# 24–27% Spare Power on Paper: Who Gets Paid While Malaysia’s Data Halls Outrun Its Power Plants
- URL: https://www.sotkn.com/markets/malaysia/malaysia-reserve-margin-data-centres-power-plants-november-2026/
- Published: 2026-11-22T09:00:39.000Z
- Updated: 2026-11-22T09:00:39.000Z
- Description: On 18 November the government told Parliament that Peninsular Malaysia’s spare power will be 24–27% in 2027–2035. The same day an MP said data halls take 1–2 years to build and gas plants 4–7. The plants that do not exist yet are the stuck step.
- Author: Sean
- Tags: #market-malaysia, Markets, #layer-ai-data-centers, #layer-power-energy

*Malaysia told Parliament on 18 November that it will keep 24 to 27 per cent of spare power on the grid from 2027 to 2035\. That sounds comfortable. But the same day, a former energy minister said a data hall can be built in one to two years and a gas power plant takes four to seven. The halls are on their way. The plants are not built yet. That gap is the stuck step.*

**MALAYSIA PULSE** · AI DATA CENTERS · POWER · Data as at 22 Nov 2026 (Dewan Rakyat debate of 18 Nov 2026; ministry projections reported 18 Nov; minister’s remarks of 21 Nov) · Next update: the next planning committee update (about mid-2027, our reading), or earlier news on new generation tenders  
**Affects:** [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/) — Markets: [Malaysia](https://www.sotkn.com/markets/malaysia/) · [Singapore](https://www.sotkn.com/markets/singapore/)

**In short:** On 18 November the deputy energy minister said spare power (the reserve margin) in Peninsular Malaysia is projected at 24–27% for 2027–2035\. The ministry’s own projections have data centres using 31% of electricity by 2035, up from 7% in 2026\. An MP said halls take 1–2 years and gas plants 4–7, so a crunch could last until new plants arrive around 2029\. Stuck step: power plants that do not exist yet. Map of who gets paid — not a buy list.

Education only, not advice to buy or sell any security. Power is measured in megawatts (MW) and gigawatts (GW); one GW is 1,000 MW. Energy used over time is measured in gigawatt-hours (GWh). Peak demand is the highest use on the grid at one moment. A reserve margin is spare generating capacity above that peak, shown as a share of it. Peninsular Malaysia means the mainland grid, where Johor and the Klang Valley sit. Our earlier notes covered TNB’s 9,000 MW forecast ([the 8 November note](https://www.sotkn.com/markets/malaysia/malaysia-tnb-9000mw-power-plants-november-2026/)), the charge for booked-but-unused power ([the 13 November note](https://www.sotkn.com/markets/malaysia/malaysia-booked-power-charge-gpu-disclosure-november-2026/)) and the grid queue in Johor ([the 28 October note](https://www.sotkn.com/markets/malaysia/malaysia-johor-data-centre-grid-connection-october-2026/)). This note covers what Parliament added this week.

### The numbers that matter this week

Reserve margin, 2027–2035

24–27%

Projected · planning committee, 11 Nov

Plan

Peak demand, 2026 → 2035

21.3 → 33.5 GW

Ministry projection · Peninsular Malaysia

Up 57%\*

Data centre share of electricity

7% → 31%

10,544 GWh in 2026 → 73,274 GWh in 2035

Up 7x\*

Hall vs plant build time

1–2 vs 4–7 yrs

Yeo Bee Yin, 18 Nov

Gap

Margin on 8 June (Yeo’s view)

\~13%

Effective, with one plant in maintenance

Thin day

The gate

New plants

Power that does not exist yet

Stuck step

Ministry of Energy Transition and Water Transformation, as reported by Bernama, 18 Nov 2026; Yeo Bee Yin, Dewan Rakyat, 18 Nov 2026\. \*Our arithmetic. Status chips are Second Order’s read.

**On this page:** [Why it matters](#why-it-matters) · [What happened](#what-happened) · [Reserve margin](#reserve-margin) · [Build clocks](#build-clocks) · [Official numbers](#official-numbers) · [Government answer](#government-answer) · [Yeo’s ideas](#yeo-ideas) · [Signed power](#signed-power) · [Who gets paid](#money-goes) · [Our math](#our-math) · [What is stuck?](#still-stuck) · [Dates next](#dates) · [FAQ](#faq)

## Why does a spare-power number matter for data centres?

Think of a car park next to a stadium. On a normal day a quarter of the spaces are empty, and nobody worries. Then the club announces a season of big matches, and a developer starts building three more stadiums next door. The empty spaces are the same number on paper. But on match day the car park is full, and a new car park takes years to build.

That is the worry behind this week’s debate. Spare power, the reserve margin, is how far the grid can stretch on its hardest day. For years Malaysia had plenty. Now data centres are asking for large blocks of power, and they are built much faster than the plants that feed them.

This matters to three groups at once. Data centre owners need a firm supply date before they can sign a customer. Factories and homes need the lights to stay on and the bill to stay fair. And the companies that build power plants, grid lines and batteries need to know how much will really be ordered. All three read the same number differently.

## What happened this week?

The main event was a parliamentary debate. On 18 November the Dewan Rakyat, Malaysia’s lower house, went through the budget for the Energy Transition and Water Transformation Ministry, known as PETRA. Thirty-two MPs spoke, according to Bernama, and the house approved RM5.33 billion for the ministry’s 2027 running and development spending. Two exchanges touched data centres.

First, Yeo Bee Yin, the MP for Puchong and a former energy minister, asked what the latest reserve margin is. She said grid records quoted in the press showed peak demand at about 21 GW on 8 June 2026, while the power actually available was only about 25 GW, because the Edra plant in Melaka was in scheduled maintenance. She put the effective margin that day at about 13%. She put the normal, whole-year margin at 23–24%, which she called the lowest in ten years, maybe fifteen.

Second, Deputy Minister Abdul Rahman Mohamad wound up the debate. He said the reserve margin for 2027 to 2035 is projected at 24–27%, based on the planning committee meeting of 11 November, and that the government is keeping its plans for a reliable supply for data centre growth. He also said measures to manage demand from big users, data centres included, had been identified.

- 18 November: reserve margin projected at 24–27% for 2027–2035 (deputy minister, Dewan Rakyat).
- 18 November: the connected load charge was adjusted to curb big capacity bookings, and the ultra-high voltage tariff, in force since 1 July 2025, applies to data centres above 50 kV.
- 18 November: an MP asked for the planning committee’s report to be made public again; the ministry noted the proposal.
- 18 November: the ministry’s projections put data centres at 31% of Peninsular electricity in 2035, up from 7% in 2026.
- 21 November: the investment minister said claims of a power shortage were untrue and that data centres must be kept separate from existing industry.
- 12 November: Princeton Digital Group and TNB formalised the electricity supply agreement for the JH2 campus in Johor.

The same day brought a water answer, which we cover below only briefly because we wrote it up on 1 November. The new part is the electricity: a number for the future, a worry about the present, and a report nobody outside can read.

## What is a reserve margin, and which number is right?

![Chart: Peninsular Malaysia peak demand 21.3 gigawatts in 2026 and 33.5 in 2035, and the capacity that a 24 to 27 percent reserve margin implies in 2035, about 41.5 to 42.5 gigawatts](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/malaysia-reserve-margin-data-centres-power-plants-november-2026-print.png)

Peak demand and the capacity a 24–27% margin implies. Our arithmetic. · Education only.

A reserve margin answers one question: how much spare generating capacity is there above the busiest moment? If peak demand is 100 and capacity is 125, the margin is 25%. The spare part covers plants that break, plants in maintenance, a heatwave, or a demand jump that nobody forecast.

The two sides in the debate are not quite arguing about the same thing. The government’s 24–27% is a projection for every year from 2027 to 2035\. It assumes the plants in the plan get built on time. Yeo’s 23–24% is her estimate of the margin now, and her 13% is one day, 8 June, when a large plant was offline for planned maintenance. One is a plan, one is a snapshot, and one is a bad day.

A word of caution on Yeo’s 13%. She took the numbers from press reports of grid operator records. If you only use her two rounded figures, 21 GW of demand and 25 GW of available capacity, the margin works out to about 19%, our arithmetic. So her 13% must include other outages or limits that she did not list. We cannot tell which, and the grid operator’s own record is not in front of us. We show her number as hers.

There is also a mismatch in the peaks. TNB’s chief executive said on 4 November that peak demand on the peninsula passed 22,000 MW in August 2026, the highest in the utility’s 77-year history. The ministry’s 2026 figure, quoted in the 18 November report, is 21.3 GW. The gap may be down to what is counted and when, and the planning report would settle it. It is not public, so we flag it rather than guess.

What matters for the read is the direction. A margin that is held at 24–27% while peak demand climbs by more than half means a lot of new capacity has to be built. For the basics of how power gets to a hall, see [data centre power distribution, explained](https://www.sotkn.com/explained/data-center-power-distribution-explained/), and for what a signed supply promise means, [contracted power, explained](https://www.sotkn.com/explained/contracted-power-explained/).

## Why do halls arrive faster than power?

![Chart: build clocks in years: data hall 1 to 2, TNB Green Lane grid connection about 1, older grid connection about 3, gas power plant 4 to 7](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/malaysia-reserve-margin-data-centres-power-plants-november-2026-shift.png)

Halls move in years; plants take longer. · Education only.

This is Yeo’s core point, and it is a timing point. In her words, a data centre can be built in 12 to 24 months. A gas power plant now takes four to seven years, because the world is short of the heavy equipment, such as gas turbines. She said there is a supply crunch until about 2029, when new plants are due to come online.

The grid line is a third clock, and TNB has been working to shrink it. TNB’s chief executive said on 4 November that its Green Lane pathway can cut the time to connect an eligible high-voltage data centre from about 36 months to about 12, depending on the project. TNB repeated the 12-month figure at a conference in Europe this week, according to Bernama.

But a fast connection is only a wire. The same chief executive said some connections are being delivered ahead of schedule, yet faster grid access must be backed by enough generation. His words, as reported by The Malaysian Reserve: “So the only problem right now is where to find the power.”

- A data hall: about 1–2 years to build (Yeo Bee Yin).
- A grid connection under TNB’s Green Lane pathway: about 12 months, down from about 36 (TNB).
- A gas power plant: about 4–7 years, with a global equipment squeeze (Yeo Bee Yin).
- New plants in the current plan: about 2029 (Yeo Bee Yin).

Put the clocks side by side and the shape is plain. If a hall is ordered today, it can be built by 2027 or 2028 and wired by then. A gas plant ordered today would arrive somewhere between 2030 and 2033, our arithmetic from her four-to-seven-year range. The plants that are due about 2029 were ordered earlier. Anything new has to join the queue behind them.

We have followed the equipment side before. On gas turbines, see [what happens if turbines stay booked into 2030](https://www.sotkn.com/analysis/if-gas-turbines-stay-booked-into-2030-where-cash-sticks/); on grid gear, [if big transformers stay sold out to 2029](https://www.sotkn.com/analysis/if-big-transformers-stay-sold-out-2029-where-cash-sticks/). Malaysia has no way round those global queues.

## What do the official 2035 numbers say?

The ministry’s own projections, quoted from the planning committee in a Bernama report of 18 November, are the most specific numbers we have. They are for Peninsular Malaysia only.

Data centre electricity use

202610,544 GWh, 7% of demand

203573,274 GWh, 31% of demand

Change (our arithmetic)about 6.9 times

SourcePETRA via Bernama, 18 Nov

Peak demand

202621.3 GW

203533.5 GW

Change (our arithmetic)+12.2 GW, +57%

SourcePETRA via Bernama, 18 Nov

Data centres today

Operating, Aug 202645 data centres

Supply capacity6.04 GW combined

Average (our arithmetic)about 134 MW each

SourcePETRA via Bernama, 18 Nov

Ministry of Energy Transition and Water Transformation, citing the planning committee, as reported by Bernama and published by Tenaga Nasional, 18 Nov 2026\. Supply capacity is what the grid is set up to supply, not what the halls use today.

Three things stand out. First, data centres are the main reason the numbers rise. Peak demand grows by about 57% in these projections, our arithmetic. Data centre use grows by about 62,700 GWh. Taking the ministry’s rounded 7% and 31% shares at face value, total use grows by roughly 85,000 GWh, so data centres are about three quarters of the rise. That is our arithmetic on rounded shares: a rough size, not a precise one.

Second, what the 2035 peak means for plants. If peak demand reaches 33.5 GW and the margin is 24–27%, the grid needs about 41.5 to 42.5 GW of dependable capacity in 2035, our arithmetic. That is about 8 to 9 GW more than the peak itself, kept as insurance. We cannot say how much capacity exists today on the same basis, so we do not guess how many new plants that means. The planning report would say.

Third, the 45 operating halls and their 6.04 GW. Supply capacity is the size of the connection, not the load the halls draw. Our October note on plugged-in versus used power ([5.65 GW plugged in, 1.26 GW used](https://www.sotkn.com/markets/malaysia/malaysia-data-centre-power-use-october-2026/)) showed how far apart those can be. The 2035 numbers are about actual use, which is why they matter more for plant planning.

One more number shapes the politics: 117 data centre projects had been approved by October 2026, and approved investment in data centres and cloud computing in the first half of this year reached RM95.8 billion, as Free Malaysia Today reported. That is a long list of projects asking for power.

## What did the government say it will do?

The government’s answer has four parts, taken from the deputy minister’s reply and the investment minister’s remarks three days later.

- Plan for supply. The reserve margin is projected at 24–27% for 2027–2035, based on the 11 November planning meeting.
- Manage demand. Demand-side measures for big users, data centres included, have been identified to protect the reserve margin. The ministry did not list them in the reply we read.
- Price the booking. The connected load charge was adjusted to curb excessive capacity reservations, so that data centre development costs are not passed to household customers.
- Keep data centres apart. Investment minister Johari Abdul Ghani said on 21 November that claims of a shortage were untrue, that TNB had assured him national needs could be met, and that data centre development must be kept separate from the 27 existing industrial sectors.

The charge is the sharpest tool. As we reported on 13 November, the connected load charge is the fee data centres pay to reserve grid capacity, and the plan is to raise it steeply so that developers stop booking power they will not use ([10 times the charge for empty power](https://www.sotkn.com/markets/malaysia/malaysia-booked-power-charge-gpu-disclosure-november-2026/)). The deputy minister now says it has been tiered to the same end. The tiers and the start date were not set out in the reply we read. The ultra-high voltage tariff, which covers users above 50,000 volts, has applied since 1 July 2025.

Johari’s line was blunt. “TNB has never lacked power,” he said, according to the New Straits Times, and he added that every data centre application is judged on its energy needs and what it is for before approval. That is a statement about the past and about approvals. It does not say when the next plant arrives.

Notice what the government did not say. It gave a margin for the whole nine-year span, but it did not give the plant list behind it, the year each plant arrives, or the data centre load it assumes in each year. Those are in the planning committee report. And the report is not public.

## Why does it matter that the planning report is private?

The committee that makes these projections is called JPPPET, a Malay acronym for the planning and implementation committee for electricity supply and tariff. It sits under the ministry and plans the long-term supply. Its reports used to set out the fuel mix, the capacity, the expected demand, and which plants will be added or retired. Industry used them as a common set of assumptions.

The last one made public was JPPPET 2020, covering 2021 to 2039, published in March 2021, The Edge Malaysia reported. The Energy Commission’s chief executive told the press on 8 September that public release stopped because the sector now moves so fast that the committee revisits its numbers twice a year. “We’ve seen the numbers change … If we publish and then \[after\] another six months we publish it again, it would create a lot more uncertainty,” she said. She added that the Commission is looking at ways to give more visibility.

On 18 November Yeo asked the Commission to publish the reports again. Bernama says the ministry noted the proposal. It did not promise to do so.

Why does a report matter to a data centre owner? Because the owner has to guess when power will be there. A published plant list lets lenders and customers check the guess. A private list means everyone relies on one-line statements such as “24 to 27 per cent”. That is not a charge against anyone. It is the reason our read keeps the plan and the proof apart.

## What did Yeo propose to close the gap?

Yeo did more than raise the alarm. In the same five-minute speech, as recorded in the Parliament’s Hansard, she set out several ideas. They are an MP’s proposals, not policy, but they show where the pressure points are.

- A separate wholesale electricity market for very large users, data centres included, which she welcomed the Energy Commission planning for 2029–2030\. Her reason: Malaysia should not build big plants to serve speculative demand and leave other customers holding the cost if that demand shrinks.
- Charge data centres the right price now, not from 2029–2030\. She suggested taking coal out of the base-load calculation for data centre tariffs, so that household customers keep the benefit of cheaper coal power.
- Do more than add generation under the Commission’s New Gen 25 tender. She welcomed the New Gen 25 and New Gen 26 tenders but asked for demand management as well, such as rewarding large users who cut their peak.
- Back battery storage. She said firms that install batteries qualify for a green investment tax allowance, but companies that lease batteries to factories do not qualify for the matching income tax exemption. Leasing is easier for factories that cannot pay upfront.

## What does signed power look like in practice?

It helps to see one data centre that has done its part. On 12 November Princeton Digital Group, or PDG, said it and TNB had formalised the electricity supply agreement for JH2, PDG’s second data centre campus in Johor. TNB’s chief executive and two senior TNB officers were at the event. PDG said TNB’s support had carried its first Johor campus, JH1, from development to operation, and said it hopes to work with TNB on renewable supply through the corporate renewable energy scheme, known as CRESS.

The announcement did not say how many megawatts the agreement covers, so we do not give a number. What it shows is the order of events. A supply agreement is a contract. It says TNB will supply power to the site. It is not a power plant. Our Wire on PDG’s Johor financing ([the PDG loan and 198.8 MW in Johor](https://www.sotkn.com/wire/princeton-digital-1-2b-loan-198-8-mw-johor-data-center-wire/)) covers how lenders treat a campus that has power lined up.

That is the pattern to watch. Operators with a signed agreement and a connection date are first in line. The 24 applications put on hold in October, and projects that have not started, sit behind them. When the ministry says the margin will hold at 24–27%, the real test is whether every signed agreement can be met at the same time as every new one.

For how a power supply promise differs from a power purchase contract, see [power purchase agreements, explained](https://www.sotkn.com/explained/power-purchase-agreement-explained/).

## What about the water answer from the same day?

It repeats a theme we covered on 1 November ([24 data centres on hold while Malaysia checks the water](https://www.sotkn.com/markets/malaysia/malaysia-data-centre-water-check-approvals-october-2026/)). The deputy minister said data centres in Selangor, Johor and Negeri Sembilan are projected to need 445.04 million litres of water a day by 2030\. About 19.5 million litres a day of recycled water from four sewage plants in Selangor and Johor already reduces their use of treated water. Under national water regulator rules, data centres must keep at least two days of water in reserve, put alternative sources first and pay for extra infrastructure. Existing customers keep priority.

## Who gets paid while the plants are built?

![Infographic: who gets paid while Malaysia waits for new power plants, from equipment makers and TNB to battery firms and halls with supply agreements, with the plants that do not exist yet as the stuck step](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/malaysia-reserve-margin-data-centres-power-plants-november-2026-infographic.png)

Who gets paid / stuck step while the plants are built. · Education only.

Money moves first to the people who build and supply the slow part. The sources do not say who wins which tender, so this is a map by role, not a list of names.

Gets paid now

Plant and grid buildersorders for turbines, boilers, lines, transformers

TNB, through its networkRM43bn of regulated network spending for 2025–27

Battery storage firmsif demand management and storage are backed

Halls with a signed supply dealcan sell capacity that is real

Waits

Halls without a supply datecannot give customers a go-live

Projects not yet startedsit behind approved ones

Customers booking powerpay a higher charge for empty capacity

Lenderswait for connection dates

Protected, by promise

Household customersthe ministry says data centre costs will not be passed on

27 existing industrieskept separate from data centres, per Johari

Existing water userspriority kept, per the ministry

Proofpromises to be tested by the plant list

TNB figure from its chief executive, 4 Nov 2026 (The Malaysian Reserve). Other lines from the 18 and 21 Nov 2026 reports. Role map is Second Order’s read, not a list of contract winners.

The first group is paid because the order comes before the plant. The second group waits because it cannot finish a hall without a date for power. The third group is protected by promises, and promises are only as good as the plant list behind them. That is why the privacy of the planning report matters.

## What does our own arithmetic show?

These are our sums from the published figures. They are simple on purpose, and they carry the caveats of the figures they use.

- Peak demand: 21.3 GW in 2026 to 33.5 GW in 2035 is +12.2 GW, or +57%.
- Data centre use: 10,544 GWh to 73,274 GWh is about 6.9 times.
- Capacity with a 24–27% margin on a 33.5 GW peak: about 41.5–42.5 GW.
- Time to build, from Yeo’s ranges: a gas plant ordered in late 2026 arrives about 2030–2033; a hall is built in about 2027–2028.
- On 8 June, using only her rounded 21 GW and 25 GW, the margin is about 19%, not 13%; her 13% must include other limits.

What these sums do not show is how many plants are already planned or how much of today’s capacity is firm. Those answers are in the planning report. Until it is public, the sums frame the problem but do not settle it.

## What is stuck, and what would change our read?

The stuck step is the power plants that do not exist yet. The government has given a number for spare power and a promise on supply. A hall and a grid link can be done in one to two years. A plant cannot. Until the next plants are built, the margin rests on plants that are already ordered and on how fast data centres really switch on.

What would make us more positive? A published plant list with delivery years. Results of the New Gen tenders with dates. Data centre load that comes on slower than the approvals suggest. Demand management that really cuts the evening peak. Or the 2029 plants arriving early.

What would make us more cautious? Another day like 8 June, with a large plant in maintenance and the peak close to the available supply. A slip in the 2029 plants. Approvals that run well ahead of the plant plan. Or a finding that the charge for booked power does not stop developers booking more than they will use.

## What dates test this next?

![Calendar of dates: 11 November 2026 planning committee, 18 November 2026 reserve margin answer, mid 2027 next planning update, 2028 to 2030 grid investment period, about 2029 new plants and separate wholesale market, 2035 projections](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/malaysia-reserve-margin-data-centres-power-plants-november-2026-calendar.png)

Clocks that test the read. · Education only.

- 11 November 2026 — planning committee meeting that produced the 24–27% margin (done).
- 18 November 2026 — deputy minister gives the margin in Parliament (done).
- Mid-2027 — next planning committee update, if it keeps to two reviews a year (our reading, not a stated date).
- 2028–2030 — TNB’s next regulatory period, which it says needs more network spending than the current one.
- About 2029 — new plants due online, and the separate wholesale market for large users that Yeo cites.
- 2035 — the projection year: peak 33.5 GW, data centres 31% of electricity.

Dates from the 18 and 21 Nov 2026 reports, TNB’s 4 Nov remarks and The Edge Malaysia, 8 Sep 2026\. Plans, not facts.

## How does this fit the rest of our Malaysia notes?

It joins a line we have followed since October. The grid queue came first ([Johor’s connection wait](https://www.sotkn.com/markets/malaysia/malaysia-johor-data-centre-grid-connection-october-2026/)), then the booking charge ([booked, not used](https://www.sotkn.com/markets/malaysia/malaysia-data-centre-unused-power-charge-october-2026/)), then the water check ([24 halls on hold](https://www.sotkn.com/markets/malaysia/malaysia-data-centre-water-check-approvals-october-2026/)), then TNB’s 9,000 MW forecast and its search for plants ([where Malaysia looks for the plants](https://www.sotkn.com/markets/malaysia/malaysia-tnb-9000mw-power-plants-november-2026/)). This week adds the spare-power number and the build-time gap. For green power pricing, see [18 sen to use the wire](https://www.sotkn.com/markets/malaysia/malaysia-data-centre-green-power-grid-charge-october-2026/). For a neighbour that is also rationing power for halls, see [Singapore’s power plan for data centres](https://www.sotkn.com/markets/singapore/singapore-power-plan-data-centres-green-fuel-october-2026/). For how big electricity prepayment and delays move the stuck step, see [where the stuck step moves](https://www.sotkn.com/analysis/where-does-the-stuck-step-move/). For how much power an AI hall draws, see [how much power an AI data centre uses](https://www.sotkn.com/explained/how-much-power-does-an-ai-data-center-use/). All our notes are on [Malaysia Markets](https://www.sotkn.com/markets/malaysia/).

Second-order read. Malaysia says spare power will hold at 24–27% to 2035\. Builders of plants and grid lines, TNB and halls with signed supply get paid first. Halls without a date wait. The stuck step is the power plants that do not exist yet, with new ones due about 2029\. Watch the next planning update and any move to publish the report.

**Get the Wire.** Second Order’s free daily brief on what moved in the AI chip map. [Read the Wire →](https://www.sotkn.com/the-wire/) · [Subscribe free →](https://www.sotkn.com/#/portal/signup)

**How we check this.** The reserve margin, water and demand-control remarks come from the Bernama report of the Dewan Rakyat debate on 18 November 2026 and the Parliament’s own record of that day. The 2026 and 2035 demand and capacity projections are the Energy Transition and Water Transformation Ministry’s, as reported by Bernama and published by Tenaga Nasional. Yeo Bee Yin’s numbers are her own, as spoken in the debate and reported by Free Malaysia Today; we do not vouch for them and say so where it matters. The planning committee report itself is not public, so we have not seen it. Every sum we worked out is labelled “our arithmetic”. Projections are plans, not facts yet. The references we used are listed at the end. [Our editorial standards →](https://www.sotkn.com/editorial-standards/)

## FAQ

**What did Malaysia say about spare electricity on 18 November?**  
In the Dewan Rakyat, Deputy Minister Abdul Rahman Mohamad said the electricity reserve margin for Peninsular Malaysia is projected at 24 to 27 per cent for 2027 to 2035\. He said this comes from the planning committee that met on 11 November. A reserve margin is the spare generating capacity above the highest demand.

**Why are people worried?**  
Because data halls are built faster than power plants. Yeo Bee Yin, an MP and former energy minister, said a data centre can be built in 12 to 24 months while a gas plant takes four to seven years. She said she fears a crunch until new plants arrive around 2029, and she put the margin on one day in June, 8 June, at about 13% once a plant in maintenance is counted.

**What do the official projections say about 2035?**  
The ministry, quoting the planning committee, says data centres in Peninsular Malaysia will use 73,274 GWh in 2035, 31% of electricity, up from 10,544 GWh, 7%, in 2026\. Peak demand is projected to rise from 21.3 GW to 33.5 GW.

**What is the stuck step?**  
The power plants that do not exist yet. Halls and grid connections can move in one to two years. New generation takes much longer. TNB’s chief executive said the only problem right now is where to find the power.

**Who gets paid while the plants are built?**  
Equipment makers and builders of power plants and grid lines, TNB through its regulated network spending, companies that win new generation tenders, battery storage firms, and data centre owners that already hold a supply agreement. Developers without one wait. The government says other customers will not be asked to pay for data centre costs.

**Is this investment advice?**  
No. Education only. It maps who gets paid and which step is stuck. It is not a recommendation to buy or sell any security, and we leave out price targets and ratings on purpose.

---

### References

Outbound links below are nofollow. We list only the sources actually used. Internal sotkn.com links in the body are separate.

1. Bernama (BernamaBiz), 2027-2035 Electricity Reserve Margin Projected At 24-27 Pct - PETRA, 18 Nov 2026\. [bernamabiz.com](https://www.bernamabiz.com/news.php?id=2636321&ref=sotkn.com) — the 24–27% reserve margin, the 11 November planning committee meeting, demand-side measures, the connected load charge, the ultra-high voltage tariff, the call to publish the report, and the water figures.
2. Parliament of Malaysia, Dewan Rakyat Hansard, committee stage debate on the Energy Transition and Water Transformation Ministry, 18 Nov 2026\. [hansard.parlimen.gov.my](https://hansard.parlimen.gov.my/hansard/dewan-rakyat/2026-11-18?ref=sotkn.com) — Yeo Bee Yin’s remarks on 8 June, build times, the separate wholesale market, the New Gen tenders and battery storage.
3. Free Malaysia Today, Yeo bimbang bekalan elektrik tak mampu tampung pertumbuhan pusat data, 18 Nov 2026\. [freemalaysiatoday.com](https://www.freemalaysiatoday.com/category/bahasa/tempatan/2026/11/18/yeo-bimbang-bekalan-elektrik-tak-mampu-tampung-pertumbuhan-pusat-data?ref=sotkn.com) — the 21 GW peak, the 25 GW available, the 13% effective margin and the 117 approved projects.
4. Bernama via Tenaga Nasional, Grid readiness critical to meeting rising AI data centre demand: TNB, 18 Nov 2026\. [tnb.com.my](https://www.tnb.com.my/assets/newsclip/18112026f.pdf?ref=sotkn.com) — the ministry’s 2026 and 2035 projections for data centre electricity use and peak demand, the 45 operating data centres and TNB’s Green Lane pathway.
5. New Straits Times, Johari: Data centre boom won’t squeeze power supply for industries, 21 Nov 2026\. [nst.com.my](https://www.nst.com.my/news/nation/2026/11/1582517/johari-data-centre-boom-wont-squeeze-power-supply-industries?ref=sotkn.com) — the investment minister’s remarks on supply and on keeping data centres apart from existing industry.
6. New Straits Times, Data centres must store two days’ water supply, use alternative sources, 18 Nov 2026\. [nst.com.my](https://www.nst.com.my/news/nation/2026/11/1580649/data-centres-must-store-two-days-water-supply-use-alternative-sources?ref=sotkn.com) — the same-day water answer and the demand-control remarks.
7. The Edge Malaysia, Malaysia seeks greater transparency on power capacity planning, 8 Sep 2026\. [theedgemalaysia.com](https://theedgemalaysia.com/node/817199?ref=sotkn.com) — why the planning reports stopped being public and that the last public one was published in March 2021.
8. The Malaysian Reserve, TNB sees additional 9,000MW electricity demand over next five years, 4 Nov 2026\. [themalaysianreserve.com](https://themalaysianreserve.com/2026/11/04/tnb-sees-additional-9000mw-electricity-demand-over-next-five-years/?ref=sotkn.com) — TNB’s August peak, the Green Lane timeline and the chief executive’s comment on finding power.
9. Princeton Digital Group, A new milestone in PDG and TNB’s partnership in Malaysia (LinkedIn post), 12 Nov 2026\. [linkedin.com](https://www.linkedin.com/posts/princetondg%5Fprincetondg-digitalinfrastructure-malaysia-activity-7526479357507403776-3Rgo?ref=sotkn.com) — the signed electricity supply agreement for the JH2 campus.

Not investment advice. Do your own research. Education only. Map of who gets paid and which step is stuck — not a buy list.

More on this desk: [Malaysia Markets](https://www.sotkn.com/markets/malaysia/) · [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/) · [contracted power, explained](https://www.sotkn.com/explained/contracted-power-explained/) · [all Markets](https://www.sotkn.com/markets/).