# Bring Your Own Capacity: Who Gets Paid While New England’s Data Centers Wait for Firm Power
- URL: https://www.sotkn.com/markets/us/us-iso-ne-large-loads-own-capacity-november-2026/
- Published: 2026-11-16T08:57:44.000Z
- Updated: 2026-11-16T08:57:44.000Z
- Description: ISO New England asked FERC on 13 November to accept rules for data centers of 50 MW or more. Firm power needs new capacity and built upgrades; until then a site runs non-firm and gives way above $250/MWh. Service starts June 2028.
- Author: Sean
- Tags: #market-us, Markets, #layer-power-energy, #layer-ai-data-centers

*New England has written the rules for data centers before the data centers have arrived. On 13 November its grid operator asked the federal regulator to accept a new deal for any site that can draw 50 megawatts or more. Firm power, the kind that stays on, comes only after the grid upgrades are built and the site brings new generating capacity of its own. Until then a site can run, but it gives way whenever local power costs more than $250 a megawatt-hour. The stuck step is firm service.*

**US PULSE** · POWER · GRID · AI DATA CENTERS · Data as at 16 Nov 2026 (ISO New England filing 13 Nov; Oregon order 13 Nov) · Next update: FERC comment date, 4 December 2026  
**Affects:** [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/) · [Hyperscalers](https://www.sotkn.com/stack/hyperscalers/) — Markets: [US](https://www.sotkn.com/markets/us/) · [Australia](https://www.sotkn.com/markets/australia/) · [Malaysia](https://www.sotkn.com/markets/malaysia/) · [Korea](https://www.sotkn.com/markets/korea/)

**In short:** ISO New England filed large-load rules at FERC on 13 November, docket ER27-484\. A large load is one site of 50 MW or more connected above 60 kV. Firm service needs every grid upgrade built and new capacity to match the load. Until then a site can take interim or non-firm service and must give way when its local price passes $250/MWh, which happened in about 1% of hours from 2021 to 2025\. Applications open 1 June 2027; service starts 1 June 2028\. The same day Oregon approved Pacific Power’s 20 MW data center contracts, from 1 January 2027\. Who gets paid first: the wire owners and new power builders. Stuck step: firm service. Map of who gets paid — not a buy list.

Education only, not advice to buy or sell any security. All figures are US dollars. A megawatt (MW) is a measure of how much power a site can draw at once; a megawatt-hour (MWh) is that much power for one hour. The Federal Energy Regulatory Commission, or FERC, oversees the big wires and wholesale power markets. A grid operator such as ISO New England runs the wholesale market and decides who can plug in. For how much power an AI site actually needs, see [how much power an AI data center uses](https://www.sotkn.com/explained/how-much-power-does-an-ai-data-center-use/).

### The numbers that matter this week

Large-load line

50 MW

One site · connected above 60 kV · same line as PJM

New

Give-way price

$250/MWh

Interim and non-firm sites are re-dispatched above it

Rule

Hours above it

About 1%

Load zone prices, 2021–2025 · about 88 hours a year (our arithmetic)

History

To apply

$200,000

$50,000 fee, not refunded, plus a $150,000 study deposit

Paid

Service starts

1 June 2028

Applications open 1 June 2027 · 566 days from filing (our arithmetic)

Clock

Firm service

Bring your own capacity

All upgrades built and new capacity designated first

Stuck step

ISO New England filing announcement, 13 Nov 2026, and Large Loads summary, 9 Nov 2026\. Status chips are Second Order’s read.

**On this page:** [Why it matters](#why-it-matters) · [What was filed](#what-changed) · [The three services](#three-doors) · [The $250 line](#the-250-line) · [Who pays for the wires](#who-pays) · [Oregon, same day](#oregon) · [Our math](#our-math) · [Who gets paid](#money-goes) · [What is stuck?](#still-stuck) · [Dates next](#dates) · [FAQ](#faq)

## Why do rules for a region with no big data centers matter?

Picture a town water company with a full reservoir. A bottling plant asks for a pipe as big as a neighbourhood’s. The company says yes, with conditions. Water every hour means paying for a bigger main and bringing a new well. Shutting the taps on the few dry days a year means connecting sooner and cheaper. Either way, the town’s families do not pay for the plant’s pipe.

That is almost exactly what ISO New England has proposed for data centers. The region’s electricity use has been flat or falling for a decade, and the grid operator told FERC that the region is generally long on supply. In February its chief executive told six New England senators that no new large data centers had committed to construction. On 13 November it filed the rules for them anyway. That is the point. New England has watched other regions scramble after the requests arrived. It is writing the price of the pipe first.

For AI builders the question is simple: where in America can you plug in a large site, how fast, and on what terms? Our earlier US Pulses have followed the same question from other angles: PJM, the biggest grid in the country, ran short of capacity ([PJM’s capacity shortfall](https://www.sotkn.com/markets/us/us-pjm-capacity-shortfall-october-2026/)), Virginia’s 3 GW of requests waited for first power ([Virginia’s first power](https://www.sotkn.com/markets/us/us-virginia-3gw-data-center-first-power-october-2026/)), and Anthropic took over a generator order rather than wait ([Anthropic’s 1.7 GW of generators](https://www.sotkn.com/markets/us/us-anthropic-1-7gw-generators-site-november-2026/)). New England’s filing turns the waiting into a written rule with a price on it.

## What did ISO New England file on 13 November?

ISO New England filed jointly with the New England Power Pool, the body of market participants, and the committee of transmission owners. Thirteen wire owners are named, including Eversource, National Grid, Central Maine Power and Versant Power. The filing sits in FERC docket ER27-484\. It answers an order FERC sent on 18 June 2026 to every regional grid operator, asking how each would connect large loads. FERC paused New England’s case on 14 August so the region could write its own rules.

- Who counts: a commercial or industrial customer at one site with a gross peak demand of 50 MW or more, connected to the grid above 60 kilovolts. The grid operator says loads of 20 to 50 MW do not raise the same reliability worries.
- Who is left out: storage, hospitals, water treatment, railroads and airports, and campuses without 50 MW of dedicated computing or process load, such as a university without a major data center.
- Who is already in: a site that was running, or “sufficiently under construction”, on 18 June 2026 keeps its existing demand outside the rules. It becomes a large load only if it grows 50 MW beyond that.
- What it costs to ask: a $50,000 application fee that is not refunded, a $150,000 study deposit, and a sworn statement that no duplicate application exists.
- How the line works: applications are studied one at a time in queue order, with a 90-day target for the main study. The queue is public, showing each site’s peak demand, location, status, the service it wants and the date it applied.
- No netting: a data center with its own power plant on site cannot subtract that plant’s output from its demand when it is measured. The netting threshold is zero MW.
- A public price list: the grid operator will post every network upgrade found for each large load, with cost estimates.
- When it starts: applications and studies on 1 June 2027; service on 1 June 2028, the date the grid operator says its software will be built and tested.

The region’s market participants backed the package. Three committees of the power pool recommended support on 3 November and its Participants Committee supported it on 12 November. The filing asks FERC to make the rules effective on 14 November. FERC’s notice set comments for 4 December; the grid operator and the Electric Power Supply Association, which speaks for competitive generators, asked for 7 December, citing the breadth of the filing, the holiday, and other large-load filings due on 16 November. FERC has not ruled on any of it.

![Chart: ISO New England large-load timeline in days after the 13 November 2026 filing: FERC comments day 21, applications open 1 June 2027 day 200, service begins 1 June 2028 day 566](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/us-iso-ne-large-loads-own-capacity-november-2026-print.png)

566 days from filing to first service. Day counts are our arithmetic. · Education only.

## What are the three ways to plug in?

The heart of the filing is a choice of three services. A site can mix them, but together they must cover its whole load; it cannot take the ordinary network service other customers use.

Firm Contract Demand Service

PrioritySame as every other firm customer

Before it startsAll network upgrades in service

CapacityNew capacity designated to match the firm amount

How longPermanent, for a fixed contract MW

Interim Contract Demand Service

PriorityNon-firm; gives way above $250/MWh

Before it startsAvailable while upgrades are still being built

CapacityNot yet designated

How longUp to 7 years, or as long as upgrades take, if longer

Non-Firm Contract Demand Service

PriorityNon-firm; gives way above $250/MWh

Before it startsMay need fewer upgrades

CapacityNo new capacity needed

How longPermanent

ISO New England filing announcement, 13 Nov 2026, and Large Loads summary, 9 Nov 2026.

Firm service is the full deal: the same claim on power as any home. But it starts only when every upgrade the study found is built and the customer has designated new capacity to match the firm amount. The grid operator calls this “bring your own new capacity”.

Interim service is the waiting room for a site working towards firm service. It lasts up to seven years or as long as the upgrades take, whichever is longer. Non-firm service is the permanent version for a flexible site that never wants to bring capacity, and it may need fewer upgrades.

One detail matters for power plants built next to data centers. A generator close enough to count enters with zero megawatts of normal grid service. It can shorten the time a site spends giving way, but it does not count towards the capacity a firm customer must bring unless it passes the regular study for new plants. A turbine on the lot helps a site ride through price spikes. It does not, by itself, buy firm service.

The capacity rule itself is still a notice. Interim and non-firm sites will be left out of the Installed Capacity Requirement, the amount of power the region’s capacity market must buy. What counts as “new” capacity, and where it must sit, is left for talks and a filing in 2027\. A developer learns today that it must bring capacity, but not yet what qualifies.

## What does giving way above $250 mean?

Every point on the grid has a price for power that changes through the day, the locational marginal price. When the price at an interim or non-firm site passes $250 per megawatt-hour, the grid operator re-dispatches it, in whole or in part: the site must cut what it draws or raise output from its own eligible generation.

Why $250? Load zone prices crossed it in about 1% of hours from 2021 through 2025, the grid operator says, and it matches the penalty price the region already uses for replacement reserves. In plain terms, $250 is where the grid is already under strain, so a site with fewer upgrades and no capacity of its own steps back first.

One per cent of hours is about 88 hours a year, by our arithmetic. For a site that can shift work or run back-up power, that may be a small price for connecting years earlier. For a site selling guaranteed computing time, even 88 hours is a problem. And that history comes from a grid with no big data centers; add many and the hours above $250 could rise. That risk sits with the site, not the town.

The rules also ask more of a data center than of an ordinary customer. A large load must send an hourly forecast of its use for the next seven days, every day. Changes from that forecast need the grid operator’s approval. It must install fast phasor meters, because big computing sites can swing their demand quickly. Australia now makes every data center of 30 MW or more meet a fixed set of grid standards before it connects ([Australia’s 30 MW rule](https://www.sotkn.com/catalyst/australia-30-mw-data-center-grid-rule-ride-through/)). The pattern across grids is the same: a data center is being treated less like a customer and more like a power plant in reverse.

## Who pays for the wires if the data center never comes?

This is where the transmission owners come in, and it is the part of the filing that moves money most directly. Their worry is about utilities, not data centers. In New England states without retail choice, the local utility must take grid service on behalf of the data center. If the data center then failed to show up, that utility would be left holding network upgrades that, in the filing’s words, could easily run to the hundreds of millions of dollars. A side promise from the data center might not hold up, given the utility’s state duty to serve.

So the owners propose a Large Load Cost Recovery Agreement that binds the data center directly. It is a three-way contract among the transmission owner, the customer that takes grid service, and the company that owns the load. The money runs four ways:

- Wires used only by the site are paid for by the site directly, including their upkeep.
- A monthly Cost Recovery Charge equal to the yearly cost of the upgrades minus the grid charges the customer already pays, credited back to other customers.
- An exit fee equal to what is left of the upgrades’ book value plus the cost of taking them down.
- Credit support, in a form each transmission owner sets for itself.

Every upgrade a study finds, beyond the connection itself, is the customer’s alone to pay for. This is the one part the region did not fully sign: the power pool did not join the filing on the cost agreement. The owners admit a contract with a retail customer raises a legal question, and say in advance that FERC may change or cut those terms.

The politics pointed this way first. In January six senators, including Peter Welch and Edward Markey, wrote that tech companies, not American families, should foot the bill. The grid operator’s chief executive, Vamsi Chadalavada, replied that data centers had not driven wholesale costs in New England. By the close of 13 November no data center developer had filed in the docket; the Massachusetts Attorney General had moved to intervene.

## What did Oregon decide on the same day?

On the other side of the country, the Public Utility Commission of Oregon approved Pacific Power’s data center deal on 13 November. Order No. 26-443 adopts a settlement signed on 16 September by Pacific Power, the commission’s staff, the Oregon Citizens’ Utility Board and community and environmental groups. The only opposition came from the Data Center Coalition. The new Schedule 401 starts on 1 January 2027, and Pacific Power must file the final tariff pages by 24 November.

The line is lower: a site that uses or can use 20 MW or more, whose business is computing, data processing or web hosting. And there is no posted price. Each site signs its own agreement, for 10 to 30 years, which the commission approves within 90 days for a standard contract or 180 days for an unusual one. Pacific Power’s senior vice president for planning and regulation, Rick Link, said the aim is that new large users pay their own way while growth continues.

- Grid upgrades are paid up front, except for some large shared lines, where the site pays a monthly share instead.
- Energy is priced at the day-ahead market price at an agreed point, plus a peak demand charge on the site’s own highest monthly draw.
- New generation and storage built to serve the site are paid in full, through a monthly reservation charge or by repaying the utility directly.
- A community energy benefits charge of 1 cent per kilowatt-hour applies to sites with 100 MW or more of allocated capacity, matching the rate already set for Portland General Electric. The money funds efficiency, home repairs and local power for households that struggle with bills.
- A site with a contract signed before 16 June 2025 is treated as new if serving it needs $10 million or more of new investment after that date.
- A site must have senior debt rated A- or better, or post collateral to cover its exit fee. Exit fees are limited to the costs the utility would really be stuck with.

Like New England, Oregon gave no count of the data centers or megawatts that will come in under the rule. The first report with counts, published only in ranges until at least four separately owned sites take service, is due by 31 March 2027\. Parties have 60 days from service of the order to ask for rehearing.

![Chart: three large-load grid lines compared: Pacific Power Oregon 20 MW, ISO New England and PJM 50 MW, ERCOT 75 MW](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/us-iso-ne-large-loads-own-capacity-november-2026-shift.png)

Where each grid draws the large-load line. · Education only.

Side by side, the tools differ but the shape is the same. New England works at the wholesale level, with a give-way price and a cost agreement with the wire owners. Oregon works at the retail level, with a contract for each site. Both make the newcomer pay, both protect existing customers with exit fees and collateral, and both leave the real price for any one site to be found later.

## What does the arithmetic say?

Everything below is our arithmetic from the published figures, not a forecast by ISO New England, Pacific Power or the regulators. Where we use a round example site, we say so.

- The clock: from the filing on 13 November 2026 to the first day of service on 1 June 2028 is 566 days, a little over 18 months. Applications open after 200 days. Comments are due after 21 days.
- The waiting room: a site that starts interim service on 1 June 2028 could stay there until June 2035 under the seven-year limit, or longer if its upgrades take longer.
- The give-way hours: about 1% of 8,760 hours in a year is about 88 hours. A 100 MW site that stepped back fully in all of them would give up about 8,800 MWh out of a possible 876,000 MWh, about 1% of its year. That is on past prices, before any big data centers joined the grid.
- The ticket to ask: $50,000 plus $150,000 is $200,000 for each application in New England. For a 50 MW site that is $4,000 per megawatt asked for. Oregon’s fee is $25,000, before study costs.
- The community charge: a 100 MW Oregon site drawing its full load every hour would use about 876 million kWh a year, so 1 cent per kWh would come to about $8.8 million a year. A site running at 80% would pay about $7.0 million.
- The lines: Oregon at 20 MW, New England and PJM at 50 MW, ERCOT in Texas at 75 MW. ERCOT is checking whether developers shrank projects to stay under its line; nearly 10 GW of requests sit between 60 MW and 74.9 MW. Watch whether New England requests bunch just under 50 MW.

The arithmetic says the ticket is cheap; the time and the risk are not. A New England site could run from mid-2028, but as a guest that steps aside when the grid is tight, until it has paid for the wires and found capacity of its own.

New England large loads, the proposal at a glance

DocketFERC ER27-484, filed 13 Nov 2026

Who countsOne site, 50 MW or more, above 60 kV

Firm serviceAll upgrades built + new capacity designated

Interim serviceNon-firm, up to 7 years or until upgrades finish

Give-way price$250/MWh · about 1% of hours in 2021–2025

To apply$50,000 fee + $150,000 deposit

Applications / service1 June 2027 / 1 June 2028

FERC comments4 Dec 2026 (7 Dec requested)

ISO New England filing announcement and Large Loads summary; Load Factor News reading of the transmittal letter, 15 Nov 2026\. Sums marked as ours are Second Order arithmetic.

## Who gets paid, and who waits?

![Infographic: who gets paid while New England data centers wait for firm power, from transmission owners and new capacity builders to the grid operator, with firm service as the stuck step](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/us-iso-ne-large-loads-own-capacity-november-2026-infographic.png)

Who gets paid / stuck step while data centers wait for firm power. · Education only.

1 · Wire owners

**Who:** Eversource, National Grid, Central Maine Power, Versant Power and the other owners  
**Paid:** Upgrades paid by the site, with a monthly charge, an exit fee and credit support

Paid first

2 · New capacity builders

**Who:** Developers of new generation and storage in New England  
**Paid:** A new buyer: firm service needs new capacity to match the load

Paid

3 · The grid operator

**Who:** ISO New England, which studies and queues each site  
**Paid:** $50,000 fee and $150,000 deposit per application

Paid

4 · Equipment and on-site power

**Who:** Makers of transformers, switchgear, meters and on-site generators  
**Paid:** As upgrades and back-up plants are ordered and built

Paid while building

5 · Existing customers

**Who:** New England and Oregon households and businesses  
**Paid:** Protected by exit fees and credits; Oregon’s 1 cent charge funds local programs

Protected

6 · Firm service

**Who:** All upgrades built and new capacity designated  
**Paid:** Until then a site runs non-firm and gives way above $250/MWh

Stuck step

First in line are the owners of the wires. Under the proposed agreement, the data center pays for the lines only it uses, pays a monthly charge that covers the yearly cost of the shared upgrades it caused, and owes an exit fee if it leaves early. The owners also set the credit support. That turns a risky upgrade, built for a customer who might not come, into one backed by a contract. The filing does not say how much any owner expects to build.

Second, whoever builds new power in New England. The firm-service rule makes a data center a buyer of new capacity: it must designate enough new generation or other capacity to match the firm amount it wants. Until the 2027 rules say what counts as new, no one can say which kinds of plant will qualify. Our explainers on how big buyers contract for power cover the tools they are likely to use ([power purchase agreements explained](https://www.sotkn.com/explained/power-purchase-agreement-explained/), [how hyperscalers buy power](https://www.sotkn.com/stack/hyperscalers/how-do-hyperscalers-buy-power/)).

Third, the grid operator collects $200,000 per application before any study begins. Fourth, the makers of grid equipment and on-site plants are paid as upgrades and back-up power are ordered. Oregon’s commission said very large loads raise prices for scarce things, from transformers to specialised labour. Our Analysis desk has already asked what happens if big transformers and gas turbines stay sold out ([if big transformers stay sold out to 2029](https://www.sotkn.com/analysis/if-big-transformers-stay-sold-out-2029-where-cash-sticks/), [if gas turbines stay booked into 2030](https://www.sotkn.com/analysis/if-gas-turbines-stay-booked-into-2030-where-cash-sticks/)), and who supplies the kit ([who makes data center power equipment](https://www.sotkn.com/explained/who-makes-data-center-power-equipment/)).

Last come the data center developers and their tenants. They pay first, in fees, deposits, upgrades and collateral, and they wait longest for the firm service that a guaranteed computing contract usually needs. For how those costs are usually financed, see [data center financing explained](https://www.sotkn.com/explained/data-center-financing-explained/). Existing customers are the group both rules are written to protect.

## What is stuck, exactly?

The stuck step is firm service. It is not the right to connect: a New England site could, if the rules pass, apply in June 2027 and run from June 2028\. It is not the money to apply: $200,000 is small for a site of this size. It is the two conditions for firm power: every upgrade built, and new capacity of its own designated. Until both are met, the site is a guest that steps aside above $250.

The clock has three parts. First the rules: FERC must accept them, and the capacity details are not due until 2027\. Second the study: one at a time, in queue order, with a 90-day target. Third the build: the upgrades and the new capacity. The filing gives no time for that third part, which is why interim service may last seven years or more.

There are honest reasons for caution. First, this is a filing. FERC accepted PJM’s 50 MW definition and registry on 9 October but, according to a summary by the power pool’s counsel, rejected PJM’s package of new-capacity and capacity-market rules, so New England’s own capacity rules could change. Second, the $250 price rests on the grid operator’s own testimony, and the 1% history comes from a grid without big data centers. Third, the cost agreement with retail customers raises a legal question the owners admit. Fourth, neither New England nor Oregon has said how many sites or megawatts are waiting. Rules for a market that has not arrived may simply sit unused. The one-line rule our Analysis desk keeps coming back to still applies: the slow step sets the timing for everyone else, and the money gathers at the scarce step ([where the stuck step moves](https://www.sotkn.com/analysis/where-does-the-stuck-step-move/)).

It also fits a pattern across our grid coverage this autumn. Our Analysis desk asked what happens when a campus is named before the plug is approved ([if the campus is named before the plug](https://www.sotkn.com/analysis/if-the-campus-is-named-before-the-plug-is-approved-where-cash-sticks/)). PJM’s capacity backstop showed the cost of finding power after the requests arrive ([PJM’s 6,831 MW backstop](https://www.sotkn.com/catalyst/pjm-6831-mw-power-backstop-data-center-growth/)). New England is trying the other order: price the plug first.

## Which dates test the read?

![Calendar of dates that test the read: 24 November Oregon tariffs, 4 or 7 December FERC comments, 1 January 2027 Oregon start, 31 March 2027 Oregon report, 1 June 2027 New England applications, 1 June 2028 service](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/us-iso-ne-large-loads-own-capacity-november-2026-calendar.png)

Dates that test the read. · Education only.

- 13 November 2026 — ISO New England files ER27-484; Oregon approves Schedule 401.
- 24 November 2026 — Pacific Power files the final Schedule 401 tariff pages; the first site agreement filed after that will be the first Oregon price anyone can read.
- 4 December 2026 — FERC comment date on ER27-484 (7 December requested). Watch for the first data center developers to say whether $250 and seven years of interim service are workable.
- 1 January 2027 — Oregon’s Schedule 401 takes effect.
- 31 March 2027 — Oregon’s first report on large energy-use sites, covering 2025 and 2026.
- 2027 — New England’s talks and filing on what counts as new capacity.
- 1 June 2027 — New England applications and studies open.
- 1 June 2028 — New England large-load service begins, if FERC accepts.

Dates from ISO New England (13 Nov 2026), Load Factor News (14 and 15 Nov 2026) and Pacific Power (13 Nov 2026). FERC has not ruled on the requested 7 December date.

## How does this look from Australia, Malaysia and Korea?

Grids across our markets are writing the same kind of rule. Australia’s new rule makes sites of 30 MW or more prove they can ride through grid faults ([Australia’s 30 MW rule](https://www.sotkn.com/catalyst/australia-30-mw-data-center-grid-rule-ride-through/)). Malaysia’s Johor has made grid connection the gate for its data center boom ([Johor’s grid connection](https://www.sotkn.com/markets/malaysia/malaysia-johor-data-centre-grid-connection-october-2026/)), and Korea’s AI data centers wait in a grid queue of their own ([Korea’s grid queue](https://www.sotkn.com/markets/korea/korea-ai-data-centre-grid-queue-october-2026/)). New England’s version is the clearest yet on one point: firm power is something a data center earns by building, not something it is given by asking.

For where AI sites cluster and why, see [where AI data centers are located](https://www.sotkn.com/explained/where-are-ai-data-centers-located/). For what contracted power means on a data center operator’s report, see [contracted power explained](https://www.sotkn.com/explained/contracted-power-explained/). For the full set of US notes, see [US Markets](https://www.sotkn.com/markets/us/).

Second-order read. New England asked FERC on 13 November to accept rules for 50 MW data centers before any have committed to build. Firm power needs built upgrades and new capacity; until then a site gives way above $250/MWh. Wire owners and new power builders are paid first. Watch the 4 December comments.

**Get the Wire.** Second Order’s free daily brief on what moved in the AI chip map. [Read the Wire →](https://www.sotkn.com/the-wire/) · [Subscribe free →](https://www.sotkn.com/#/portal/signup)

**How we check this.** The New England rules come from ISO New England’s own announcement of the 13 November filing and its Large Loads Integration summary, updated 9 November. Details of the transmittal letter, the docket number, the cost recovery agreement, the votes and the comment dates come from Load Factor News, which read the letter and FERC’s notice. The comparison with PJM and ERCOT comes from Voltgrid News. The Oregon rules come from Pacific Power’s release and Load Factor News’ reading of Order No. 26-443\. A filing is not a ruling: FERC can accept, reject or change any part of it, and we say so where it matters. Every sum we worked out is labelled “our arithmetic”. Neither filing counts the data centers or megawatts waiting to use the rules, so we do not guess. Price targets and ratings are left out on purpose. The references we used are listed at the end. [Our editorial standards →](https://www.sotkn.com/editorial-standards/)

## FAQ

**What did ISO New England file on 13 November?**  
ISO New England, the region’s grid operator, filed rules with the Federal Energy Regulatory Commission (FERC) for “large loads”: one site that can draw 50 megawatts or more and connects above 60 kilovolts. Data centers are the obvious case. The rules create three ways to get grid service: firm, interim and non-firm. The filing sits in FERC docket ER27-484\. FERC has not ruled on it.

**What is the stuck step?**  
Firm power. To get the same priority as every other customer, a data center must wait until every grid upgrade it needs is built and must bring new generating capacity to match what it asks for. Until then it can run on interim or non-firm service, which means it gives way whenever local power prices pass $250 per megawatt-hour.

**How often would a non-firm data center have to give way?**  
ISO New England says local prices passed $250 per megawatt-hour in about 1% of hours from 2021 to 2025\. That is roughly 88 hours a year (our arithmetic). The ISO also says large data centers have not yet arrived in New England, so that history is a starting point, not a forecast.

**Who gets paid first?**  
The transmission owners, such as Eversource, National Grid, Central Maine Power and Versant Power, get a contract that binds the data center to pay for its upgrades, with an exit fee if it leaves. Builders of new generation and storage gain a new buyer, because firm service needs new capacity. The grid operator collects application fees and deposits. Data center developers pay first and wait.

**Is this investment advice?**  
No. Education only. It maps who gets paid and which step is stuck. It is not a recommendation to buy or sell any security, and we leave out price targets and ratings on purpose.

---

### References

Outbound links below are nofollow. We list only the sources actually used. Internal sotkn.com links in the body are separate.

1. ISO Newswire (ISO New England), ISO-NE files proposal with FERC to address ‘large loads’, 13 Nov 2026\. [isonewswire.com](https://isonewswire.com/2026/11/13/iso-ne-files-proposal-with-ferc-to-address-large-loads/?ref=sotkn.com) — the three services, the bring-your-own-new-capacity rule, the $250/MWh re-dispatch price, the about 1% of hours, the June 2027 start of applications and the capacity-requirement exclusion.
2. ISO New England, Large Loads Integration Proposal Information summary (last updated 9 Nov 2026), Nov 2026\. [iso-ne.com](https://www.iso-ne.com/static-assets/documents/100040/large%5Floads%5Fintegration%5Fproposal%5Finformation%5Fsummary%5F10.09.26.pdf?ref=sotkn.com) — the 50 MW and 60 kV definition, the seven-year interim service, fees and deposits, the 90-day study, the public queue, forecasting and metering rules.
3. Load Factor News, ISO New England files large-load rules before the large loads arrive (Docket ER27-484-000), 15 Nov 2026\. [loadfactornews.com](https://loadfactornews.com/readings/2026/11/15/iso-new-england-er27-484-large-load-tariff-bring-your-own-capacity/?ref=sotkn.com) — the docket number, the transmission owners named, the cost recovery agreement and exit fee, the zero netting threshold, the comment dates, the NEPOOL votes and the senators’ letters.
4. Voltgrid News, ISO-NE files 50 MW large-load tariff at FERC, $250/MWh re-dispatch, 13 Nov 2026\. [voltgridnews.com](https://voltgridnews.com/story/iso-ne-files-50-mw-large-load-tariff-at-ferc-250-mwh-re-dispatch?ref=sotkn.com) — the comparison with PJM’s 50 MW line and ERCOT’s 75 MW line, and the open points FERC has not ruled on.
5. Pacific Power, Pacific Power will require new large data centers to pay their way, 13 Nov 2026\. [pacificpower.net](https://www.pacificpower.net/about/newsroom/news-releases/large-load-filing.html?ref=sotkn.com) — the Oregon approval, the 20 MW customer class and the 1 January 2027 start.
6. Load Factor News, Oregon PUC adopts Pacific Power’s data center settlement (Order No. 26-443, Docket UE 463), 14 Nov 2026\. [loadfactornews.com](https://loadfactornews.com/readings/2026/11/14/oregon-puc-order-26-443-adopts-pacific-power-schedule-401-data-center-contracts/?ref=sotkn.com) — the Schedule 401 charges, the community charge, the credit and exit-fee rules, the 24 November and 31 March dates.

Not investment advice. Do your own research. Education only. Map of who gets paid and which step is stuck — not a buy list.

More on this desk: [US Markets](https://www.sotkn.com/markets/us/) · [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/) · [how much power an AI data center uses](https://www.sotkn.com/explained/how-much-power-does-an-ai-data-center-use/) · [PJM capacity](https://www.sotkn.com/markets/us/us-pjm-capacity-shortfall-october-2026/) · [all Markets](https://www.sotkn.com/markets/).