ own worst-case figures, not expected losses. Every share, ratio and per-year figure not quoted from a source is our arithmetic, checked in code. Who gets paid and the stuck step are our read, labelled as such. We do not name the parties behind private leases unless a filing names them. The featured image is a CC0 photograph of a steel frame under construction, with a grade added by us; it is illustrative and not tied to any company named here. This page explains how build-to-suit data center deals work. It does not rate any company as an investment or give buy or sell calls. Not investment advice. Do your own research.

**Last reviewed:** 28 Nov 2026 · **Next review:** after Meta, Alphabet, Microsoft and Amazon file their 2026 annual reports (early 2027), or when Fermi signs a definitive lease at Project Matador

Spot an error? [Tell us](mailto:sean@thekopinotes.com) and we will correct it and note the change here.

[Our editorial standards →](https://www.sotkn.com/editorial-standards/)

## References

1. [Meta Platforms — Form 10-Q for the quarter ended 30 September 2026 (filed 22 Oct 2026)](https://www.sec.gov/Archives/edgar/data/1326801/000162828026066773/meta-20260930.htm?ref=sotkn.com) — Louisiana venture (October 2025) and Texas venture (July 2026), 20% each; about US$27bn and US$14bn estimated development costs; leases start 2029 and 2028, four-year initial terms, up to 20 years with renewals; residual value guarantees; maximum exposure US$68.4bn incl. US$41.5bn of guarantees; leases not yet commenced about US$355.73bn
2. [Alphabet — Form 10-Q for the quarter ended 30 September 2026 (filed 29 Oct 2026)](https://www.sec.gov/Archives/edgar/data/1652044/000165204426000084/goog-20260930.htm?ref=sotkn.com) — Backstops of data center lease payments and energy costs for third parties, booked as credit derivatives: notional US$48.0bn vs US$16.9bn at 31 Dec 2025; terms up to 15 years; right to take over or sublease on default; US$10.0bn potential backstops tied to the Crux AI joint venture; leases not yet commenced US$130.5bn
3. [Amazon — Form 10-Q for the quarter ended 30 September 2026 (filed 30 Oct 2026)](https://www.sec.gov/Archives/edgar/data/1018724/000101872426000040/amzn-20260930.htm?ref=sotkn.com) — Commitments table: leases not yet commenced US$164.9bn by year; other commitments include payments for rent and tenant improvements on build-to-suit lease arrangements under construction
4. [Microsoft — Form 10-Q for the quarter ended 30 September 2026 (filed 28 Oct 2026)](https://www.sec.gov/Archives/edgar/data/789019/000119312526436133/msft-20260930.htm?ref=sotkn.com) — Leases not yet commenced, primarily datacenters, US$364.6bn, some subject to contractual conditions, starting fiscal 2027 to fiscal 2034, terms 1 to 20 years
5. [Applied Digital — Form 10-Q for the quarter ended 31 August 2026 (filed 7 Oct 2026)](https://www.sec.gov/Archives/edgar/data/1144879/000114487926000059/apld-20260831.htm?ref=sotkn.com) — About 15-year lease signed 5 June 2026 with a high investment-grade hyperscaler for a single 210 MW building under construction at Delta Forge 2, about US$5.2bn over the base term, delivery expected in the first half of 2028; ready-for-service timing at other campuses
6. [Fermi — Fermi Announces Binding Lease Agreement with TensorWave, press release (10 Aug 2026)](https://investor.fermiamerica.com/fermi-announces-binding-lease-agreement-with-tensorwave?ref=sotkn.com) — First binding lease at Project Matador: 222 MW turnkey data center for TensorWave from the second half of 2027, about US$6.5bn over a 15-year initial term
7. [Fermi — Form 10-Q for the quarter ended 30 September 2026 (filed 12 Nov 2026)](https://www.sec.gov/Archives/edgar/data/2071778/000207177826000058/frmi-20260930.htm?ref=sotkn.com) — TensorWave build-to-suit lease (signed 9 Aug 2026) ended 10 Nov 2026 after the 31 Oct closing date passed without extension; non-binding letter of intent for about 600 MW of powered land with an investment-grade hyperscaler, US$200m prepayment and US$15m early construction agreement
8. [Digital Realty — Third quarter 2026 results, Form 8-K Exhibit 99.1 (29 Oct 2026)](https://www.sec.gov/Archives/edgar/data/1297996/000110465926120212/dlr-ex99d1.htm?ref=sotkn.com) — Weighted-average 17-month lag between new leases signed in the quarter and contractual commencement; signed-but-not-commenced backlog US$2.5bn at 100% share, US$1.8bn at its share
9. [Iron Mountain — Supplemental Financial Information, third quarter 2026 (5 Nov 2026)](https://s204.q4cdn.com/148941814/files/content%5Ffiles/Q3-2026-SRP-vFinal.pdf?ref=sotkn.com) — Total development 317.1 MW, of which 197.3 MW (62.2%) pre-leased; pre-leased defined as a lease signed before construction has completed; project table with expected completion dates
10. [GDS Holdings — Annual report on Form 20-F for 2025 (filed 29 Apr 2026)](https://www.sec.gov/Archives/edgar/data/1526125/000110465926051006/gds-20251231x20f.htm?ref=sotkn.com) — Accounting policy for build-to-suit lease arrangements: asset and financing obligation recorded during construction where the company controls the asset; deemed owner if a sale-leaseback test fails

S

**[Sean](https://www.sotkn.com/author/sean/)**

Writes Second Order by TKN — a plain-English map of AI infrastructure and semiconductors for non-specialist investors. Focus: who gets paid, where money sticks, and which step is stuck.

Covers AI infrastructure, semiconductors, and second-order stack reads.

[Author page →](https://www.sotkn.com/author/sean/) · [Editorial standards →](https://www.sotkn.com/editorial-standards/)