# 52,160 AI Cards, No Price Yet: Who Gets Paid While China Mobile’s Second Supernode Order Waits for 14 December
- URL: https://www.sotkn.com/markets/china/china-mobile-52160-cards-supernode-tender-november-2026/
- Published: 2026-11-23T08:58:44.000Z
- Updated: 2026-11-23T08:58:44.000Z
- Description: On 20 November China Mobile put 52,160 AI supernode cards out to tender, two and a half times its first batch. It set a price cap but did not publish it, and bids open on 14 December. Until then the price and the winners are blank. That is the stuck step.
- Author: Sean
- Tags: #market-china, Markets, #layer-ai-data-centers, #layer-semiconductors

*China Mobile wants 52,160 more AI cards. On 20 November it put them out to tender, two and a half times the size of its first batch in September. It set a top price but did not print it. Bids open at 9 a.m. on 14 December. Until then, nobody outside knows who wins, how many cards each gets, or what they will be paid. The order is real. The money has no name on it yet. That is the stuck step.*

**CHINA PULSE** · AI DATA CENTERS · SEMICONDUCTORS · Data as at 23 Nov 2026 (China Mobile tender notice of 20 Nov; first-batch notice of 28 Oct; NEA power data of 23 Nov) · Next update: the 14 December bid opening and the winner list that follows  
**Affects:** [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/) · [Semiconductors](https://www.sotkn.com/stack/semiconductors/) — Markets: [China](https://www.sotkn.com/markets/china/) · [US](https://www.sotkn.com/markets/us/)

**In short:** On 20 November 2026 China Mobile opened a second tender for AI supernode equipment: 52,160 cards in one lot, six to seven winners, makers only. The first batch, 20,480 cards, drew five winners whose bids all sat near RMB11.6–11.7 billion, about RMB570,000 a card. At those prices the new batch would be about RMB29.5–29.8 billion before tax, our arithmetic. The price cap is not public and bids open on 14 December. Stuck step: the price and the winner list. Map of who gets paid — not a buy list.

Education only, not advice to buy or sell any security. RMB is the Chinese yuan. An “AI card” here means one AI accelerator, the chip that does the AI maths, counted the way the tender counts it. A kilowatt-hour (kWh) is a unit of electricity used over time. Our own sums are labelled. On 11 November we wrote about China Mobile’s 2027 spending plan and the substation wait behind its new halls ([4,096 cards in 30 days, a substation in 18 months](https://www.sotkn.com/markets/china/china-mobile-ai-supernodes-substation-wait-november-2026/)). This note does not repeat that. It is about the new tender and the blank space in it: price, winners and shares.

### The numbers that matter this week

Second batch, notice 20 Nov

52,160 cards

One lot · 6–7 winners · makers only

New

First batch, Sep tender

20,480 cards

Five winners · 448 switches · 82 storage sets

Delivering

First-batch bids

RMB11.60–11.70bn

All five within 0.9%\* · about RMB570k a card

Tight

Second batch at first-batch prices

\~RMB29.5–29.8bn

Before tax · our arithmetic, not a stated value

Estimate\*

Data-service power, Jan–Oct

89.2bn kWh

Up 40.8% on a year · NEA, 23 Nov

Rising

The gate

14 Dec, 09:00

Price cap unpublished · winners unnamed

Stuck step

China Mobile tender notice CMCC20260500304, 20 Nov 2026; first-batch candidate notice of 28 Oct 2026 as reported by C114 and OFweek; National Energy Administration, 23 Nov 2026\. \*Our arithmetic. Status chips are Second Order’s read.

**On this page:** [Why it matters](#why-it-matters) · [What happened](#what-happened) · [What is a supernode?](#what-is-a-supernode) · [The rules](#tender-rules) · [First batch](#first-batch) · [Price and shares](#price-ladder) · [Our math](#our-math) · [Halls and power](#halls-and-power) · [Who gets paid](#money-goes) · [What is stuck?](#still-stuck) · [Dates next](#dates) · [FAQ](#faq)

## Why does one telecom’s tender matter for China’s AI build?

Think of a city that orders 500 new buses. Everyone knows the buses are coming. But until the city opens the sealed bids, the bus makers do not know who builds how many, or at what price. The factories cannot hire for it. The parts suppliers cannot plan. The order exists, but nobody can book it yet.

That is where China Mobile’s second AI tender sits today. China Mobile is the biggest of China’s three state telecom operators. It now buys AI computers in large, public batches, and it publishes the rules, the sizes and, later, the winning bids. That makes its tenders one of the few clear windows into what China’s AI hardware costs and who makes it.

Most AI spending in the world is hard to see. A cloud company buys chips under private contracts and reports one big capital spending number each quarter. A state operator’s tender is different. It names a card count, a timetable and, at the end, a price per bidder. For anyone mapping who gets paid in China’s AI build, that is rare, hard data.

It also matters because of what kind of chips these are. China cannot buy the newest US AI chips freely, and our recent notes have followed how its labs and clouds work around that ([the licence rule on offshore chips](https://www.sotkn.com/markets/china/china-remote-access-rule-offshore-chips-license-november-2026/), [Alibaba waiting for its own chips](https://www.sotkn.com/markets/china/china-alibaba-cloud-growth-own-chips-november-2026/)). A tender this size, aimed at makers of complete supernode systems, shows where the home-grown hardware is being sold in bulk.

## What happened this week?

On 20 November 2026 China Mobile Communications Co., Ltd. published a tender notice for the second batch of its “2026–2027 new-generation AI supernode equipment”. The tender number is CMCC20260500304\. The buyer is China Mobile itself, and the tender agent is China Posts and Telecom Equipment Group. The notice says the money is the operator’s own and is already in place.

The headline is the size: 52,160 AI cards, bought as one lot. The first batch, tendered at the end of September, was 20,480 cards. Trade site C114 reported the new tender on 21 November and OFweek followed on 23 November. Neither the notice nor China Mobile gave a value.

- 20 November: China Mobile publishes the second-batch notice for 52,160 AI supernode cards, with six to seven winners.
- 21 November, 06:30: the tender documents become available, free of charge, through China Mobile’s electronic purchasing system.
- 23 November: the National Energy Administration says internet data services used 89.2 billion kWh in January–October, up 40.8%.
- 26 November, 07:00: the document window closes. Firms that have not taken the documents by then cannot bid.
- 2 December, 17:00: deadline for bidders to upload supplier information for China Mobile’s check, which feeds part of the scoring.
- 14 December, 09:00: bids close and are opened online at the same moment.

Two other numbers landed in the same week. On 20 November, at the World Computing Conference in Changsha, an official from a government research centre said China had 52 computing facilities with more than 10,000 AI chips each by the end of September, Xinhua reported. And on 15 November the city of Ulanqab in Inner Mongolia said 30 of its 34 approved computing projects had started building. We come back to both below, because a card order is only half of the picture. The cards need a hall and power.

## What is an AI supernode, in plain words?

A normal AI cluster is many servers joined by a network. Each server holds eight or so chips. The chips inside one server talk fast; chips in different servers talk more slowly over the network. A supernode tries to remove that gap. It wires hundreds of chips together so tightly that software can treat them as one very large computer, with one shared pool of memory. We explain the idea in [rack-scale AI, explained](https://www.sotkn.com/explained/rack-scale-ai-explained/) and [scale-up versus scale-out](https://www.sotkn.com/explained/scale-up-vs-scale-out/).

C114 describes the industry’s working definition the same way: many compute nodes joined by very fast links, with memory that can be addressed across the whole block, so that it looks like one machine. That is why a supernode is sold as a system, not as loose chips. The buyer gets the chips, the links between them, memory, storage, cooling and the software that runs it all.

Why would a telecom operator want this? Mostly for inference, which means running AI models for users rather than training them. Inference needs quick answers for many people at once. C114 says operators are moving from building mainly for training to building mainly for inference. That fits our explainers on [training versus inference](https://www.sotkn.com/explained/ai-training-vs-inference/) and [who sells AI inference](https://www.sotkn.com/explained/who-sells-ai-inference/).

One caution. A “card” in this tender is the unit China Mobile counts. The notice does not name a chip, a chip maker or a setup in the public text; those sit in the technical chapter of the tender documents, which only registered bidders can read. So when we talk about price per card below, it is the price of a complete system divided by its card count, not the price of a chip.

## What do the tender rules say?

The rules matter because they decide who can win. Here is what the 20 November notice sets out, in plain words.

Size and shape

Cards52,160, one lot

Winners6 to 7

SharesSet by the scoring rules

Price capYes, not published

Who may bid

Bidder typeSupernode makers only

AgentsNot accepted

ConsortiaNot accepted

Linked firmsCannot both bid

Promises

Full offerEvery standard setup, one plan

Minimum supplyAt least 30% of each setup

MoneyBuyer’s own, in place

Supplier checkUpload by 2 Dec, 17:00

China Mobile tender notice CMCC20260500304, 20 Nov 2026\. “Setup” is our plain word for the notice’s “typical configuration”.

Three rules stand out. First, makers only. A bidder that is not the maker counts as an agent and is out, unless the maker is its own subsidiary. That keeps out traders who would buy systems and resell them.

Second, the 30% promise. Each bidder must promise it can supply at least 30% of each standard setup in the lot. On a 52,160-card lot, if there were just one setup, that would be about 15,650 cards per bidder, our arithmetic. That is a big promise. Only firms with factory space, parts and chip supply in hand can make it honestly. OFweek’s read was blunt: after these rules, not many firms can take the order at all.

Third, the hidden price cap. Any bid above the cap is thrown out. Bidders know the cap from the documents. Outsiders do not. That is normal for this kind of tender, but it means the public will not see a value until the bids are opened.

## What happened in the first batch?

![Chart: China Mobile AI supernode cards by batch: first batch 20,480, second batch 52,160, both batches 72,640](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/china-mobile-52160-cards-supernode-tender-november-2026-shift.png)

The second batch is 2.5 times the first. · Education only.

The first batch is the best guide to the second. China Mobile tendered it at the end of September: 20,480 AI supernode cards, plus 448 lossless Ethernet switches of the RoCE type and 82 storage sets. Bids were opened on 26 October. On 28 October China Mobile listed five winning candidates.

That was quick. About four weeks from notice to opening, then two days to a winner list. If the second batch moves at the same pace, the winner list could come within days of 14 December. That is our reading of the first batch, not a date China Mobile has given.

Delivery was also quick. Dahua Technology, whose unit Zhejiang Huaqi won 4,096 cards, told the Shenzhen exchange on 3 November that its share was worth about RMB2.63 billion including tax, with delivery within 30 days, and that the formal contract was not yet signed. We covered that award in our [11 November note](https://www.sotkn.com/markets/china/china-mobile-ai-supernodes-substation-wait-november-2026/). The point for today is that a winner in this format can be shipping within weeks of the list.

China Mobile’s chairman Chen Zhongyue also gave the wider frame at the operator’s network conference in early November, as C114 recounts. He said three gigawatt-level computing parks broke ground this year with about 1.5 GW of capacity expected, two more follow next year for seven in total, and 2027 purchasing will top RMB500 billion, of which computing is more than RMB100 billion. We wrote up that plan on 11 November, so we only use it here as the yardstick for the new tender.

## Why were the prices so close and the shares so far apart?

![Chart: China Mobile first AI supernode batch, card shares by winner: 6,144, 5,120, 4,096, 3,072 and 2,048 cards, while all five bids sat between RMB11.60 and 11.70 billion](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/china-mobile-52160-cards-supernode-tender-november-2026-print.png)

Same price, very different shares. Shares as % are our arithmetic. · Education only.

This is the most useful part of the first batch. Each of the five winners bid for the whole 20,480-card lot. Their bids were almost the same. Their shares were not.

First batch: bid for the whole lot, and cards won

Sichuan Huakun ZhenyuRMB11.702bn · 6,144 cards (30%\*)

PowerLeader (Baode)RMB11.599bn · 5,120 cards (25%\*)

Zhejiang Huaqi (Dahua unit)RMB11.638bn · 4,096 cards (20%\*)

BaixinRMB11.702bn · 3,072 cards (15%\*)

Digital China KuntaiRMB11.666bn · 2,048 cards (10%\*)

First-batch candidate notice of 28 Oct 2026, as reported by OFweek, 23 Nov 2026\. \*Share of 20,480 cards, our arithmetic.

Look at the spread. The highest bid was RMB11.702 billion and the lowest RMB11.599 billion. The gap is about RMB103 million, under 1% of the lot, our arithmetic. Per card, the bids work out at about RMB566,000 to RMB571,000\. In a tender with a price cap and only a few qualified makers, everyone lands close to the line.

Now look at the shares. They step down in neat fives: 30%, 25%, 20%, 15% and 10% of the cards, our arithmetic. The top winner got three times the cards of the fifth. So the money is not split by price. It is split by rank, and rank comes from the full score, which also weighs technical marks and supplier checks.

One more check helps. Dahua said its 4,096 cards were worth about RMB2.63 billion including tax. That is about RMB642,000 a card. Its unit’s whole-lot bid was RMB11.638 billion, about RMB568,000 a card. Add China’s standard 13% value-added tax to the second number and you get almost exactly the first, our arithmetic. So the public bids look like prices before tax, and the amounts winners book with tax are about 13% higher. That is our reading of two public numbers, not a statement by China Mobile.

Who are these firms? Trade press says most of them build on Huawei’s Kunpeng processors and Ascend AI chips. Huakun Zhenyu, Huaqi and Digital China’s Kuntai unit are named as part of that line. OFweek adds that PowerLeader is the subject of a planned 65.47% stake purchase by Huibo Yuntong, and that Kuntai belongs to Digital China. In other words, a state telecom order is pulling a set of server makers, some from outside the old server business, into the home-grown AI supply chain.

For the chip side, see our notes on [what Huawei does](https://www.sotkn.com/stack/hyperscalers/what-does-huawei-do/) and on the [Ascend 950DT 10,000-card pool](https://www.sotkn.com/markets/china/china-ascend-950dt-10000-card-pool-october-2026/). The tender text itself does not name a chip, so we do not claim which chips these 52,160 cards will be.

## What could the second batch be worth?

China Mobile has not said. Here is a careful estimate, with every step shown. It rests on one big assumption: that the second batch costs about the same per card as the first. Trade press itself warns that may not hold.

Our arithmetic, at first-batch prices

Cards, second batch52,160

Before tax, per cardRMB566k–571k

Before tax, whole lot\~RMB29.5–29.8bn

With 13% VAT\~RMB33.4–33.7bn

Second vs first batch2.55x the cards

Both batches72,640 cards

Our arithmetic on first-batch bids reported by OFweek and C114\. C114 and OFweek give their own static estimate of close to RMB30 billion (OFweek: about RMB29.7 billion). Not a stated value.

So the second batch could be about RMB30 billion before tax. Set that against the chairman’s plan for more than RMB100 billion of computing spend in 2027\. On those numbers, one tender would be up to about 30% of a year’s computing budget, our arithmetic. OFweek reached the same rough share. It is a large slice for one purchase.

Why might the real price differ? OFweek lists the reasons. The second batch’s links between chips, its storage and its liquid cooling have not been disclosed. The first batch came with switches and storage; the public text of the second batch only lists cards. More winners, six or seven instead of five, can also change the price. And a bigger lot gives the buyer more pull on price, while tight chip supply pushes the other way. We do not know which wins. That is exactly why 14 December matters.

One more sum, for scale only. If the top winner again gets 30% of the cards, that would be about 15,650 cards. At first-batch prices that is close to RMB9 billion before tax for one firm, our arithmetic. The bottom of the ladder could get a few thousand cards. The real shares depend on the second batch’s scoring rules, which are not public.

## Where will 52,160 cards go, and is there power for them?

A card order is only half the picture. Each card needs a rack, a hall, cooling and a steady power line. We wrote on 11 November about the wait for substations behind new halls. This week brought two fresh signals on the hall and power side.

First, the power meter. On 23 November the National Energy Administration said internet data services used 89.2 billion kWh in January to October 2026, up 40.8% on a year earlier. The January to September figure was 79.3 billion kWh. So October alone was about 9.9 billion kWh, our arithmetic from the two totals, a touch above September’s 9.8 billion. Total power use in China rose 3.7% over the same ten months. Data services are about 1% of all electricity, but they grow about eleven times faster, our arithmetic.

That growth rate has been steady near 40% all year, which is what you would expect if new halls keep switching on. We first tracked this line in our [August data-services note](https://www.sotkn.com/markets/china/china-data-services-power-august-2026/), and the gap between compute and power growth in [compute up 146%, power up 35%](https://www.sotkn.com/markets/china/china-ai-compute-146-percent-power-35-percent-october-2026/). The NEA also said on 30 October that it expects computing to add more than 100 billion kWh of demand a year to 2030, reaching about 800 billion kWh. For how much one AI hall draws, see [how much power an AI data centre uses](https://www.sotkn.com/explained/how-much-power-does-an-ai-data-center-use/).

Second, the building site. Inner Mongolia Daily reported on 15 November that Ulanqab, a cold city in Inner Mongolia that has become a big computing hub, has 34 approved computing projects. Together they carry RMB130.8 billion of approved investment and 6.6 GW of IT load. Thirty have started building and the last four were due to start in November. Spending so far is RMB30.4 billion, of which RMB15.5 billion came this year.

Put those two numbers side by side. About 23% of the approved money has been spent, our arithmetic. The halls are being built, but most of the work is still ahead. The average project is about 194 MW of IT load, also our arithmetic. One example in the report: a China Unicom site with RMB2 billion of investment, about 80 MW of IT load, three computing buildings and its own 110 kV substation. It started building on 26 September and aims to top out its first building by 15 December.

So the timing lines up in an awkward way. China Mobile’s second batch opens bids on 14 December. If winners ship as fast as the first batch did, cards could start arriving early in 2027\. Some halls will be ready for them; many are still structures in the cold. A card that arrives before its hall is inventory, not income. Our explainer on [how long an AI data centre takes to build](https://www.sotkn.com/explained/how-long-does-it-take-to-build-an-ai-data-center/) walks through each step, and our note on [cluster acceptance](https://www.sotkn.com/explained/gpu-cluster-acceptance-explained/) explains why money only flows fully once the system is switched on and signed off.

The wider count points the same way. Xinhua reported that China had 52 facilities with more than 10,000 AI chips each at the end of September. A single 52,160-card order is, on paper, enough for about five such facilities, our arithmetic. Where those cards land, and when they are plugged in, is the next question after 14 December.

## Who gets paid while the second batch waits?

![Infographic: who gets paid while China Mobile's second supernode tender waits for 14 December, from first-batch makers and the chip stack to hall and power builders, with the blank price and winner list as the stuck step](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/china-mobile-52160-cards-supernode-tender-november-2026-infographic.png)

Who gets paid / stuck step while the second batch waits. · Education only.

Here is the map, from the money that is already moving to the money that is waiting for a name.

Gets paid now

First-batch makersDelivering 20,480 cards

Chip and software stackBehind those systems

Switch and storage makers448 switches, 82 sets

Hall and power buildersUlanqab: RMB30.4bn spent

Waits for 14 December

Second-batch bidders52,160 cards, unassigned

Their parts suppliersNo firm volumes yet

China Mobile itselfPrice not locked

Waits for a hall

Cards that arrive earlyInventory until switched on

Projects still building\~77% of Ulanqab money ahead\*

Second Order’s read of the tender notices, the first-batch results and the 15 Nov Ulanqab report. \*Our arithmetic.

The first-batch makers are paid first. They won their shares in October, and at least one said it would deliver within 30 days. Their bills, with tax, come to roughly RMB13 billion across the lot, our arithmetic on the bid level plus VAT. That money flows now.

Behind them, the chip and software suppliers are paid. Trade press places most of these systems on Huawei’s Kunpeng and Ascend line. Whoever makes the chips inside the 20,480 cards is paid as the makers build. The same goes for the switch and storage makers in the first batch’s 448 switches and 82 storage sets.

The builders of halls and power links are paid as the sites rise. In Ulanqab alone, RMB15.5 billion went into computing projects this year. That money buys steel, concrete, cooling plant, transformers and grid work long before a single card arrives. Our explainer on [who makes AI cluster networking](https://www.sotkn.com/explained/who-makes-ai-cluster-networking/) covers the switch side of the same story.

Who waits? Every firm bidding for the second batch. Until 14 December they cannot book the order, set a production plan or promise volumes to their own suppliers. China Mobile waits too, in a different way: it does not know its price until the bids are opened. And any card that arrives before its hall is ready waits as inventory.

## What is stuck, and what would change our read?

The stuck step is the price and the winner list. China Mobile has said how many cards it wants and when bids open. It has not said what it will pay or who will supply. Until 9 a.m. on 14 December, the RMB30 billion or so in this order, by our arithmetic, has no name on it.

After that, the stuck step moves. Once winners are named, the question becomes whether chips, parts and halls can keep up with a 52,160-card order. The first batch delivered in about a month. A lot two and a half times bigger is a harder test.

What would make us more positive? Bids that land near the first batch’s level, showing stable prices at scale. A quick winner list, as in October. Winners confirming delivery inside a few weeks. And more Ulanqab-style reports of halls topping out on time.

What would make us more cautious? A delay to the bid opening. Fewer than six winners, which would hint that few makers can meet the 30% promise. Bids far above the first batch, which would suggest chip or parts costs are rising. Or a gap between cards delivered and halls ready, which would show up as slower growth in the NEA’s data-service power line.

For how the stuck step tends to move from one link to the next, see [where the stuck step moves](https://www.sotkn.com/analysis/where-does-the-stuck-step-move/).

## What dates test this next?

![Calendar of dates: 29 September first-batch notice, 26 October bids opened, 28 October winners listed, 20 November second-batch notice, 2 December supplier check, 14 December bids open, early 2027 first deliveries (our reading)](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/china-mobile-52160-cards-supernode-tender-november-2026-calendar.png)

Clocks that test the read. · Education only.

- 29 September 2026 — first-batch notice: 20,480 cards, 448 switches, 82 storage sets (done).
- 26 October 2026 — first-batch bids opened (done).
- 28 October 2026 — five winning candidates listed (done).
- 20 November 2026 — second-batch notice: 52,160 cards, six to seven winners (done).
- 26 November 2026, 07:00 — document window closes.
- 2 December 2026, 17:00 — supplier information deadline.
- 14 December 2026, 09:00 — bids close and open: the price and ranking become known to China Mobile.
- Mid-December 2026 — winner list, if it keeps the first batch’s two-day pace (our reading, not a stated date).
- Early 2027 — first second-batch deliveries, if winners ship as fast as in batch one (our reading).

China Mobile tender notices of 29 Sep and 20 Nov 2026; first-batch results as reported by C114 and OFweek; Dahua filing of 3 Nov 2026\. Plans, not facts.

## How does this fit the rest of our notes?

It continues a China line we have followed through the autumn. China Mobile’s spending plan and the substation wait came first ([the 11 November note](https://www.sotkn.com/markets/china/china-mobile-ai-supernodes-substation-wait-november-2026/)). The tool and wafer side sits in [SMIC’s 16–24 month tool wait](https://www.sotkn.com/markets/china/china-smic-q3-tool-lead-times-november-2026/). The cloud side sits in [Baidu’s third quarter](https://www.sotkn.com/markets/china/china-baidu-q3-gpu-yuan-unnamed-november-2026/) and [Alibaba’s cloud growth](https://www.sotkn.com/markets/china/china-alibaba-cloud-growth-own-chips-november-2026/). For the other end of the world’s AI hardware money, see today’s US note on [NVIDIA’s US$390 billion supply book](https://www.sotkn.com/markets/us/us-nvidia-supply-book-memory-unnamed-november-2026/). For what a cluster is in the first place, see [GPU clusters, explained](https://www.sotkn.com/explained/gpu-cluster-explained/). All our China notes are on [China Markets](https://www.sotkn.com/markets/china/).

Second-order read. China Mobile wants 52,160 more AI cards, 2.5 times its first batch. At first-batch prices that is about RMB30 billion before tax, our arithmetic. First-batch makers, the chip stack behind them and hall builders are paid now. The stuck step is the blank price and winner list until bids open on 14 December. Watch the bid level and the winner count.

**Get the Wire.** Second Order’s free daily brief on what moved in the AI chip map. [Read the Wire →](https://www.sotkn.com/the-wire/) · [Subscribe free →](https://www.sotkn.com/#/portal/signup)

**How we check this.** The second-batch rules and dates come from China Mobile’s tender notice of 20 November 2026 (tender no. CMCC20260500304), read in a republished copy because the operator’s own procurement site needs a login. The first-batch bids and card shares come from the public candidate notice as reported by C114 and OFweek, and the Dahua figure from Dahua’s own stock-exchange filing. Power-use numbers are the National Energy Administration’s. The Ulanqab figures are the city’s, as reported by Inner Mongolia Daily. China Mobile has not published a value for the second batch; every value we give for it is labelled “our arithmetic” and rests on the first batch’s prices. The references we used are listed at the end. [Our editorial standards →](https://www.sotkn.com/editorial-standards/)

## FAQ

**What did China Mobile put out to tender on 20 November?**  
A second batch of AI supernode equipment for 2026–2027: 52,160 AI cards in one lot, with six to seven winners. Only makers of supernode equipment may bid. There is a price cap, but the notice does not print it. Bids close and open at 09:00 on 14 December 2026.

**What is a supernode?**  
A supernode is a big block of AI chips wired together so tightly that software can treat it like one very large computer. It is sold as a system: the chips, the fast links between them, memory, storage, cooling and the management software.

**How much could the second batch be worth?**  
China Mobile has not said. If the first batch’s prices held, 52,160 cards would come to about RMB29.5–29.8 billion before tax. That is our arithmetic on the first batch’s bids. Trade press warns the second batch may use different setups, so the real figure will only be known when the bids are opened.

**What is the stuck step?**  
The price and the winner list. Until bids open on 14 December, nobody outside the tender knows who will supply the cards, at what price, or in what shares. Bidders cannot book the order and their suppliers cannot plan for it.

**Who gets paid now?**  
The five first-batch winners, which are delivering 20,480 cards. The chip and software stack behind them, which trade press says is mostly Huawei’s Kunpeng and Ascend line. And builders of the halls and power links that these cards go into.

**Is this investment advice?**  
No. Education only. It maps who gets paid and which step is stuck. It is not a recommendation to buy or sell any security, and we leave out price targets and ratings on purpose.

---

### References

Outbound links below are nofollow. We list only the sources actually used. Internal sotkn.com links in the body are separate.

1. China Mobile Communications Co., Ltd., tender notice for the 2026–2027 new-generation AI supernode equipment, second batch (tender no. CMCC20260500304), as republished by a tender listing site, 20 Nov 2026\. [bj.zhiliaobiaoxun.com](https://bj.zhiliaobiaoxun.com/article/120215937?ref=sotkn.com) — the 52,160 cards, one undivided lot, six to seven winners, the unpublished price cap, the makers-only and no-consortium rules, the 30% minimum supply commitment, the document window, the 2 December supplier check and the 14 December bid opening.
2. C114, 中国移动启动第二批新一代AI超节点集采 (China Mobile starts second AI supernode purchase), 21 Nov 2026\. [c114.com.cn](https://www.c114.com.cn/news/118/a1321457.html?ref=sotkn.com) — the second-batch size, the first-batch scope and prices, the chairman’s park and 2027 spending remarks, and China Mobile’s first-half 2026 compute figures.
3. OFweek AI, 央企再度开启AI算力集采 (state firm opens another AI compute purchase), 23 Nov 2026\. [ofweek.com](https://www.ofweek.com/ai/2026-11/ART-201714-8120-30713018.html?ref=sotkn.com) — the five first-batch bids and card shares, the 26 October bid opening, the static estimate for the second batch and its caveats, and the ownership notes on two winners.
4. C114, China Mobile AI supernode purchase: five winning candidates, 28 Oct 2026\. [c114.com.cn](https://www.c114.com.cn/news/118/a1320000.html?ref=sotkn.com) — the 28 October candidate notice and the first batch’s 448 switches and 82 storage sets.
5. Dahua Technology (Shenzhen Stock Exchange 002236), Announcement 2026-079, 3 Nov 2026\. [static.cninfo.com.cn](http://static.cninfo.com.cn/finalpage/2026-11-03/1225653806.PDF?ref=sotkn.com) — the subsidiary’s 4,096-card share at about RMB2.63 billion including tax, the 30-day delivery and the unsigned contract.
6. Yicai, National Energy Administration: January–October electricity use up 3.7%, 23 Nov 2026\. [yicai.com](https://www.yicai.com/brief/103450504.html?ref=sotkn.com) — October and January–October power use, including 89.2 billion kWh for internet data services, up 40.8%.
7. National Energy Administration, January–September 2026 electricity use, 21 Oct 2026\. [nea.gov.cn](https://www.nea.gov.cn/20261021/bab7b2135e424adeaacf169cb40115ae/c.html?ref=sotkn.com) — the January–September figure for internet data services, 79.3 billion kWh, used for our October sum.
8. Inner Mongolia Daily via People’s Daily Online, 乌兰察布算力项目建设忙 (Ulanqab compute projects busy), 15 Nov 2026\. [nm.people.com.cn](http://nm.people.com.cn/n2/2026/1115/c192247-41751249.html?ref=sotkn.com) — the 34 approved projects, 6.6 GW of IT load, RMB130.8 billion approved and RMB30.4 billion spent, and the China Unicom site with its own 110 kV substation.
9. Xinhua, China’s intelligent computing expected to top 90 pct of total computing capacity, 21 Nov 2026\. [english.news.cn](https://english.news.cn/20261121/a9ee630207e74af1a3f9084a3a5ba3fe/c.html?ref=sotkn.com) — the 52 facilities with more than 10,000 AI chips and the inference share forecast for 2030.
10. National Energy Administration, press conference remarks by Tan Hongjiang, 30 Oct 2026\. [nea.gov.cn](https://www.nea.gov.cn/20261030/417c3369620343cc9584ce66621619ed/c.html?ref=sotkn.com) — the forecast that compute power use rises by more than 100 billion kWh a year to about 800 billion kWh in 2030.

Not investment advice. Do your own research. Education only. Map of who gets paid and which step is stuck — not a buy list.