# Capex Review Done, Power Still Late: Who Gets Paid While NEXTDC’s M3 Waits for Jemena’s 66kV Line
- URL: https://www.sotkn.com/markets/australia/australia-nextdc-agm-m3-66kv-power-november-2026/
- Published: 2026-11-22T02:42:04.000Z
- Updated: 2026-11-22T02:42:04.000Z
- Description: At its 20 November AGM, NEXTDC kept FY27 spending at A$4.5–5.0 billion, lifted guidance outside M3 and named six sites on hold. Jemena now expects to finish the 66kV line to M3 in June–August 2027. That line is the stuck step.
- Author: Sean
- Tags: #market-australia, Markets, #layer-ai-data-centers, #layer-power-energy

*NEXTDC is Australia’s biggest listed data centre builder. On 20 November it held its yearly meeting. It said its review of spending was done, nudged its profit guidance up, and named the sites it has put on ice. The date that matters most came from someone else. Jemena, the local power network, now expects to finish the 66kV line to NEXTDC’s M3 hall in June to August 2027\. Until then the extra power waits. That line is the stuck step.*

**AUSTRALIA PULSE** · AI DATA CENTERS · POWER · Data as at 22 Nov 2026 (NEXTDC ASX releases and AGM of 20 Nov 2026; press reports of 20 Nov) · Next update: NEXTDC’s half-year result in February 2027, or earlier news on Jemena’s works  
**Affects:** [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/) · [NEXTDC](https://www.sotkn.com/stack/ai-data-centers/what-does-nextdc-do/) — Markets: [Australia](https://www.sotkn.com/markets/australia/) · [Malaysia](https://www.sotkn.com/markets/malaysia/)

**In short:** At its 20 November AGM, NEXTDC kept FY27 spending at A$4.5–5.0 billion after a project-by-project review, and named six uncontracted sites that stay on hold. It lifted FY27 guidance a little, still without the affected M3 contracts (about A$140 million a year). The slides gave Jemena’s dates: earliest restart February 2027, 66kV works done June–August 2027\. Stuck step: Jemena’s 66kV line to M3\. Map of who gets paid — not a buy list.

Education only, not advice to buy or sell any security. Money is in Australian dollars. NEXTDC’s financial year ends on 30 June, so FY27 runs from July 2026 to June 2027\. A megawatt (MW) is a measure of how much power a hall can feed to servers. A 66kV line is a mid-sized power line, 66,000 volts, that carries power from a bigger grid point to a local site. Net revenue is NEXTDC’s revenue after direct costs such as power. Our earlier notes covered the M3 delay itself ([the West Footscray power delay](https://www.sotkn.com/markets/australia/australia-nextdc-melbourne-power-delay-october-2026/)), the guidance cut that followed ([A$140 million off the year](https://www.sotkn.com/markets/australia/australia-nextdc-fy27-guidance-cut-october-2026/)) and the share raid by two rivals ([the Goodman and Digital Realty stake](https://www.sotkn.com/markets/australia/australia-nextdc-goodman-digital-realty-raid-november-2026/)). This note covers what the AGM added.

### The numbers that matter this week

FY27 capital spending

A$4.5–5.0bn

Reaffirmed 20 Nov after review

Held

FY27 net revenue guide

A$485–500m

Bottom end +A$10m · ex-M3

Up a little

FY27 underlying EBITDA guide

A$260–275m

+A$12.5m at mid-point · ex-M3

Up a little

M3 contracts outside guide

\~A$140m

Each of net revenue and EBITDA

Waits

Jemena 66kV works done

Jun–Aug 2027

Earliest restart Feb 2027

Late

The gate

66kV line

Power to M3 runs through Jemena

Stuck step

NEXTDC ASX releases and AGM slides, 20 Nov 2026\. Jemena dates as advised to NEXTDC. Status chips are Second Order’s read.

**On this page:** [Why it matters](#why-it-matters) · [What happened](#what-happened) · [Guidance](#guidance) · [The review](#the-review) · [M3 dates](#m3-dates) · [The money](#the-money) · [Our math](#our-math) · [Who gets paid](#money-goes) · [The vote](#the-vote) · [What is stuck?](#still-stuck) · [Dates next](#dates) · [FAQ](#faq)

## Why does one power line matter so much?

Picture a shop that has sold out its next season. The customer has signed. The shelves are going up. But the delivery road to the shop is half built, and the road crew has stopped work. The shop can keep building shelves. It cannot sell what is on them until the road opens.

That is M3, NEXTDC’s big campus in West Footscray, in Melbourne’s inner west. The customer has signed. Construction goes on. But the extra power has to come down new poles and wires that Jemena, the local network company, must build. Jemena stopped part of that work in September after residents objected to the size of the new poles. No new line, no new power. No new power, no new billing on that part of M3.

On 21 October NEXTDC took about A$140 million of net revenue and the same of underlying EBITDA out of its FY27 guidance because of this. It promised a full review of its spending by the AGM. On 20 November it delivered that review, and its slides put Jemena’s timing on one page. The review changed little. The timing is the news.

So the useful questions are simple. What did NEXTDC actually say? Who keeps getting paid while M3 waits? And what has to happen for the line to be finished?

## What happened on 20 November?

NEXTDC lodged three documents with the ASX before its meeting in Sydney: a guidance upgrade, the chairman and CEO’s speeches, and the slides. After the meeting it lodged the vote results. In short:

- FY27 capital spending stays at A$4.5 to A$5.0 billion, the range set on 21 October, now confirmed by a project-by-project review.
- FY27 net revenue guidance moves to A$485–500 million (from A$475–500 million) and underlying EBITDA to A$260–275 million (from A$245–265 million).
- Both ranges still leave out the affected M3 contracts, including the part already billing, and any service credits owed on them.
- Six uncontracted sites stay on hold: M4, M5, S5, S7, GC1 and AK1, plus any new land buying.
- Jemena’s advised dates: February 2027 is the earliest restart of its suspended works; June to August 2027 is its current expectation for finishing its 66kV works.
- The planning decision for M3 Stages 6 and 7 is not expected before the first quarter of 2027, after the 28 November Victorian election.
- NEXTDC says it does not expect to raise capital from shareholders at this time to deliver its contracted capacity.
- Shareholders voted 72.06% against the pay report, a second strike in a row, and 96.21% against spilling the board.

The market did not cheer. Reuters reported that NEXTDC shares closed 7.1% lower at A$9.01 on 20 November, their weakest session since 23 October. The wider technology index fell 4.7% the same day, so not all of that move was about NEXTDC.

The chairman, Douglas Flynn, used his last AGM to put the blame on the network company. “This is an issue of execution by a local monopoly electricity supplier,” he said, according to The Sydney Morning Herald. He said Jemena knew it had made a mistake. Jemena declined to comment. The CEO, Craig Scroggie, took a different line in his speech: “As CEO, I am accountable for delivery.”

## What changed in the guidance, and what did not?

![Chart: NEXTDC FY27 guidance mid-points in Australian dollars: net revenue 627.5 million in August, 487.5 million in October, 492.5 million in November; underlying EBITDA 397.5 million, 255 million, 267.5 million](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/australia-nextdc-agm-m3-66kv-power-november-2026-print.png)

Guidance nudged up; the M3 contracts are still outside it. · Education only.

NEXTDC has now given three sets of FY27 guidance in under three months. The first, on 27 August, included the M3 contracts. The second, on 21 October, took them out. The third, on 20 November, keeps them out but lifts the rest a little.

Net revenue, FY27

27 Aug 2026 (with M3)A$615–640m

21 Oct 2026 (without M3)A$475–500m

20 Nov 2026 (without M3)A$485–500m

FY26 actualA$405.0m

Underlying EBITDA, FY27

27 Aug 2026 (with M3)A$385–410m

21 Oct 2026 (without M3)A$245–265m

20 Nov 2026 (without M3)A$260–275m

FY26 actualA$248.8m

Capital spending, FY27

27 Aug 2026A$5,250–5,750m (no capitalised interest)

21 Oct 2026A$4,500–5,000m

20 Nov 2026A$4,500–5,000m (reaffirmed)

Like-for-like cut vs Augustabout A$980m, 17–19%

NEXTDC, FY27 Guidance Upgrade, 20 Nov 2026\. The October and November capital ranges include about A$230m of capitalised interest and about A$500m of customer fit-out that is paid back.

Why the lift? NEXTDC gives two reasons. Sales and revenue outside M3 are strong, and it is more confident about when other customers will move in. And it has cut running costs by focusing spending on getting capacity to customers. At the mid-point, net revenue guidance is 22% above FY26 and EBITDA guidance is 8% above, in the company’s own sums, even without M3.

What did not change is the hole. The M3 contracts carried about A$140 million of each of net revenue and EBITDA in the August plan. They are still outside the range, because NEXTDC says it cannot yet reliably estimate what they will bring in this year. And there is a catch in the small print: if service credits become payable to the M3 customer, EBITDA could fall below the new range. A service credit is money a data centre owes a customer when it misses an agreed standard.

So the guidance tells you the rest of the business is doing what it said. It does not tell you when M3 gets its power. For the difference between a contract signed and a contract billing, see [leases not yet commenced, explained](https://www.sotkn.com/explained/leases-not-yet-commenced-explained/), and our earlier read on [what NEXTDC’s price assumes about signed-not-billing capacity](https://www.sotkn.com/analysis/nextdc-signed-not-billing-stuck-step-what-price-assumes/).

## What did the spending review decide?

On 21 October NEXTDC promised a detailed review of its capital spending, to be announced by the AGM. It kept that promise. The review went project by project, for FY27 and beyond. Its answer for FY27 was: no change. The October range had already stripped out most optional spending, so what was left was mainly money for halls customers have already signed.

Here is where the money goes, in NEXTDC’s words. Most FY27 spending is on existing customer contracts at four sites: S4 in Western Sydney, M2 and M3 in Melbourne, and KL1 in Kuala Lumpur. Together those contracts are about 600 MW of contracted use, on a pro forma basis at 30 June 2026.

The review also set rules for the future. These matter more than the FY27 number, because they say when the paused sites can restart. NEXTDC will commit new money to a project only when four things are true at once:

- There are customer contracts in place.
- The expected returns are above NEXTDC’s cost of capital.
- Power and planning are sufficiently advanced, after talking with government and the local community.
- The funding is in place.

Look at the third rule. Power and planning are now an entry ticket, not something to sort out later. That is the lesson of M3 written into company policy. It means the six paused sites, M4, M5, S5, S7, GC1 and AK1, wait not just for customers but for power and approvals that are well along.

Two smaller points from the review. NEXTDC is still looking at bringing in a partner for its S4 Sydney campus through a joint venture, which would share the cost. And on site sales, the October release said the board would look at selling development sites it does not need. The November release narrows that: apart from sites near homes that it no longer plans to develop, sales are not expected in the near term, and no decision has been made.

That last point links to a wider change. Flynn told the meeting that NEXTDC does not intend to pursue new development opportunities near homes. Asked whether it would buy the M3 site again, he said no, according to The Sydney Morning Herald. The same pressure is showing up across Australia, from council benefit rules in Wagga Wagga ([the 1.5% community benefit policy](https://www.sotkn.com/markets/australia/australia-wagga-wagga-data-centre-community-benefit-policy-november-2026/)) to hundreds of objections at Kurri Kurri ([AirTrunk’s wind and power clock](https://www.sotkn.com/markets/australia/australia-airtrunk-kurri-kurri-wind-2032-november-2026/)).

## What are the new dates for M3’s power?

This is the part that matters most for when M3 earns again. The AGM slides set out the next steps, with the timing that Jemena has advised NEXTDC. The status is as at 20 November 2026, and every date depends on third parties: Jemena, the local council and the Victorian government.

Jemena’s 66kV works

Earliest restart of suspended worksFebruary 2027

Current expectation for finishingJune–August 2027

Who leads consultationJemena, once its solution is final

SourceNEXTDC AGM slides, 20 Nov

M3 Stages 6 and 7

Planning decisionnot before Q1 2027

Whyprocess resumes after Victorian election

Election date28 November 2026

Decision makerVictorian government

Later power steps

Depend onnew transformers at Brooklyn Terminal Station

First of those projectsnow later than expected

Affects FY27 guidance?no, per NEXTDC

Affectscapacity billing after FY28

NEXTDC 2026 AGM presentation, slide “M3 action plan in progress”, 20 Nov 2026\. Dates as advised by Jemena to NEXTDC; not confirmed by Jemena to us.

The February 2027 restart date is not new. NEXTDC said in October that Jemena would not restart before then. What is new is the finish line: June to August 2027 for the 66kV works. If work does restart in February, that is four to six months of building, our arithmetic. Counting from the September stop, it is roughly nine to eleven months before the line is done.

NEXTDC is working with Jemena on four paths at once to bring power forward. The CEO listed them:

- Other routes for the line, through industrial streets and underground.
- Other substations.
- Upgrades to existing feeders, the lines already in place, so they carry more power to M3.
- Wider grid options.

The slide notes that these options are linked, so NEXTDC will confirm timing only when there is enough certainty. Put simply: a shorter route or a feeder upgrade might help, but nobody is promising a date earlier than Jemena’s.

There is a second, slower clock behind the first. Later increases in power to M3 need new transformers at Brooklyn Terminal Station, a bigger grid point upstream. NEXTDC now expects the first of those projects to finish later than it thought. It says this does not change FY27 guidance, but it does change when capacity turns into billing after FY28\. So even when the 66kV line is done, the last stages of M3 wait for the transmission side.

The contract itself still stands. NEXTDC says the affected M3 capacity remains under contract, subject to the customer’s rights, and construction continues. The company has not named the customer, and it has not said what those rights are in detail.

## Does NEXTDC have the money to wait?

![Chart: NEXTDC money: FY27 capital spending guidance 5,250 to 5,750 million in August and 4,500 to 5,000 million now; liquidity 8,675 million at 30 September and 8,200 million at 31 October; cash 1,275 million and 793 million](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/australia-nextdc-agm-m3-66kv-power-november-2026-shift.png)

Spending held; cash keeps flowing into contracted halls. · Education only.

On its own numbers, yes, for the halls it has already sold. The slides show A$8.2 billion of liquidity at 31 October 2026\. That is A$793 million of cash, A$6,700 million of senior bank debt not yet drawn, and a A$700 million hybrid securities series that is committed and can be drawn until 15 May 2027\. (The 21 October release gave 15 April 2027 for that series; the AGM slide says 15 May. We did not find an explanation.)

The board also said NEXTDC complied with its loan tests at 30 June 2026 and expects to comply at the next test on 31 December 2026\. The two main tests were well clear at 30 June: interest cover of 5.91 times against a floor of 1.5 times, and gearing of 8.2% against a ceiling of 60%.

Two things temper that comfort. First, most of the liquidity is bank debt that has not been drawn yet, and NEXTDC said in October that full use of it depends on how and when contracts start billing. Billing dates are exactly what M3 has lost. Second, cash is going out fast because the halls are being built. Cash fell from A$1,275 million at 30 September to A$793 million at 31 October.

There is also a value question still open. NEXTDC carries M3 and S4 as investment properties, valued at A$3,236.7 million in total at 30 June 2026\. It said in October that the M3 delay is likely to change that value. On 20 November it said it has not yet put a number on it, and expects to reflect it in the half-year accounts to 31 December 2026, after an outside valuation.

And the A$1.1 billion of convertible notes issued in September, due 2031, were ratified by shareholders with 99.10% of votes. That refreshes the company’s room to issue new shares later without a vote, though the chairman said no raise is planned now. For how big builds like this are usually paid for, see [data center financing explained](https://www.sotkn.com/explained/data-center-financing-explained/).

## What does the arithmetic say?

All of the sums below are our arithmetic on NEXTDC’s published numbers. They use mid-points of ranges and mix dates, so treat them as rough sizes, not precise figures.

How big the M3 hole is

Net revenue mid-point, Aug vs NovA$627.5m vs A$492.5m

Gapabout A$135m

M3 share of August net revenue planabout 22%

M3 share of August EBITDA planabout 35%

Spending vs earning

Capital spending mid-pointA$4,750m

Net revenue mid-pointA$492.5m

Spending vs a year’s net revenueabout 9.6 times

Spending per month at mid-pointabout A$396m

Cash in one month

Cash, 30 Sep vs 31 OctA$1,275m vs A$793m

Changeabout −A$482m

Liquidity changeabout −A$475m

Undrawn senior debt share of liquidityabout 82%

The waiting time

Earliest restart to finish4–6 months

September stop to finishabout 9–11 months

Margin, EBITDA vs net revenueabout 54% (Nov mid)

Each 1% change in property valueabout A$32m

Sydney’s S4, for comparison

Contracted of 365 MW planned250 MW · about 68%

Phase 1 under construction115 MW

Phase 1 share of contractedabout 46%

Phase 1 billingexpected FY28 (company)

Our arithmetic on NEXTDC releases of 21 Oct and 20 Nov 2026\. The one-month cash drop includes all cash flows, not only building; we do not have the split. The property value line is a sensitivity, not a forecast of any write-down.

Three things stand out. First, the M3 contracts are big next to the year: on the August plan they were about a fifth of net revenue and about a third of EBITDA. That is why one power line moved the share price so far in October.

Second, NEXTDC is spending close to ten times its yearly net revenue on building this year. That is normal for a builder in a growth phase, but it means the gap between paying for halls and getting paid for them is wide. Every month a signed hall waits for power, the spending has happened and the billing has not.

Third, cash fell by roughly A$480 million in a single month, about what you would expect from a spending plan of A$4.5–5.0 billion a year. The money is there, mostly as loans not yet drawn. The question is not whether NEXTDC can pay its builders. It is how long the money sits in halls that cannot bill.

## Who gets paid, and who waits?

![Infographic: who gets paid while NEXTDC's M3 waits for power, from builders at S4, M2, M3 and KL1, lenders and the halls outside M3 to the M3 customer and shareholders, with Jemena's 66kV line as the stuck step](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/australia-nextdc-agm-m3-66kv-power-november-2026-infographic.png)

Who gets paid / stuck step while M3 waits for its line. · Education only.

1 · Builders and equipment makers

**Who:** Contractors and power and cooling gear at S4, M2, M3, KL1  
**Paid:** Most of A$4.5–5.0bn FY27 spending goes to contracted halls

Paid

2 · Lenders and note holders

**Who:** Banks, hybrid and convertible note holders  
**Paid:** About A$230m of interest capitalised in FY27; A$1.1bn notes at 1.75%

Paid

3 · NEXTDC, outside M3

**Who:** Halls in Sydney, Brisbane, Perth and elsewhere  
**Paid:** FY27 net revenue guide A$485–500m, up 22% at mid-point on FY26

Paid

4 · The M3 customer

**Who:** Unnamed; capacity still under contract  
**Paid:** Waits for power; may be owed service credits

Waits

5 · Shareholders

**Who:** Including Goodman and Digital Realty’s 9.9% vehicle  
**Paid:** A$9.01 on 20 Nov vs A$9.50 paid by Ackland; \~A$140m a year on hold

Waits

6 · Jemena’s 66kV line

**Who:** The network company’s works to M3  
**Paid:** Earliest restart Feb 2027; finish June–August 2027

Stuck step

NEXTDC ASX releases and AGM slides, 20 Nov 2026; Reuters, 20 Nov 2026 (share price). Status chips are Second Order’s read.

Read the chain from the top. Builders and equipment makers are paid as halls go up, and NEXTDC has kept its spending at the October level. Most of it is going to halls customers have signed for. These firms do not wait for Jemena: construction at M3 itself continues.

Lenders are paid every period too. About A$230 million of FY27 interest is being capitalised, meaning it is added to the cost of the buildings rather than charged against profit straight away. The holders of the A$1.1 billion convertible notes earn 1.75% a year on them. None of this depends on M3’s timing.

NEXTDC itself keeps getting paid on the rest of its estate. It runs 18 data centres across Australia and Malaysia. The guidance lift says that part is growing faster than NEXTDC expected a month ago.

The M3 customer is in an odd spot. Its capacity is still under contract and its halls are being built, but the power it wants will be late. It may even end up being paid: NEXTDC flags that service credits could become payable on the affected contracts, which would come out of NEXTDC’s EBITDA. How much is not disclosed.

Shareholders wait. That includes Ackland Investments No.1, the vehicle owned half each by Goodman Group and Digital Realty, which paid A$9.50 a share for its 9.9% stake in November. The 20 November close of A$9.01 is about 5% below that price, our arithmetic. NEXTDC’s board repeated that it has received no takeover proposal. For more on the two rivals, see [what Digital Realty does](https://www.sotkn.com/stack/ai-data-centers/what-does-digital-realty-do/) and our read on [Goodman’s power bank](https://www.sotkn.com/analysis/goodman-power-bank-lease-stuck-step-what-price-assumes/).

## What did the vote tell us?

Australia has a “two strikes” rule. If 25% or more of votes go against a company’s pay report two years in a row, shareholders then vote on whether to sack the board and make every director stand again. That vote is called a spill.

NEXTDC got its second strike: 72.06% of votes cast were against the FY26 pay report, almost the same as the roughly 72% last year. But only 3.79% voted for a spill, and 96.21% against. Three directors were re-elected. Stuart Davis got the weakest support, 66.11%, and has said he will step down once new directors are found.

The message reads as: unhappy about pay, not willing to blow up the board in the middle of a crisis. The board had already cut non-executive fees by 10% and withdrawn two items: a bigger fee pool for directors and the CEO’s FY27 bonus grants. A new chair and one more independent director are expected in the first quarter of 2027, with a search for people with data centre, energy, infrastructure and capital management skills.

The day before, at Goodman Group’s own AGM, a small group of holders asked Goodman to publish how it weighs the community and planning risks of data centres near homes. Goodman’s results show the needed rule change got only 8.44% support, so the request never came to a vote. Goodman also took a first strike on its own pay report. Both meetings show investors watching the same thing: whether data centre builders can get the community, the power and the permits lined up before they spend.

## What is stuck, exactly?

Not the money. NEXTDC has the funding for its signed halls, on its own words. Not the customer. The contract still stands. Not the building. Construction goes on.

What is stuck is Jemena’s 66kV line to M3\. It is the one step NEXTDC cannot finish by itself. The network company owns the line, leads the consultation with residents, and needs its own approvals. NEXTDC can support that process, and has appointed two directors and a permanent community engagement manager for M3, but it cannot run it.

Behind that sits a second gate, slower and further upstream: the new transformers at Brooklyn Terminal Station that later M3 stages need. And to the side sits a third: the Victorian government’s planning decision on Stages 6 and 7, not expected before the first quarter of 2027.

This is the pattern we keep seeing across AI data centres: the cash moves to whoever controls the slowest step. Here, the slowest step is not a chip or a loan but a line of poles in a Melbourne suburb. For the general idea, see [where the stuck step moves](https://www.sotkn.com/analysis/where-does-the-stuck-step-move/), and for how power gets promised to a site before it is delivered, [contracted power explained](https://www.sotkn.com/explained/contracted-power-explained/). Australia’s new grid rule for loads above 30 MW adds another layer for future halls ([the 30 MW ride-through rule](https://www.sotkn.com/catalyst/australia-30-mw-data-center-grid-rule-ride-through/)).

## What would change this read?

- Jemena confirms a route, substation or feeder fix that brings power to M3 before mid-2027\. That would shorten the wait.
- Jemena’s works do not restart in February 2027, or the June–August finish slips. That would lengthen it.
- NEXTDC puts a number on the M3 contracts’ FY27 contribution, or on service credits, at the February half-year result.
- The half-year valuation shows a large change in M3’s carrying value.
- The new Victorian government decides the Stages 6 and 7 permit, either way.
- A paused site restarts with a signed customer and power in place, which would show the new rules working.
- Goodman, Digital Realty or anyone else makes a formal proposal for NEXTDC.

## Which dates test the read?

![Calendar of dates: 20 November 2026 AGM, 28 November Victorian election, 31 December covenant test, February 2027 earliest Jemena restart and half-year result, first quarter 2027 Stages 6 and 7 decision earliest, June to August 2027 66kV works due](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/australia-nextdc-agm-m3-66kv-power-november-2026-calendar.png)

Clocks that test the read. · Education only.

- 28 November 2026 — Victorian state election; NEXTDC expects the Stages 6 and 7 planning process to resume after it.
- 31 December 2026 — next loan covenant test; NEXTDC expects to comply.
- February 2027 — earliest restart of Jemena’s suspended works, and NEXTDC’s half-year result with an M3 progress update.
- First quarter of 2027 — earliest planning decision on M3 Stages 6 and 7; new chair and director expected.
- 15 May 2027 — last day to draw the A$700 million hybrid series, per the AGM slide.
- June–August 2027 — Jemena’s current expectation for finishing its 66kV works.
- FY28 — S4 Phase 1 (115 MW) expected to begin billing.

Dates from NEXTDC releases and AGM slides of 20 Nov 2026\. Jemena dates as advised to NEXTDC. Plans, not facts.

## How does this fit the rest of our Australia notes?

It closes a loop we have followed since October. First came the delay ([M3’s power delay](https://www.sotkn.com/markets/australia/australia-nextdc-melbourne-power-delay-october-2026/)), then the money ([the FY27 guidance cut](https://www.sotkn.com/markets/australia/australia-nextdc-fy27-guidance-cut-october-2026/)), then the rivals’ stake, where we said the next stuck step was the 20 November verdict ([the Goodman and Digital Realty raid](https://www.sotkn.com/markets/australia/australia-nextdc-goodman-digital-realty-raid-november-2026/)). The verdict is in: spending held, the M3 hole unchanged, and a later finish date for the line. For the wider Sydney and Melbourne pipeline, see [the permit pipeline note](https://www.sotkn.com/markets/australia/australia-data-centre-pipeline-sydney-melbourne-permit-october-2026/); for who funds Australia’s halls, [AI data centre funding](https://www.sotkn.com/markets/australia/australia-ai-data-centre-funding-october-2026/); for a smaller listed peer, [what Macquarie Technology does](https://www.sotkn.com/stack/ai-data-centers/what-does-macquarie-technology-do/). For how shared halls differ from single-tenant ones, see [colocation explained](https://www.sotkn.com/explained/colocation-explained/). All our notes are on [Australia Markets](https://www.sotkn.com/markets/australia/).

Second-order read. NEXTDC’s review kept FY27 spending at A$4.5–5.0 billion and lifted guidance outside M3\. Builders, lenders and the rest of the estate keep getting paid. The M3 customer and shareholders wait. The stuck step is Jemena’s 66kV line, now due June to August 2027\. Watch February 2027: the restart and the half-year result.

**Get the Wire.** Second Order’s free daily brief on what moved in the AI chip map. [Read the Wire →](https://www.sotkn.com/the-wire/) · [Subscribe free →](https://www.sotkn.com/#/portal/signup)

**How we check this.** Every NEXTDC guidance, spending, liquidity, covenant, site and timing figure comes from the company’s own ASX releases of 20 November 2026 (the guidance upgrade, the chairman and CEO’s address and the AGM slides) and 21 October 2026, which we read directly. Jemena’s dates are as NEXTDC reported them; Jemena itself declined to comment to the press. Vote shares come from the company’s results of meeting, and the share price move from Reuters. Quotes from the meeting floor come from The Sydney Morning Herald and The Guardian. Every sum we worked out is labelled “our arithmetic”. Guidance and dates are plans, not facts yet. The references we used are listed at the end. [Our editorial standards →](https://www.sotkn.com/editorial-standards/)

## FAQ

**What happened at NEXTDC’s AGM on 20 November?**  
NEXTDC said it had finished the review of its spending it promised on 21 October. It kept FY27 capital spending at A$4.5 to A$5.0 billion and named six uncontracted sites that stay on hold. It nudged up FY27 net revenue guidance to A$485–500 million and underlying EBITDA guidance to A$260–275 million, both still excluding the affected M3 contracts. Shareholders voted 72.06% against the pay report, a second strike, but 96.21% against a board spill.

**What is new about M3?**  
The AGM slides gave Jemena’s advised dates for the first time in one place: February 2027 is the earliest restart for its suspended works, and June to August 2027 is Jemena’s current expectation for finishing its 66kV works. The planning decision for M3 Stages 6 and 7 is not expected before the first quarter of 2027, after the Victorian election. Later power steps depend on new transformers at Brooklyn Terminal Station, now expected later than before.

**What is the stuck step?**  
Jemena’s 66kV line to M3\. The hall is being built and the customer is still under contract, but the extra power cannot arrive until the network company finishes the line. NEXTDC cannot finish that step by itself.

**Who gets paid while M3 waits?**  
Builders and equipment suppliers on S4 Sydney, M2, M3 and KL1, since most of the A$4.5–5.0 billion goes there; lenders and note holders, through about A$230 million of interest that is capitalised this year; and NEXTDC itself on halls outside M3, where revenue is rising. The M3 customer may even be owed service credits. NEXTDC’s about A$140 million a year from the affected M3 contracts waits.

**Does NEXTDC need to raise money from shareholders?**  
Not on its own words. The chairman said NEXTDC does not expect to raise capital from shareholders at this time to deliver its current contracted capacity. It reported A$8.2 billion of liquidity at 31 October 2026, most of it undrawn bank debt.

**Is this investment advice?**  
No. Education only. It maps who gets paid and which step is stuck. It is not a recommendation to buy or sell any security, and we leave out price targets and ratings on purpose.

---

### References

Outbound links below are nofollow. We list only the sources actually used. Internal sotkn.com links in the body are separate.

1. NEXTDC Limited, FY27 Guidance Upgrade (ASX release), 20 Nov 2026\. [asx.com.au](https://www.asx.com.au/markets/trade-our-cash-market/announcements.nxt?ref=sotkn.com) — the three sets of FY27 guidance, the capital expenditure review outcome, the six sites on hold, the S4 split and the investment property note.
2. NEXTDC Limited, 2026 AGM – Chairman and CEO’s Address (ASX release), 20 Nov 2026\. [announcements.asx.com.au](https://announcements.asx.com.au/asxpdf/20261120/pdf/076v44fjx7dkp1.pdf?ref=sotkn.com) — the M3 account in the company’s words, the four power pathways, the community steps, the covenant and capital-raising comments.
3. NEXTDC Limited, 2026 Annual General Meeting presentation, 20 Nov 2026\. [nextdc.com](https://www.nextdc.com/our-company/investor-centre?ref=sotkn.com) — Jemena’s advised dates (earliest restart February 2027, 66kV works June–August 2027), the Stages 6 and 7 timing, the Brooklyn Terminal Station note, liquidity at 31 October and covenant ratios.
4. NEXTDC Limited, M3 Melbourne Power Delay and Revised FY27 Guidance (ASX release), 21 Oct 2026\. [asx.com.au](https://www.asx.com.au/markets/trade-our-cash-market/announcements.nxt?ref=sotkn.com) — liquidity and cash at 30 September 2026, used for comparison.
5. Reuters (via MarketScreener), Australia’s NextDC shareholders deliver second pay strike but stop short of board spill, 20 Nov 2026\. [marketscreener.com](https://www.marketscreener.com/news/australia-s-nextdc-shareholders-deliver-second-pay-strike-but-stop-short-of-board-spill-ce785ed2d18af724?ref=sotkn.com) — the vote shares and the 20 November share price move.
6. The Sydney Morning Herald, ‘They know they screwed up’: Data centre giant throws power company under the bus, 20 Nov 2026\. [smh.com.au](https://www.smh.com.au/technology/furious-investors-revolt-over-executive-pay-at-data-centre-giant-20261120-p61fv0.html?ref=sotkn.com) — the chairman’s remarks on Jemena and the site, and the residents’ view.
7. The Guardian, NextDC vows to keep future datacentres away from homes after community backlash in Melbourne, 20 Nov 2026\. [theguardian.com](https://www.theguardian.com/australia-news/2026/nov/20/nextdc-vows-to-keep-future-datacentres-away-from-homes-after-community-backlash-in-melbourne?ref=sotkn.com) — the 22-metre poles and Jemena’s response.
8. Goodman Group, Results of Annual General Meetings (ASX release), 19 Nov 2026\. [goodman.com](https://www.goodman.com/-/media/project/goodman/global/files/investor-centre/gmg-goodman-group/announcements/asx-announcements/2026/agm-results-of-meeting.pdf?ref=sotkn.com) — the first strike and the 8.44% vote on the data centre disclosure request.

Not investment advice. Do your own research. Education only. Map of who gets paid and which step is stuck — not a buy list.

More on this desk: [Australia Markets](https://www.sotkn.com/markets/australia/) · [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/) · [what NEXTDC does](https://www.sotkn.com/stack/ai-data-centers/what-does-nextdc-do/) · [revenue backlog vs RPO](https://www.sotkn.com/explained/revenue-backlog-vs-rpo/) · [all Markets](https://www.sotkn.com/markets/).