# What Is an OSAT? How Outsourced Assembly and Test Gets Paid
- URL: https://www.sotkn.com/explained/osat-explained/
- Published: 2026-11-24T01:20:41.000Z
- Updated: 2026-11-24T01:20:41.000Z
- Description: An OSAT packages and tests chips it does not print. The die stays the customer's, and the bill is the package and the test.
- Author: Sean
- Tags: #desk-explained, Mechanism

EXPLAINED · Mechanism · Last reviewed: 24 Nov 2026 · Next review: after ASE and Amkor report fourth-quarter 2026 results

An OSAT, short for outsourced semiconductor assembly and test, is a factory that packages and tests chips another company has already printed. It is paid for that service. In the ordinary case it does not own the silicon.

A bare die cannot be soldered down, so the designer's sale waits on the package and the test. The OSAT's own sale is only the service fee. That fee can come from a full factory that still has almost no order book, because the contracts are short. The 2026 exception is the leading-edge slice: ASE says demand still outruns the lines it can turn on.

## What is an OSAT?

An OSAT does the back end of chipmaking. Amkor's annual report for 2025 describes the company as the world's largest U.S.-headquartered outsourced semiconductor assembly and test provider. It lists the path as design, wafer fabrication, wafer probe, packaging, and final test, and it says its own work comes after the wafer is made.

ASE's audited 2025 report shows why the holding-company total is the wrong number. Packaging brought in US$9,829.2 million. Testing brought in US$2,292.0 million. Electronic manufacturing, through USI, brought in US$8,198.7 million and was still 39.9 percent of operating revenue. Packaging plus testing is US$12,121.2 million. That sum is our arithmetic. The assembly-and-test step is the OSAT. The EMS arm builds modules. It is a different bill.

Amkor's customers are a short list. For the year ended 31 December 2025, its ten largest customers were 72 percent of net sales. Apple was 29.8 percent and Qualcomm was 11.1 percent. Those shares are the filing's.

## Where does an OSAT sit after the wafer?

A [tape-out](https://www.sotkn.com/explained/tape-out-explained/) sends a design to a foundry. A [fabless](https://www.sotkn.com/explained/fabless-explained/) company does not own that foundry. The package house sees the die only after the wafer exists.

| Step      | What happens                                    | Who gets paid                            | What they do not own                               |
| --------- | ----------------------------------------------- | ---------------------------------------- | -------------------------------------------------- |
| Print     | The foundry makes the wafer                     | The foundry, for the wafer               | The package                                        |
| Hand-over | The wafer is consigned to the OSAT              | Nobody, at this step                     | Title to the die                                   |
| Package   | The die is bumped, set down, and sealed         | The OSAT packaging line, for the service | The silicon                                        |
| Test      | The part is screened and bad units are pulled   | The OSAT test line, for the service      | Sometimes the tester, if the customer consigned it |
| Ship      | A finished part goes to the designer's customer | The designer, last                       | —                                                  |

Who is paid at each step is our read of the filings below.

[TSMC](https://www.sotkn.com/stack/semiconductors/cowos/what-does-tsmc-do/) can keep the advanced join. CoWoS is its name for attaching a compute die to memory. On 4 October 2024 TSMC and Amkor said TSMC would contract turnkey packaging and test, including InFO and CoWoS, from Amkor's planned Peoria plant. That is a contract for a factory, not a 2026 invoice. Amkor's report for the quarter ended 30 September 2026 still calls the Arizona facility a construction project.

## Why does the die stay the customer's?

Because the expensive part is consigned.

ASE's 2025 annual report says the silicon die is typically the most costly part of the package, and that its cost is usually absent from ASE's costs and revenues, because customers supply it. Amkor's report says the wafer is generally consigned, title stays with the customer, and Amkor buys the laminate, leadframe, capacitors, and bond wire instead. Unused materials bought to a forecast generally sit with the customer. That board is a separate sale, on our [IC substrates](https://www.sotkn.com/explained/who-makes-ic-substrates/) page.

A higher wafer price does not, by itself, become a higher OSAT invoice. ASE's unaudited third-quarter 2026 release shows the split. In the assembly-and-test arm, raw materials were 27 percent of that arm's net revenue. In the EMS arm, raw materials were 82 percent. The EMS business is mostly a parts invoice. The OSAT business is mostly the work, and the customer's die is not inside that 27 percent.

## Who gets paid — and where is the stuck step?

Two clocks run at once. One is short. One is stuck on buildings and tools.

On the short clock, Amkor's quarterly report says packaging and test does not typically operate with any material backlog. A quarter's sales depend on that quarter's demand, customers generally do not commit far ahead, and a large share of cost is fixed. Third-quarter 2026 net sales were US$1,990.6 million, up 0.2 percent from a year earlier. Computing, and automotive and industrial, each grew 37 percent. Communications fell 28 percent, to 37 percent of the quarter from 51 percent. Computing rose to 26 percent from 19 percent. Advanced products were US$1,631.6 million, 82.0 percent of the quarter. That share is our arithmetic. The first nine months were US$5,573.2 million, up 15.6 percent, the filing's own figure. Fourth-quarter guidance on 26 October 2026 was US$1.9 billion to US$2.0 billion of sales. That is an outlook, not a result. 2026 capital spending was put at about US$2.5 billion, mainly for Arizona.

On the stuck clock, ASE's leading-edge work, which it calls LEAP, is the bind. In the third quarter of 2026 its assembly-and-test capacities ran at or near full utilization. Management said demand still outpaced supply, in LEAP and in much of the rest of that arm. Revenue grew faster than expected, mainly because high-demand LEAP tools were installed sooner than planned.

The LEAP dollars are what management said. They are not an income-statement line. On 5 February 2026 ASE said LEAP reached US$1.6 billion in 2025, 13 percent of assembly-and-test revenue, up from US$0.6 billion in 2024\. On 29 October 2026 the finance chief raised 2026 LEAP from the US$3.7 billion mentioned the quarter before to over US$4 billion. That is more than two and a half times the 2025 print, our arithmetic, using US$4 billion as the floor. He still expects LEAP revenue to double in 2027\. That is an expectation.

Asked about full-process CoWoS, he answered in revenue. Full-process revenue was on track at US$300 million for 2026, and he expects over US$1 billion in 2027\. He said the yield allows mass production. He did not give the yield. US$300 million is under 8 percent of a LEAP book above US$4 billion. That share is our arithmetic on the floor he stated. He said the larger demand is still on-substrate work, with test strong too, and that construction cannot catch it.

Space is part of the bind. He said suitable plants to buy are scarce, and he raised 2026 capital spending from US$10.5 billion to US$11.5 billion. Of the extra US$1 billion, half is for facilities and half for equipment, and he said 60 percent would go to LEAP and 40 percent to mainstream advanced packaging. Assembly-and-test equipment spending was already US$2,063 million in the quarter, against US$736 million a year earlier.

## Why can the line be full and the book still be short?

Utilization and backlog are different facts.

Amkor's quarterly report repeats it in the risk factors. There is no material backlog. Customers can delay, shrink, or cancel. Its ten largest customers were 66 percent of third-quarter 2026 net sales, down from 73 percent a year earlier. The list is still short. It is not a booked queue. A busy quarter is not a multi-year order.

ASE's fullness is a loading statement, not a dollar backlog. Management can say the lines are full and, in the same quarter, say it still cannot catch demand. Both describe capacity. Neither is a signed book.

Arizona is the same clock in years. Construction began in the second half of 2025\. By 30 September 2026 Amkor had incurred US$553.3 million, including US$8.5 million of capitalized interest. The 2025 annual report expected manufacturing in the first half of 2028, and the later quarterly report does not pull that date forward. A December 2024 CHIPS Act award is up to US$407 million. "Up to" is a ceiling, not cash received. Until the plant runs, the 2024 agreement with TSMC is not a fee.

## How do packaging and test split the bill?

Packaging is the larger revenue. Test is often the richer margin, and the tool takes longer to arrive.

In ASE's audited 2025 figures, packaging gross margin was 22.1 percent and testing gross margin was 31.0 percent, a gap of 8.9 points, our arithmetic. Testing revenue grew 31.8 percent that year and packaging 17.8 percent, which the company tied to leading-edge work and to test.

In the third quarter of 2026, bumping, flip chip, wafer-level packaging, and system-in-package were 51 percent of that arm. Wirebonding was 24 percent, against 26 percent a year earlier. Testing was 17 percent. Testers in service were 8,831, against 7,066, about 25 percent more. Wirebonders were 24,801, against 25,120\. Those comparisons are our arithmetic. ASE is adding graders for advanced packages, not classic wirebond tools.

Amkor's 2025 annual report says test equipment is generally more capital-intensive than packaging equipment, and that testers tend to have longer delivery times. Sometimes the customer consigns the tester, so the test fee is not always earned on the OSAT's own machine. An interim test also pulls bad chips before they are packaged, which is the back-end view of [semiconductor yield](https://www.sotkn.com/explained/semiconductor-yield-explained/). Who sells the testers is on [who tests AI chips](https://www.sotkn.com/explained/who-tests-ai-chips/).

The profit sticks in assembly and test, not in the group average. ASE's third-quarter assembly-and-test gross margin was 30.6 percent. On the call, that arm was 62 percent of holding-company revenue and 91 percent of operating profit. On the EMS lines of the same release, cost of revenues was NT$85,676 million against net revenues of NT$93,469 million, a gross margin of about 8.3 percent. The 8.3 percent is our arithmetic. Amkor, without an EMS arm of that size, reported a company gross margin of 18.3 percent, with packaging at 88 percent of sales and test at 12 percent.

## Common misconceptions

People assume every AI package fee is an OSAT fee. TSMC still runs its own [CoWoS](https://www.sotkn.com/explained/cowos-explained/). The Peoria contract was still a construction project on 30 September 2026, and ASE's 2026 full-process revenue was the US$300 million named on the call.

People assume the invoice includes the chip. Both annual reports say the die is generally consigned and stays off OSAT sales.

People assume a full factory is a long order book. Amkor says there is typically no material backlog. ASE's fullness is utilization, plus demand it says it cannot yet supply.

People read the group total as packaging. Packaging was NT$122,173 million of third-quarter net revenue of NT$244,161 million, or 50 percent. EMS was NT$92,997 million, or 38 percent. Testing was NT$26,302 million, or 11 percent. Those shares are our arithmetic. Operating profit, on the call, sat in assembly and test.

## FAQ

### What is an OSAT?

An OSAT is an outsourced semiconductor assembly and test provider. It packages and tests chips after someone else has printed the wafer, and it is paid for that service.

### Does an OSAT own the chip it packages?

No. Both annual reports say the wafer is generally consigned, and the silicon stays off the OSAT's revenue. Amkor says title stays with the customer.

### What is the difference between an OSAT and a foundry?

A foundry prints the wafer. An OSAT packages and tests the die afterwards. An OSAT fee starts only when that later work is contracted out.

### Is CoWoS an OSAT service?

CoWoS is TSMC's packaging family, and TSMC runs it. ASE put full-process revenue at US$300 million for 2026\. Amkor's Arizona plant, the one tied to a CoWoS and InFO contract, was still under construction at 30 September 2026.

### Why can an OSAT line be full with no backlog?

A busy factory is not a signed queue. Amkor says customers can cancel and that it typically has no material backlog. ASE's full lines are a utilization statement, not a dollar book.

### Why is ASE's test margin higher than its packaging margin?

In the audited 2025 figures, testing gross margin was 31.0 percent and packaging gross margin was 22.1 percent. The tester is costly, and the customer sometimes consigns it.

### When will Amkor package chips in Arizona?

The 2025 annual report expected a start in the first half of 2028\. The 30 September 2026 report still calls the plant a construction project, with US$553.3 million incurred.

## Related terms

[Hybrid bonding](https://www.sotkn.com/explained/hybrid-bonding-explained/) is the copper-to-copper attach Amkor lists among its development areas, not a 2025 sales line. CoWoS is the foundry join an accelerator still has to clear. IC substrates are the boards the OSAT buys. Tester makers, yield, tape-out, and the fabless hand-off are the steps on either side of this fee.

## Markets and stack doors

The step lives in the [Semiconductors](https://www.sotkn.com/stack/semiconductors/) layer. ASE's loading sits on the [Taiwan](https://www.sotkn.com/markets/taiwan/) door. Amkor's customer list and the Arizona plant sit on the [US](https://www.sotkn.com/markets/us/) door. One level down: [what ASE does](https://www.sotkn.com/stack/semiconductors/what-does-ase-do/) and [what Amkor does](https://www.sotkn.com/stack/semiconductors/cowos/what-does-amkor-do/).

## How we check this

Figures come from company filings and earnings calls, each dated in the list below. Quarterly figures are unaudited, as the companies say. LEAP revenue, full-process revenue, and timing stated on a call are labelled as what management said, not as audited lines. Where we work something out ourselves, the arithmetic is shown in full. This page is education, not investment advice.

**Last reviewed:** 24 Nov 2026 · **Next review:** after ASE and Amkor report fourth-quarter 2026 results

Spot an error? Use our [editorial standards](https://www.sotkn.com/editorial-standards/). [Sean](https://www.sotkn.com/author/sean/) covers AI infrastructure, semiconductors, and second-order stack reads.

## Sources

1. Amkor, Form 10-K for the year ended 31 December 2025\. [SEC filing](https://www.sec.gov/Archives/edgar/data/1047127/000104712726000014/amkr-20251231.htm?ref=sotkn.com). Consignment, customer concentration, test equipment, Arizona timing.
2. Amkor, Form 10-Q for the quarter ended 30 September 2026\. [Company 10-Q](https://ir.amkor.com/static-files/a4cb594b-31ef-45b7-aa3b-10edf1b0c40c?ref=sotkn.com). Net sales, no material backlog, Arizona costs, CHIPS award.
3. Amkor, results release, 26 October 2026\. [Press release](https://ir.amkor.com/news-releases/news-release-details/amkor-technology-reports-financial-results-third-quarter-2026?ref=sotkn.com). Mix, test split, fourth-quarter outlook.
4. ASE, Form 20-F for the year ended 31 December 2025, filed 1 April 2026\. [SEC filing](https://www.sec.gov/Archives/edgar/data/1122411/000119312526135585/d50802d20f.htm?ref=sotkn.com). Segment revenue, margins, consignment.
5. ASE, Form 6-K, 29 October 2026\. [SEC filing](https://www.sec.gov/Archives/edgar/data/1122411/000095010326016324/dp255760%5F6k.htm?ref=sotkn.com). Unaudited quarter, mix, tool counts, materials share.
6. ASE, earnings conference, 29 October 2026\. [Company transcript](https://media-aseholdco.todayir.com/20261102120005848469499%5Fen.pdf?ref=sotkn.com). LEAP, full process, capital spending.
7. ASE, earnings conference, 5 February 2026\. [Company transcript](https://media-aseholdco.todayir.com/20260206170733832166573%5Fen.pdf?ref=sotkn.com). 2025 LEAP of US$1.6 billion.
8. TSMC and Amkor, 4 October 2024\. [Joint release](https://pr.tsmc.com/english/news/3174?ref=sotkn.com). Peoria turnkey packaging, including InFO and CoWoS.