# RMB 12 Billion Built, RMB 8.5 Billion Paid: Who Gets Paid While China’s Data Centre Builders Wait on the Move-In
- URL: https://www.sotkn.com/markets/china/china-gds-capex-payables-move-in-november-2026/
- Published: 2026-11-27T09:03:40.000Z
- Updated: 2026-11-27T09:03:40.000Z
- Description: On 25 November GDS cut the cash it will pay for building in 2026 to RMB8.5 billion, while it builds about RMB12 billion. The gap sits with suppliers as bills to be paid later. Customers take about 12 months to move in. That move-in is the stuck step.
- Author: Sean
- Tags: #market-china, Markets, #layer-ai-data-centers

*On Wednesday 25 November, GDS, one of China’s biggest independent data centre builders, said something small that matters. It will build about RMB12 billion of halls this year. It will pay out only about RMB8.5 billion of that in cash. The rest becomes bills its suppliers wait to collect. Demand is not the issue. GDS says its new halls are almost fully signed. The issue is time. A signed customer takes about a year to move in and pay in full. Until then, someone has to carry the cost. This week, part of that someone is the builders. The stuck step is the move-in.*

**CHINA PULSE** · AI DATA CENTERS · Data as at 27 Nov 2026 (GDS Q3 release and call, 25 Nov; VNET Q3 release, 6-K and call, 23 Nov; Kingsoft Cloud Q3, 24 Nov) · Next update: VNET fourth-quarter deliveries, GDS year-end bookings and the early-2027 C-REIT injection  
**Affects:** [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/) — Markets: [China](https://www.sotkn.com/markets/china/)

**In short:** On 25 November 2026 GDS Holdings (Nasdaq: GDS; HKEX: 9698) cut its 2026 capex guidance from RMB10 billion to about RMB8.5 billion. On the call, the CFO said capex incurred this year will be around RMB12 billion and the difference will be capex payables: bills to suppliers paid later. GDS has 191,930 sqm under construction, up 163.8% in a year and 91.3% pre-committed. Contracts give customers about 12 months to move in. VNET (23 Nov) has 1,127 MW in service and 797 MW used. Power costs squeezed both margins. Stuck step: the move-in. Map of who gets paid — not a buy list.

Education only, not advice to buy or sell any security. Capex is money spent on buildings and equipment. Wholesale means one big customer takes a whole hall or building ([retail vs wholesale colocation, explained](https://www.sotkn.com/explained/retail-vs-wholesale-colocation/)). For who these two companies are, see our Stack pages on [what GDS does](https://www.sotkn.com/stack/ai-data-centers/what-does-gds-do/) and [what VNET does](https://www.sotkn.com/stack/ai-data-centers/what-does-vnet-do/). This note is about their latest quarter, and the wait between a signed hall and a full one.

### The numbers that matter this week

GDS capex incurred, 2026

\~RMB12bn

Work done on halls this year (CFO, 25 Nov)

Building

GDS capex paid, 2026 guide

RMB8.5bn

Cut from RMB10bn · rest becomes payables

New

GDS area under construction

191,930 sqm

+163.8% y/y · 91.3% pre-committed

Signed

GDS utilisation

81.2%

Up from 74.4% · CFO: dips into the 70s next

Watch

VNET wholesale MW

1,127 / 797

In service / used by customers, 30 Sep

Filling

The wait

\~12 months

Average move-in until fully billable (GDS)

Stuck step

GDS release and call, 25 Nov 2026; VNET release and call, 23 Nov 2026\. Status chips are Second Order’s read.

**On this page:** [Why it matters](#why-it-matters) · [What GDS reported](#what-happened) · [Built vs paid](#payables) · [The move-in](#move-in) · [VNET](#vnet) · [Power bills](#power-bills) · [Domestic chips](#domestic-chips) · [Funding](#funding) · [The tenant side](#tenant) · [Clocks](#clocks) · [Who gets paid](#money-goes) · [What is stuck?](#still-stuck) · [Dates next](#dates) · [FAQ](#faq)

## Why does a change in payment timing matter?

Picture a builder putting up a block of flats. Every flat is sold before it is finished. The buyers have signed. But they get the keys in stages, and they only pay the full price once they move in. Meanwhile the developer has bills for concrete, cables and lifts. So the developer asks its suppliers to wait a little longer for their money. Nobody has cancelled. The money is simply moving later down the line.

That is the picture at GDS this week. It has stepped up its bookings this year. Its new halls are 91.3% pre-committed. But a signed hall is not a paying hall. GDS says customers get about 12 months, on average, to fill the space and become fully billable. So while the halls fill, cash goes out faster than it comes in. One way to ease that is to pay suppliers later. GDS just told us it will do exactly that, by about RMB3.5 billion this year (our arithmetic).

It fits a pattern we have followed in China all month. China Mobile has ordered 52,160 AI cards and waits for prices on 14 December ([China Mobile’s second supernode order](https://www.sotkn.com/markets/china/china-mobile-52160-cards-supernode-tender-november-2026/)). Alibaba says its cloud growth waits on its own chips ([Alibaba’s own chips](https://www.sotkn.com/markets/china/china-alibaba-cloud-growth-own-chips-november-2026/)). Each time, the money is signed early and paid late. The gap in between is where the risk sits.

Why should a reader outside China care? Because GDS is a bellwether. Its top three customers are the biggest internet and cloud firms in the country. When it books, those firms are planning to fill halls. When it slows payments, it tells us how long the gap between building and earning has become. And because GDS also owns a minority stake in DayOne, the Johor and Singapore builder, its numbers touch our Asia doors too.

## What did GDS report on 25 November?

GDS released its results for the quarter to 30 September on Wednesday 25 November. It held a call at 8 p.m. Beijing time. Here is what it said, in order.

- Revenue rose 10.1% from a year earlier to RMB3,180.1 million (US$474.3 million). Adjusted EBITDA rose 2.8% to RMB1,380.2 million.
- Gross margin fell to 19.7% from 22.1%. The company says this was mainly because utility costs — mostly power — rose as a share of revenue.
- Net income was RMB28.5 million, down from RMB728.6 million. Last year’s figure included a one-off gain when GDS moved assets into its C-REIT, a listed property trust in Shanghai.
- Total area committed and pre-committed was 823,876 sqm, up 25.5%. Area in service was 690,529 sqm, up 5.6%. Area used by customers was 560,957 sqm, up 15.3%.
- Area under construction was 191,930 sqm, up 163.8% from 72,764 sqm a year earlier. 91.3% of it is pre-committed, up from 73.0%.
- Utilisation of area in service was 81.2%, up from 74.4%.
- Cash was RMB17,817.8 million. New debt and refinancing in the quarter was RMB2,328.7 million.
- Revenue and EBITDA guidance for 2026 was kept. Capex guidance for 2026 was cut to about RMB8,500 million from RMB10,000 million.

On the call, the chairman said bookings for the first nine months were 686 MW, and that GDS still expects about 1 GW for the full year. Over 80% of new business is with the top three internet and cloud customers in China. All contracts are take-or-pay, meaning the customer pays for the space whether it uses it or not, once the agreed ramp is reached. The move-in period averages 12 months.

What the release did not say is just as useful. It did not name the customers. It did not name the suppliers whose bills will wait. It did not give a payables figure for the year. The RMB12 billion and the payables point came only on the call, in answer to a question from an analyst.

## What does “RMB12 billion built, RMB8.5 billion paid” mean?

![Chart: GDS 2026 capex, RMB billion: capex incurred about 12, capex paid guide was 10 and is now 8.5, paid in the first nine months 4.3, and about 3.5 left as bills to suppliers (our arithmetic)](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/china-gds-capex-payables-move-in-november-2026-print.png)

GDS release and call, 25 Nov 2026\. The 3.5 is our arithmetic. · Education only.

There are two ways to count capex. One is the work done: concrete poured, generators installed, cooling fitted. Accountants call that capex incurred. The other is the cash that leaves the bank to pay for it. That is the number in the cash-flow statement, and it is the one GDS gives as guidance.

On the call, an analyst asked whether the cut was because GDS could pay suppliers later, or because customers wanted slower delivery. The CFO answered: “It’s the first reason you gave. It’s a small adjustment to the timing of payments to our CapEx suppliers.” He said capex incurred in 2026 will be around RMB12 billion, cash paid RMB8.5 billion, “and the difference will be CapEx payables.” Asked if customers had signalled any delay, he said: “No change at all to any of our plans or ongoing execution.”

Our arithmetic: RMB12 billion minus RMB8.5 billion is about RMB3.5 billion. At the company’s own exchange rate of RMB6.7045 to the US dollar, that is about US$0.52 billion. That is work done this year that suppliers will be paid for after year-end. GDS also said organic capex paid in the first nine months was RMB4.3 billion. So, by our arithmetic, it plans to pay about RMB4.2 billion in the fourth quarter alone, roughly as much as in the first three quarters together.

Is this unusual? Not by itself. Builders often get paid on milestones, and big buyers often stretch terms. In effect the suppliers are lending GDS money for a few months, free of interest. We covered how that works in [vendor financing, explained](https://www.sotkn.com/explained/vendor-financing-explained/). What is new is the size and the timing. The suppliers now carry a larger share of the gap between building and earning, at the moment GDS is building faster than it has in years.

Who are the suppliers? GDS does not say. In China, a data hall bill is mostly construction firms, electrical gear, generators, transformers, cooling plant and fit-out. Our read: those are the firms whose receivables rise when GDS pays later. We do not name any company, because GDS has not.

The bigger clock sits behind it. The CFO said GDS needs about RMB16 billion more over the next two years to finish the halls for its year-end backlog. It expects net debt of about RMB32 billion at the end of 2026 and about RMB38 billion at the end of 2028, after operating cash and asset sales. So paying later this year does not shrink the bill. It moves part of it into 2027.

## Why is the move-in the stuck step?

A data hall earns in three steps. First it is signed. Then it is built and handed over. Then the customer moves in, rack by rack, until it uses what it signed for. Only at the end of the third step is the contract fully billable. GDS says that third step takes about 12 months on average.

The CFO explained how this shows up in the numbers. GDS counts a whole contract’s space as in service once the building is handed over. Then the customer has about 12 months to fill it. So, he said, as the big wave of halls now under construction comes into service, “the utilization will dip down back into the 70s.” He added that “pretty much everything we’re building is 100% committed,” and that utilisation should later climb into the mid- to high 80s.

Our arithmetic shows the size of the wait. GDS has 823,876 sqm committed and 560,957 sqm used. The gap is about 262,900 sqm. That is space customers have signed for but are not yet using. It is about a third of everything committed. In the third quarter, net new commitments were 39,074 sqm, while net new move-ins were 18,721 sqm. Commitments ran about twice as fast as move-ins.

The company put a number on what the wait is worth. At the end of 2026 it expects total billings of 1.4 GW and a backlog of 1.15 GW that is signed but not yet billable. The CFO said the backlog will be fully billable within two years. On his figures, that adds about RMB2.5 billion a year of EBITDA, at about RMB2.2 million per MW. Annualised adjusted EBITDA would rise from about RMB5.5 billion in the fourth quarter of 2026 to about RMB6.7 billion in the fourth quarter of 2028\. That projection uses only contracts signed by the end of 2026.

So the earning power is largely signed. What is not in the company’s hands is how fast customers fill the space. That depends on their own plans and on their own supply of servers and chips. This is the same gap we describe for US leases in [leases not yet commenced, explained](https://www.sotkn.com/explained/leases-not-yet-commenced-explained/): signed, but not yet paying.

## What did VNET add on 23 November?

![Chart: VNET wholesale capacity at 30 September 2026: 1,127 MW in service, 797 MW used by customers, about 330 MW built but not yet used (our arithmetic), 548 MW under construction](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/china-gds-capex-payables-move-in-november-2026-shift.png)

VNET release and call, 23 Nov 2026\. The 330 MW is our arithmetic. · Education only.

VNET, the other big listed builder, reported two days earlier. It counts its wholesale business in megawatts, which makes the wait easier to see.

- Wholesale capacity in service was 1,127 MW at 30 September, up 44.1% (345 MW) from a year earlier.
- Wholesale capacity used by customers was 797 MW, up 37.1% (216 MW). Utilisation was 70.7%, down from 74.3%.
- Capacity under construction was 548 MW, 93.6% pre-committed. Capacity in service was 97.1% committed.
- VNET delivered 121 MW in the third quarter. It plans about 213 MW in the fourth quarter and 335 MW in the first nine months of 2027.
- Orders signed in 2026 reached 922 MW, including a new 60 MW order from a large cloud provider. About 287 MW deliver in 2026, 405 MW in 2027 and 230 MW in 2028 or later.
- Revenue rose 14.8% to RMB2.96 billion. Wholesale revenue rose 27.6% to RMB1.22 billion. Adjusted EBITDA rose 21.7% to RMB923.1 million.
- Capex in the first nine months was RMB5.73 billion. The 2026 guide was cut to RMB8–10 billion from RMB10–12 billion.

Our arithmetic: 1,127 MW in service minus 797 MW used is about 330 MW. That is power capacity that is built, mostly committed, and waiting for customers’ servers. Mature halls run at 92.2% utilisation, the company says. So the empty space sits in the new halls, as you would expect while customers move in.

VNET’s capex cut has a different reason from GDS’s. VNET says it is partly thanks to cheaper procurement, with build cost now below RMB20 million per MW. GDS says its cut is about timing of payments. We report both as given. The effect for suppliers is not the same: lower prices mean less money for them; later payment means the same money, later.

## Why are power bills eating the margin?

Both companies said the same thing about cost. Power is taking a bigger share of revenue. At GDS, gross margin fell from 22.1% to 19.7%, and adjusted gross margin from 51.0% to 47.1%, mainly because of utility costs. At VNET, gross margin fell from 20.9% to 15.8%. VNET blamed higher depreciation from new halls and utility costs rising as a share of revenue.

Why would power rise faster than revenue? Our read: in a take-or-pay hall, the customer pays a fixed amount for space and capacity as it moves in. Power use follows the servers. When servers arrive faster than billing steps up, or when the landlord carries power for common systems such as cooling, the power bill can run ahead of the fee. A hot summer adds to it. VNET noted higher power use in the summer months. We have not seen either company’s contracts, so we do not know how much power cost is passed through.

The national data back up the scale. China’s National Energy Administration said on 23 November that internet data services used 9.9 billion kWh in October, up 34.7% from a year earlier, and 89.2 billion kWh in the first ten months, up 40.8%. We used that series to frame China Mobile’s order on 23 November ([52,160 cards, no price yet](https://www.sotkn.com/markets/china/china-mobile-52160-cards-supernode-tender-november-2026/)), so we only note it here. The halls are using much more power. The landlords are paying more of it.

VNET says it will try participation in electricity spot markets, direct green power supply and battery storage, working with its new shareholder, affiliates of the battery maker CATL. Those tools take time. For how long-term power deals work, see [power purchase agreements, explained](https://www.sotkn.com/explained/power-purchase-agreement-explained/).

## Do domestic chips set the pace of the move-in?

This is the part most likely to move the clock. A customer can only move in as fast as it gets servers. For China’s big cloud firms, the newest US chips are out of reach. On 19 November a new US rule also began requiring licences for remote access to US chips in overseas data centres used by Chinese firms.

Both landlords answered the question head on. The GDS chairman said: “We only target orders which rely on domestic technologies.” He said GDS tracks its customers’ supply chains and that the backlog delivery schedule will not change. VNET’s rotating president said designs and power specifications for orders now moving in, and for next year, have been “matched to domestic chips,” and that customers have locked in top-tier domestic production capacity. He expects the impact on move-in to be “within a controllable range.” We covered the remote-access rule from the lab side in [offshore chips need a licence](https://www.sotkn.com/markets/china/china-remote-access-rule-offshore-chips-license-november-2026/).

That makes domestic chip output the real pace-setter. And domestic chip output has its own stuck steps. SMIC said on its 13 November call that its fabs are near full and that some tools now take 16 to 24 months to arrive ([SMIC waits for machines](https://www.sotkn.com/markets/china/china-smic-q3-tool-lead-times-november-2026/)). If domestic accelerators come slower than the halls, the 12-month move-in could stretch. If they come on time, the landlords’ plans hold.

Outside views are more cautious. Fitch Ratings said on 26 November, as reported by Reuters, that China-focused operators may have to offer less advanced computing or keep using existing chips without upgrades, and that nearly finished projects could slip if chips or eligible customers cannot be confirmed. Fitch was writing about operators across Asia, not GDS or VNET by name. We note it as the other side of the argument.

## How is the building paid for?

Three sources stand out in this quarter’s numbers: banks at home, asset sales into trusts, and suppliers who wait.

GDS

Cash, 30 SepRMB17.8bn

Set aside for a convertible bondRMB4bn, early 2027

Net debt / EBITDA5.1x annualised

New loans in Q3RMB2.33bn

Mix for new halls60% debt, 40% equity

VNET

Cash incl. restricted, 30 SepRMB6.49bn

Unused credit linesRMB15.6bn

Net debt / EBITDA5.2x

New project loansLPR minus 55–60bp

Private REIT follow-onRMB1.1bn net, 18 Nov

GDS release and call, 25 Nov 2026; VNET call, 23 Nov 2026\. LPR is China’s five-year loan prime rate.

Banks at home are cheap and willing. GDS says it can access all the debt it needs from domestic banks at low rates, mostly onshore project loans. VNET says its latest project loan was priced 55 to 60 basis points below the five-year loan prime rate, and new project loans are generally below 3%. VNET also said new policy-based financial instruments can cover up to 90% of the capital for some projects, against a usual 70% to 80%.

Asset sales recycle cash. GDS runs one of only two data centre REITs listed on the Shanghai Stock Exchange. It expects to complete the first injection of new assets into it early next year, after regulatory approval. VNET completed a follow-on issue of its Wulan private REIT on 18 November: a 74 MW asset, valued at 13 times, raising RMB1.1 billion of net proceeds. It also set up a development fund with a provincial state-owned financial institution, and its board is looking at a Hong Kong listing.

And suppliers wait. The RMB3.5 billion of GDS payables is the cheapest money in the mix, because it carries no stated interest. It also moves risk onto the builders’ books. For the general picture of how halls are financed, see [data centre financing, explained](https://www.sotkn.com/explained/data-center-financing-explained/). For a Singapore view of the same question, see DayOne’s paused listing ([US$5 billion IPO on hold](https://www.sotkn.com/markets/singapore/singapore-dayone-ipo-pause-next-wave-november-2026/)).

Interest is the quiet cost of the wait. GDS paid net interest of RMB369.2 million in the third quarter, against net income of RMB28.5 million. Depreciation was RMB880.7 million. Both start the day a hall enters service, before the customer is fully billed. GDS says as much in its own release: depreciation starts as soon as a data centre enters service, while it usually takes several years to reach high utilisation.

## What does the tenant side look like?

Landlords do not name tenants, but one listed cloud firm gave a view from the other side of the lease. Kingsoft Cloud, which is linked to Xiaomi and Kingsoft, reported on 24 November.

- Revenue rose 40.4% to RMB3,478.1 million.
- AI cloud gross billings were RMB1,683 million, up 115%, and 61% of public cloud revenue, against 45% a year ago.
- IDC costs — what it pays data centre owners — rose 36.7% to RMB1,060.1 million, because of more rack services and short-term equipment rental for AI.
- Cash capex in the quarter was RMB6.2 billion, nearly all covered by operating cash flow, the CFO said.

Our read: this is what a move-in looks like from the tenant’s chair. The cloud firm buys servers, puts them in someone’s hall, and pays rising fees as it fills racks. Its own spending on servers was RMB6.2 billion in one quarter. That is the money that decides how fast a landlord’s hall fills. Kingsoft Cloud is not named as a GDS or VNET customer, and we do not say it is one.

It also shows why landlords like big, steady customers. Over 80% of GDS’s new business comes from three firms. That gives certainty. It also means three firms’ server budgets set the pace. See [customer concentration, explained](https://www.sotkn.com/explained/customer-concentration-explained/).

## What do the clocks say?

![Calendar: 23 Nov VNET results, 25 Nov GDS results, Q4 2026 VNET 213 MW deliveries, year-end GDS 1 GW bookings target, early 2027 GDS C-REIT injection and convertible bond redemption, first nine months of 2027 VNET 335 MW, end-2028 GDS over 2.4 GW billable](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/china-gds-capex-payables-move-in-november-2026-calendar.png)

Clocks that test the read. · Education only.

A build programme is a set of clocks. Here are the ones we can date, in order.

- 18 November 2026: VNET completes the Wulan private REIT follow-on, RMB1.1 billion net.
- 23 November 2026: VNET reports; 1,127 MW in service, 797 MW used.
- 25 November 2026: GDS reports; capex paid cut to about RMB8.5 billion; about RMB12 billion incurred.
- Fourth quarter 2026: VNET plans about 213 MW of deliveries. GDS aims for about 1 GW of bookings for the year.
- Early 2027: GDS expects its first post-listing C-REIT injection, and has RMB4 billion set aside to redeem a convertible bond.
- First nine months of 2027: VNET plans another 335 MW.
- 2027: the deferred GDS supplier bills fall due (our read; GDS gave no dates).
- End of 2028: GDS projects over 2.4 GW of billings, all from contracts signed by end-2026.

## Who gets paid while the halls fill?

![Infographic: who gets paid while China's new data halls fill, from contractors and gear makers to banks, landlords, power suppliers and cloud tenants, with the 12-month move-in as the stuck step](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/china-gds-capex-payables-move-in-november-2026-infographic.png)

Who gets paid / stuck step while the halls fill. · Education only.

Here is the split as we read it. It is a map of timing, not a list of winners.

Paid now

Domestic banksInterest on project loans

Power suppliersBills grow with every server

Most contractorsRMB8.5bn of cash this year (GDS)

Paid later

GDS capex suppliers\~RMB3.5bn moved past year-end (our arithmetic)

LandlordsFull fees after \~12 months of move-in

REIT investorsIncome once assets are injected

Sets the pace

Cloud tenantsServer budgets decide the move-in

Domestic chip makersSupply decides the servers

Second Order’s read of the GDS, VNET and Kingsoft Cloud releases and calls. We have not seen contracts or supplier terms.

The steadiest earners today are the banks and the power suppliers. Banks are paid interest from the day money is drawn. The power bill is paid every month, and it is rising faster than revenue at both landlords.

The contractors are split. Most are paid in cash this year. But at GDS, about RMB3.5 billion of their work will be paid later, on our arithmetic. For a large contractor, that is a longer wait for cash and a bigger receivable on its own books.

The landlords wait longest inside the year. They carry interest, depreciation and part of the power bill while customers ramp. Their reward is the signed fee stream once halls are full: GDS puts that at about RMB2.2 million of EBITDA per MW a year for its backlog. The tenants hold the key. They decide how fast to fill, and their pace depends on chips.

## What is stuck, and what would change our read?

The stuck step is the move-in. It is not demand, because the halls are signed. It is not money for building, because domestic banks lend cheaply and both firms have large credit lines. It is not the building itself, because the halls are going up. It is the months between handover and full billing, and the servers that fill them.

What would make us more positive? GDS reaching about 1 GW of bookings by year-end, as it says. VNET delivering its 213 MW in the fourth quarter on time. Utilisation falling only into the high 70s at GDS and then climbing, as the CFO expects. The C-REIT injection closing early in 2027\. Power cost growth slowing as a share of revenue.

What would make us more cautious? Capex payables at year-end well above the RMB3.5 billion implied. A cut to the 2027 or 2028 billings outlook. Utilisation falling below 70% at either firm. Customers asking to slow move-ins. Or a domestic chip shortfall that pushes servers out by a quarter or more.

We are careful about two things. First, paying suppliers later is common and does not mean a firm is short of cash. GDS holds about RMB17.8 billion. Second, the RMB12 billion and the payables figure are spoken numbers from a call. We will check them against the full-year accounts.

For how the stuck step tends to move from one link to the next, see [where the stuck step moves](https://www.sotkn.com/analysis/where-does-the-stuck-step-move/). For the power side of China’s build, see our earlier note on [the substation wait](https://www.sotkn.com/markets/china/china-mobile-ai-supernodes-substation-wait-november-2026/).

## What dates test this next?

- 14 December 2026 — China Mobile’s second supernode bids open; a read on server pricing that tenants pass to landlords.
- Mid to late December 2026 — NEA November power data for internet data services.
- Fourth quarter 2026 — VNET’s 213 MW of deliveries and GDS’s 1 GW bookings target.
- Early 2027 — GDS C-REIT injection and convertible bond redemption.
- Full-year 2026 results (early 2027) — actual capex payables at GDS and VNET.

GDS and VNET releases and calls, Nov 2026; China Mobile tender notice (see our 23 Nov note). Plans and procedure, not outcomes.

## How does this fit the rest of our notes?

If you are new to how a hall makes money, start with [the AI factory, explained](https://www.sotkn.com/explained/ai-factory-explained/) and [colocation, explained](https://www.sotkn.com/explained/colocation-explained/). All our China notes are on [China Markets](https://www.sotkn.com/markets/china/). The data-centre layer is on [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/).

Second-order read. GDS will build about RMB12 billion of halls in 2026 but pay only about RMB8.5 billion in cash; the rest, about RMB3.5 billion on our arithmetic, becomes bills its suppliers collect later. Its new halls are 91.3% pre-committed, but customers take about 12 months to move in and pay in full. VNET shows the same gap: 1,127 MW in service, 797 MW used. Banks and power suppliers are paid now; builders and landlords wait. The stuck step is the move-in, and domestic chip supply sets its pace.

**Get the Wire.** Second Order’s free daily brief on what moved in the AI chip map. [Read the Wire →](https://www.sotkn.com/the-wire/) · [Subscribe free →](https://www.sotkn.com/#/portal/signup)

**How we check this.** GDS numbers come from its own results release of 25 November 2026 and its earnings call the same day. VNET numbers come from its release and SEC filing of 23 November and its call. Kingsoft Cloud numbers come from its SEC exhibit of 24 November. The power-use figure comes from China’s National Energy Administration. Call quotes come from published transcripts; we did not listen to the recordings. The companies did not name their customers or their suppliers. Every gap, per-megawatt figure and date sum is labelled “our arithmetic”. The references we used are listed at the end. [Our editorial standards →](https://www.sotkn.com/editorial-standards/)

## FAQ

**What did GDS announce on 25 November?**  
Its results for the quarter to 30 September 2026\. Revenue rose 10.1% to RMB3,180.1 million. Adjusted EBITDA rose 2.8% to RMB1,380.2 million. It kept its revenue and EBITDA guidance. It cut its 2026 capex guidance from RMB10,000 million to about RMB8,500 million. On the call the CFO said capex incurred in 2026 will be around RMB12 billion, and the difference will be capex payables.

**Does the capex cut mean GDS is building less?**  
Not according to the company. The CFO said the cut is a small change to when it pays its suppliers, and that there is no change to its plans or delivery. The building goes on. Part of the bill is paid later. Our arithmetic: about RMB3.5 billion of 2026 work moves into bills to be paid after year-end.

**Why is the move-in the stuck step?**  
Because a finished hall does not earn in full on day one. GDS says its contracts give customers about 12 months, on average, to move in and become fully billable. Customers move in when they have servers and chips to fill the space. Until then the landlord carries the build cost, the interest and some of the power bill.

**What did VNET add?**  
VNET reported on 23 November. It had 1,127 MW of wholesale capacity in service and 797 MW used by customers at 30 September. Our arithmetic: about 330 MW is built but not yet filled. It plans about 213 MW of new deliveries in the fourth quarter and 335 MW in the first nine months of 2027\. It also cut its 2026 capex guide, to RMB8–10 billion, citing lower build costs.

**Do US chip rules matter for these halls?**  
Both companies say their new orders are designed around domestic chips. GDS said it only targets orders that rely on domestic technologies. VNET said designs for current and next-year deliveries are matched to domestic chips. So the pace of domestic chip supply, not imported chips, sets how fast these halls fill.

**Is this investment advice?**  
No. Education only. It maps who gets paid and which step is stuck. It is not a recommendation to buy or sell any security, and we leave out price targets and ratings on purpose.

---

### References

Outbound links below are nofollow. We list only the sources actually used. Internal sotkn.com links in the body are separate.

1. GDS Holdings Limited (Nasdaq: GDS; HKEX: 9698), press release: GDS Holdings Limited Reports Third Quarter 2026 Results, 25 Nov 2026\. [gdsholdingsltd.gcs-web.com](https://gdsholdingsltd.gcs-web.com/news-releases/news-release-details/gds-holdings-limited-reports-third-quarter-2026-results/?ref=sotkn.com) — revenue, adjusted EBITDA, margins and the utility-cost explanation, area committed, in service, under construction and utilised, commitment and pre-commitment rates, cash, debt, new financing and the capex guide cut from RMB10,000 million to about RMB8,500 million.
2. GDS Holdings, third quarter 2026 earnings call (transcript, The Motley Fool), 25 Nov 2026\. [fool.com](https://www.fool.com/earnings/call-transcripts/2026/11/25/gds-gds-q3-2026-earnings-call-transcript/?ref=sotkn.com) — 686 MW of bookings in nine months and the \~1 GW target, the backlog bridge to 1.15 GW and over 2.4 GW of billings by end-2028, capex incurred of about RMB12 billion versus RMB8.5 billion paid with the difference in capex payables, 12-month move-in, utilisation dipping into the 70s, domestic-technology orders, net debt to 2028 and the C-REIT injection.
3. VNET Group, Inc. (Nasdaq: VNET), press release: VNET Reports Unaudited Third Quarter 2026 Financial Results, 23 Nov 2026\. [ir.vnet.com](https://ir.vnet.com/news-releases/news-release-details/vnet-reports-unaudited-third-quarter-2026-financial-results/?ref=sotkn.com) — revenue, wholesale revenue, gross profit and margin, adjusted cash gross margin, adjusted EBITDA, wholesale capacity in service (1,127 MW) and utilised (797 MW).
4. VNET Group, Inc., Form 6-K, SEC EDGAR, Filed 23 Nov 2026\. [sec.gov](https://www.sec.gov/Archives/edgar/data/1508475/000110465926130769/tm2630453d1%5F6k.htm?ref=sotkn.com) — the filed copy of the third quarter 2026 results release.
5. VNET Group, third quarter 2026 earnings call (transcript, The Motley Fool), 23 Nov 2026\. [fool.com](https://www.fool.com/earnings/call-transcripts/2026/11/23/vnet-vnet-q3-2026-earnings-call-transcript/?ref=sotkn.com) — the 922 MW of 2026 orders and their delivery years, 213 MW due in the fourth quarter, the capex guide cut to RMB8–10 billion and build cost below RMB20 million per MW, loan pricing, the Wulan private REIT follow-on, designs matched to domestic chips and the take-or-pay clause.
6. Kingsoft Cloud Holdings Limited (Nasdaq: KC; HKEX: 3896), Exhibit 99.1 to Form 6-K: Unaudited Third Quarter 2026 Financial Results, SEC EDGAR, 24 Nov 2026\. [sec.gov](https://www.sec.gov/Archives/edgar/data/1795589/000110465926131294/tm2630350d1%5Fex99-1.htm?ref=sotkn.com) — AI cloud gross billings of RMB1,683 million, revenue growth, IDC costs up 36.7% on rack services and short-term equipment rental, and RMB6.2 billion of quarterly cash capex.
7. Kingsoft Cloud, third quarter 2026 earnings call (transcript, The Motley Fool), 24 Nov 2026\. [fool.com](https://www.fool.com/earnings/call-transcripts/2026/11/24/kingsoft-kc-q3-2026-earnings-call-transcript/?ref=sotkn.com) — ecosystem and non-ecosystem AI billings growth.
8. DCD (DatacenterDynamics), GDS Holdings posts 10 percent net revenue increase YoY, revises down capex expectations, 25 Nov 2026\. [datacenterdynamics.com](https://www.datacenterdynamics.com/en/news/gds-holdings-posts-10-percent-net-revenue-increase-yoy-revises-down-capex-expectations/?ref=sotkn.com) — independent summary of the GDS capex revision in US dollar terms.
9. National Energy Administration of China, 2026 January–October electricity consumption release, 23 Nov 2026\. [nea.gov.cn](https://www.nea.gov.cn/20261123/c7b24ed8e9f84139bfdb5dc4a37325e2/c.html?ref=sotkn.com) — internet data services power use of 9.9 billion kWh in October (+34.7%) and 89.2 billion kWh in January–October (+40.8%).
10. Reuters (via Investing.com), US chip curbs will slow Asia data-center investment, Fitch says, 26 Nov 2026\. [investing.com](https://www.investing.com/news/stock-market-news/us-chip-curbs-will-slow-asia-datacenter-investment-fitch-says-5052417?ref=sotkn.com) — Fitch’s view that China-focused operators may have to keep using existing chips and that near-complete projects can slip if chips or eligible customers are not confirmed.

Not investment advice. Do your own research. Education only. Map of who gets paid and which step is stuck — not a buy list.