# Firm Power From 2029: Who Gets Paid While PJM Builds a Faster Lane for Data Centers
- URL: https://www.sotkn.com/markets/us/us-pjm-fast-energization-data-center-firm-power-november-2026/
- Published: 2026-11-22T13:30:03.000Z
- Updated: 2026-11-22T13:30:03.000Z
- Description: PJM, the biggest US grid, filed new rules on 16 November: a one-year study lane for data centers and power plants, service that can be cut while upgrades are built, and ride-through rules for sites of 25 MW or more. The lane opens late 2027. Stuck step: firm power.
- Author: Sean
- Tags: #market-us, Markets

*PJM, which runs America's biggest power grid, has asked the federal regulator to approve a faster way to plug in data centers and new power plants, and new kinds of grid service for data centers that can accept being switched off. It filed on 16 November 2026\. The new study lane should take one year instead of two, but it does not open until late 2027 and its first answers come in 2029\. Until then a new data center can get power that can be cut, not power it can count on. The wire owners and the power plants already running are paid first. The stuck step is firm power.*

**US · AI DATA CENTERS · GRID** · PJM filings at FERC, 16 Nov 2026 (dockets ER27-531 and ER27-522) · Next update: comment deadline, about 15 Jan 2027 if FERC grants PJM's 60 days  
**Affects:** [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/) — Markets: [US](https://www.sotkn.com/markets/us/) · [Malaysia](https://www.sotkn.com/markets/malaysia/) · [Australia](https://www.sotkn.com/markets/australia/) · [Korea](https://www.sotkn.com/markets/korea/)

**In short:** PJM filed two proposals at FERC on 16 November 2026\. ER27-531: a Fast Energization Process that studies power plants and large users together and aims to finish in 12 months, with deposits paid earlier to weed out speculative projects; plus three new services for large users — interim network service (interruptible, energy only), and firm and non-firm contract demand. ER27-522: data centers with 25 MW or more behind power electronics must ride through grid faults from 16 January 2027\. The first fast-lane window opens in late November 2027 and finishes in 2029\. Paid first: wire owners and running plants. Stuck step: firm power. Map of who gets paid — not a buy list.

Education only, not advice to buy or sell any security. Figures are as published by PJM unless labelled as our arithmetic, and none of the proposals has been approved yet. A megawatt (MW) is how much power a site can draw at once; 1,000 MW is a gigawatt (GW). FERC, the Federal Energy Regulatory Commission, oversees the big wires and wholesale power markets. “Firm” power is power the grid plans for and keeps on in a shortage. For how much a modern AI site draws, see [how much power an AI data center uses](https://www.sotkn.com/explained/how-much-power-does-an-ai-data-center-use/).

### The numbers that matter this week

New study lane, target length

12 months

Down from about two years · power plants and large users studied together

Filed

First fast-lane window opens

Late Nov 2027

Applications due Aug 2028 · first cycle finishes 2029

Clock

Data center build time, per PJM

12–18 months

Faster than the plants and wires they need

Fast

Ride-through line

25 MW

Power-electronics load inside a site of 50 MW or more · from 16 Jan 2027

Rule

Biggest load drop so far

3.9 GW

22 Jul 2026 · PJM has about 10 GW of computational load

Risk

Firm power for new halls

From 2029

Until then, interim service is energy only and can be cut

Stuck step

Figures from PJM's FERC filings ER27-531 and ER27-522 (16 Nov 2026). Status chips are Second Order’s read.

**On this page:** [What PJM filed](#why-it-matters) · [The fast lane](#fast-lane) · [New services](#new-services) · [Ride-through](#ride-through) · [Who gets paid](#money-goes) · [Our math](#our-math) · [What is stuck?](#still-stuck) · [Landlords and tenants](#landlords) · [Dates next](#dates) · [Elsewhere](#elsewhere) · [What would change this](#change-view) · [FAQ](#faq)

## What did PJM file, and why does it matter for AI data centers?

PJM Interconnection runs the wholesale power market and the high-voltage grid across the mid-Atlantic and parts of the Midwest, including the data center corridor of northern Virginia. On Monday 16 November 2026 it sent two proposals to FERC. Both answer orders FERC issued in June, which said PJM's rules did not deal properly with very large users and with sites that sit next to power plants.

The first proposal, in docket ER27-531, changes how a new data center asks for power. It folds the request into one joint study with new power plants, called the Fast Energization Process, and adds three new kinds of transmission service for large users. The second, in docket ER27-522, sets out what a data center must do once it is connected: stay on through grid faults, and later follow rules on how fast it ramps up and down.

It matters because of size. PJM says in the filing that its peak load is forecast to grow by 32 GW from 2024 to 2030, and that 30 GW of that comes from data centers. Its 2026 forecast has summer peak rising 3.6% a year for ten years; in 2023 it expected 0.8% a year. PJM also writes that it is expected to host as much as 70% of future US data center development. A large load, in PJM's rules since 12 October 2026, is one site that can draw 50 MW or more.

And it matters because of speed. PJM's own filing says data centers can be built in 12 to 18 months, faster than the power plants and wires they need. For how long each part of a build takes, see [how long it takes to build an AI data center](https://www.sotkn.com/explained/how-long-does-it-take-to-build-an-ai-data-center/). This note is about the paperwork that decides when the power arrives, and who is paid while a finished hall waits.

## What is the Fast Energization Process, and when does it start?

![Timeline chart: a data center takes 12 to 18 months to build, while PJM's new fast lane opens in late November 2027, takes applications to August 2028 and finishes its first cycle in 2029](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/us-pjm-fast-energization-data-center-firm-power-november-2026-print.png)

Halls are quicker than the new lane. · Education only.

It is a single queue for two things that PJM used to study apart: new power plants asking to connect, and large users asking for transmission service. PJM says studying them together lets it pair a new data center with nearby new generation, cut duplicate upgrades and finish in 12 months. Its Inside Lines post puts it plainly: two years down to one.

The main pieces are:

- **A quick screen first.** About four months, with two rounds of grid analysis that each take less than 60 days and give rough cost and time estimates for the upgrades.
- **Money down early.** After each round there is a decision point. Projects that stay in must post readiness deposits, which are at risk. PJM says this is meant to screen out speculative plants and speculative data centers.
- **Help before the deadline.** A 14-week period before applications close, in which PJM tests applicants' models and tells them what is missing.
- **Contracts in parallel.** The final agreement talks run at the same time as the main study, not after it.
- **Software.** PJM says it has been testing an AI interconnection platform called Tapestry and is close to trusting its results without a parallel human check.

Now the timing, which is the part that matters for anyone with a hall half built. PJM proposes to open the first Fast Energization window the business day after the current cycle, Cycle 01, finishes its second decision point. PJM expects that in late November 2027\. Applications would then close in August 2028, and the first cycle would finish in 2029\. PJM says FERC would need to accept the whole filing within about ten months for that schedule to hold.

Until then, new requests to serve load go through the existing Necessary Studies process that FERC directed in the co-location case. In other words: the fast lane is a 2028 and 2029 story. A data center that breaks ground this winter is likely to be finished before the fast lane gives its first answer, on our arithmetic.

## What new kinds of grid service would data centers get?

Three, and the difference between them is the whole story. Today a large user mostly takes normal network service, which is firm: the grid plans for it and keeps it on in a shortage. The new services let a data center trade some of that firmness for getting connected sooner, or for avoiding some costs.

Interim network service

What it isA bridge while upgrades are built

PowerSpare room on the grid, as available

Firm?No — interruptible, energy only

EndsTurns into normal service once PJM checks the upgrades

Firm contract demand

What it isA firm cap set in MW

PowerEnergy and capacity up to that cap

Firm?Yes — treated like normal firm service

Exit42 months' notice before a delivery year

Non-firm contract demand

What it isA non-firm cap set in MW

PowerEnergy as available up to the cap

Firm?No — cut alongside interim service

LockNo switching from firm to non-firm for 5 years

In the filing, firm contract demand is treated the same as normal network service when the grid has to cut load. Interim service and non-firm contract demand are treated the same as non-firm service, so they go first. PJM's October workshop slides, which it calls a work in progress, go further: non-firm contract demand would be cut second and interim service third, before the grid's own emergency steps, and both would sit outside the capacity auction and its costs.

To use any of the flexible services a data center has to show it can actually hold its draw under the cap. That means control systems and protection that stop it taking more than allowed, a signed promise to cut when told, and, in the October slides, a control room staffed around the clock to answer PJM's calls. Sites that ignore cut orders more than once can lose the service.

One more change sits in the same filing. From 16 March 2027, a customer could only net up to 50 MW of its own on-site retail generation against its load for capacity and transmission charges, with exemptions for set-ups that were running or contracted by 18 December 2025\. That clause is narrow, but it closes a way of shrinking the bill.

For how a contracted megawatt differs from a delivered one, see [contracted power explained](https://www.sotkn.com/explained/contracted-power-explained/).

## What are the ride-through rules, and why now?

![Chart of three sudden large load drops on PJM's grid: about 1.5 GW in July 2024, 1.8 GW in February 2025 and 3.9 GW in July 2026](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/us-pjm-fast-energization-data-center-firm-power-november-2026-shift.png)

Why PJM wants sites to ride through. · Education only.

Because PJM has already watched data centers drop off its grid in large blocks. When a voltage dip hits, many sites switch themselves to backup power to protect their servers. One site doing that is a small event. Hundreds of megawatts doing it at once is not. PJM's filing lists three events: about 1.5 GW on 10 July 2024, about 1.8 GW on 17 February 2025, and about 3.9 GW on 22 July 2026, when frequency across the Eastern grid rose to 60.092 Hz and voltage peaked near 1.138 per unit. PJM says it already has about 10 GW of computational load.

So PJM wants a new class, the Large Computational Load: a large load, 50 MW or more, with 25 MW or more of its maximum draw running through power electronics, the equipment that turns grid power into what servers use. Such sites would have to stay connected through set voltage and frequency dips instead of jumping to backup. PJM's October draft says a site must ride through 0.90 to 1.10 per unit voltage without limit, stay on for two seconds down to 0.80, half a second down to 0.50, and a quarter of a second below that. On frequency, it must stay on between 58.8 and 61.2 Hz without limit, and for 299 seconds just outside that band.

- **New sites:** PJM asked for the rules to apply from 16 January 2027, 61 days after filing.
- **Existing sites:** anything already studied, signed, under construction or running gets until the later of 16 January 2028 or one year after it starts operating, in PJM's October draft.
- **Risky sites:** PJM may demand compliance within 90 days if a site is adding to instability.
- **No shortcut:** compliance is by the load itself riding through. Swapping in other resources does not count unless PJM and the wire owner approve it in writing.
- **Next:** ramp-rate and other operating rules, to be written with stakeholders in 2027, with a ramp-rate filing pencilled in for the second quarter of 2027.

This is the piece that turns into orders for equipment. Power conversion, protection and control gear inside the site has to be specified, tested and, for existing halls, refitted. For who makes that kit, see [who makes data center power equipment](https://www.sotkn.com/explained/who-makes-data-center-power-equipment/), and for how power moves from the grid to the rack, [data center power distribution explained](https://www.sotkn.com/explained/data-center-power-distribution-explained/).

## Who gets paid, and in what order?

![Infographic: who gets paid under PJM's proposal, from transmission owners and running power plants to power gear makers, with firm power as the stuck step for new data centers](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/us-pjm-fast-energization-data-center-firm-power-november-2026-infographic.png)

Who gets paid / stuck step on PJM. · Education only.

1\. Transmission owners

**Who:** The utilities that build and own the lines and substations  
**Paid:** Paid for the upgrades large users drive. Interim customers pay their rates and other grid charges; PJM says states will see the costs so they can bill large loads.

Paid first

2\. Power plants already running

**Who:** Generators that sell capacity in PJM  
**Paid:** Firm customers, on normal service or firm contract demand, are counted in the capacity auction and pay its costs.

Paid

3\. Power and control gear makers

**Who:** Conversion, protection, telemetry and control suppliers  
**Paid:** Ride-through, caps on draw and cut-on-command all need hardware and software, for new and existing halls.

Orders

4\. New power plant builders

**Who:** Projects that can clear the fast lane's deposits  
**Paid:** Studied alongside the load they could serve, from the first window in late 2027.

Later

5\. New data center owners and tenants

**Who:** Landlords, cloud firms and AI labs with halls to fill  
**Paid:** Can run sooner on interruptible power, but firm power waits for upgrades and, for new requests, for the 2029 answers.

Waits

First, the wire owners. Every route to power in this filing runs through upgrades to their lines and substations, and PJM's stated aim is to show states the cost of the upgrades that data centers drive so the states can bill those users. A data center on interim service also pays the wire owners' rates, PJM's administrative and grid-service charges, black start charges, any redispatch costs and transmission enhancement charges.

Second, the power plants already running. A data center that wants firm power, on normal service or the new firm contract demand, is counted in the capacity auction and pays capacity costs. One that takes the flexible services avoids those costs, in PJM's October slides, but accepts being cut first. Either way, existing generation gets paid: as capacity from firm users, or as the backstop that lets flexible users be cut.

Third, the makers of the gear that makes a site obey. Riding through faults, capping draw and answering a cut order in real time are not policies; they are equipment and staff. Existing halls have a year to catch up once the rules start.

Last, the data center owners and their tenants. They can get connected sooner on interim service, but they cannot promise a tenant firm power until the upgrades are built and PJM signs them off. One-line rule: on PJM, whoever owns the wire or the running plant is paid before whoever owns the hall.

## What does our arithmetic show?

Growth and risk

Data centers' share of 2024–2030 peak growthabout 94% (30 of 32 GW)

Data center growth vs computational load todayabout 3x (30 GW vs about 10 GW)

Largest drop vs first listed dropabout 2.6x (3.9 vs 1.5 GW)

The clocks

Comment deadline if FERC grants 60 daysabout 15 Jan 2027

Order date if FERC acts in 120 daysabout 16 Mar 2027 — the requested start

Ten months from filingabout mid-Sep 2027

Existing sites' ride-through deadline16 Jan 2028, about 14 months from filing

A hall started this month

Built in 12–18 months from Nov 2026about Nov 2027 to May 2028

Fast-lane applications closeAug 2028

First fast-lane cycle finishes2029

Gapa finished hall can wait a year or more for a firm answer

Three caveats. First, the hall example is an illustration, not a forecast for any named project: some sites already have firm service or are deep in the current queue, and they are not waiting on the new lane. Second, the dates depend on FERC accepting the filings as written and on time, which is not certain. Third, the 30 GW is PJM's forecast of peak growth, and the 10 GW is its estimate of computational load today; the two are not measured the same way, so the 3x is a rough scale, not a precise ratio.

## So what is the stuck step?

Firm power. PJM is not short of data center requests, and it is not refusing to connect them. It is offering more ways in. But every faster way in is non-firm, and every firm way in still waits for upgrades and, for new requests, for a study lane that opens in late 2027\. Three things keep the step tight:

- **The fast lane starts late.** Its first window opens in late November 2027 and its first cycle finishes in 2029, behind halls that take 12 to 18 months to build.
- **The bridge can be cut.** Interim service is energy only and cut before firm users. A tenant that needs its GPUs running every hour cannot treat it as firm.
- **None of it is approved.** These are proposals. PJM asked for 60 days of comments and an order within 120 days. FERC can change or split them.

So-what: on PJM the scarce thing is not a site, a building permit or a tenant. It is a firm megawatt that the grid has studied and upgraded for. That is the same bind we saw from the supply side in October, when PJM's last auction came up 6,831 MW short; see our [PJM capacity shortfall Pulse](https://www.sotkn.com/markets/us/us-pjm-capacity-shortfall-october-2026/) and the [PJM backstop Catalyst](https://www.sotkn.com/catalyst/pjm-6831-mw-power-backstop-data-center-growth/).

## What does this mean for data center landlords and their tenants?

For a landlord, the question a tenant asks is simple: when is my power on, and can it be cut? These filings give a landlord new answers to the first part, and harder answers to the second. A site could switch on earlier on interim service, but its lease would have to say what happens on the days the grid cuts it. A site that wants to avoid capacity costs could take non-firm contract demand, but it then sits near the front of the cut queue.

That pushes value toward halls that already hold firm service in northern Virginia and the rest of PJM, and toward landlords that can run a site flexibly: shifting work, using stored energy, or accepting cuts in their contracts. It also adds a cost line for every operator, new or old, in ride-through equipment and around-the-clock control.

The big listed landlords with large PJM footprints are mapped in [What does Digital Realty do?](https://www.sotkn.com/stack/ai-data-centers/what-does-digital-realty-do/) and [What does Equinix do?](https://www.sotkn.com/stack/ai-data-centers/what-does-equinix-do/). For the difference between renting space and renting a whole hall, see [colocation explained](https://www.sotkn.com/explained/colocation-explained/). For what happens when one huge campus waits for its first megawatts in Virginia, see our [Virginia 3 GW Pulse](https://www.sotkn.com/markets/us/us-virginia-3gw-data-center-first-power-october-2026/).

## Which dates test this read next?

![Calendar of dates that test the PJM read: comments by mid-January 2027, ride-through from 16 January 2027, new services from 16 March 2027, the first fast lane window in late 2027 and first results in 2029](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/us-pjm-fast-energization-data-center-firm-power-november-2026-calendar.png)

Dates that test the read. · Education only.

- About 15 January 2027 — comments due, if FERC grants the 60 days PJM asked for (our arithmetic). The test: whether data center owners push back on the cut order or the deposits.
- 16 January 2027 — PJM's requested start for the ride-through rules for new sites. The test: whether FERC accepts them, even if it splits them from the rest.
- 16 March 2027 — PJM's requested start for the new services and the 50 MW netting limit, and about 120 days from filing. The test: a FERC order, as filed or changed.
- Second quarter of 2027 — PJM's pencilled ramp-rate filing, in its October timeline. The test: how tightly data centers' swings are capped.
- Late November 2027 — PJM's expected opening of the first Fast Energization window. The test: whether it opens on time.
- 16 January 2028 — deadline for existing sites to ride through, in PJM's October draft. The test: exceptions and refits.
- August 2028, then 2029 — applications close, then the first cycle finishes. The test: how many megawatts come out firm.

## How does PJM compare with New England, Texas and Asia?

Three days before PJM, New England's grid operator filed its own large-load rules, with interim and non-firm service and a price above which sites give way; see our [New England large-loads Pulse](https://www.sotkn.com/markets/us/us-iso-ne-large-loads-own-capacity-november-2026/). Texas went the other way on cost, charging $50,000 a megawatt in security just to be studied; see our [Texas large-load rule Pulse](https://www.sotkn.com/markets/us/us-texas-large-load-rule-october-2026/). And inside PJM, utilities are building their own bridges, as in our [Kentucky Power Pulse](https://www.sotkn.com/markets/us/us-kentucky-power-terawulf-gas-plant-bridge-november-2026/), where a gas plant is the answer.

In Asia, the bind looks the same from different sides. Malaysia's halls are outrunning its power plants, as today's [Malaysia reserve margin Pulse](https://www.sotkn.com/markets/malaysia/malaysia-reserve-margin-data-centres-power-plants-november-2026/) showed. In Australia, NEXTDC's Melbourne hall waits on a 66 kV line, in today's [NEXTDC M3 Pulse](https://www.sotkn.com/markets/australia/australia-nextdc-agm-m3-66kv-power-november-2026/). In Korea, the queue is for high-voltage lines into Seoul, as our [Korea grid queue Pulse](https://www.sotkn.com/markets/korea/korea-ai-data-centre-grid-queue-october-2026/) found. PJM's version is the most formal: it is writing the wait into the tariff.

## What would change this view?

- FERC orders the fast lane to start sooner, or lets new requests into the current queue faster — the 2029 clock would shorten.
- FERC rejects or waters down the cut order for interim and non-firm service — flexible power would be closer to firm, and landlords would gain.
- Data center owners show they can ride through and cap draw cheaply — the equipment bill would be smaller than the rules imply.
- Large-load requests drop sharply once deposits are due — the queue would thin and firm megawatts would free up for real projects.
- New generation arrives faster than PJM expects — the capacity side of the bind would ease, though upgrades would still set the pace.

## Practical takeaways

- PJM filed ER27-531 and ER27-522 at FERC on 16 November 2026; nothing is approved yet
- Fast Energization: power plants and large users studied together, target 12 months, deposits earlier
- First window opens late November 2027; applications close August 2028; first cycle finishes 2029
- New services: interim (interruptible, energy only), firm contract demand, non-firm contract demand
- Ride-through for sites with 25 MW or more behind power electronics, from 16 January 2027; existing sites a year later
- PJM: about 10 GW of computational load today, 30 GW of data center peak growth to 2030
- Wire owners and running plants are paid first. Stuck step: firm power

## FAQ

**What did PJM file on 16 November 2026?**  
Two proposals at the Federal Energy Regulatory Commission. The first, docket ER27-531, sets up a Fast Energization Process that studies new power plants and large users such as data centers together and aims to finish in 12 months instead of about two years. It also adds three new kinds of grid service for large users. The second, docket ER27-522, says data centers with 25 MW or more of power-electronics load must ride through grid disturbances instead of dropping off the system.

**When does the faster process start?**  
Not soon. PJM says the window for the first Fast Energization cycle opens the business day after the current cycle's second decision point, which it expects in late November 2027\. Applications would be due in August 2028 and the first cycle would finish in 2029\. Until then, requests go through the existing Necessary Studies process.

**Can a new data center get power before its grid upgrades are built?**  
Under the proposal, yes, but not firm power. Interim network service lets a site use spare room on the grid while it waits for upgrades. It is energy-only, it is interruptible, and it can be cut first, alongside non-firm service. Firm Contract Demand service gives energy and capacity up to a set level and is treated like normal firm service when the grid has to cut load.

**What are the ride-through rules?**  
A data center that sees a voltage or frequency dip must stay connected, within limits PJM will write into its manuals, rather than switching itself to backup power. PJM says it already has about 10 GW of computational load and has seen sudden load drops of about 1.5 GW in July 2024, 1.8 GW in February 2025 and 3.9 GW in July 2026\. PJM asked for the rules to take effect on 16 January 2027\. Existing sites get a year to comply.

**Who gets paid, and what is the stuck step?**  
On our map: the transmission owners who build the upgrades, which states can now bill to large users; the power plants already running, whose capacity firm customers must buy; and the makers of the power and control gear the new rules require. New data center owners and their tenants wait. The stuck step is firm power, and the process that decides who gets it does not return its first answers until 2029.

**Is this investment advice?**  
No. Education only. It maps who gets paid and which step is stuck. It is not a recommendation to buy or sell any security, and we leave out share prices, valuations, broker ratings and price targets on purpose.

## Keep reading on the map

- [US Markets hub](https://www.sotkn.com/markets/us/) — country page
- [PJM capacity shortfall Pulse](https://www.sotkn.com/markets/us/us-pjm-capacity-shortfall-october-2026/) · [PJM backstop Catalyst](https://www.sotkn.com/catalyst/pjm-6831-mw-power-backstop-data-center-growth/) · [PJM Ohio power study Wire](https://www.sotkn.com/wire/pjm-softbank-10-gw-ohio-data-center-power-study-wire/)
- [New England large-loads Pulse](https://www.sotkn.com/markets/us/us-iso-ne-large-loads-own-capacity-november-2026/) · [Texas large-load rule Pulse](https://www.sotkn.com/markets/us/us-texas-large-load-rule-october-2026/) · [Kentucky Power Pulse](https://www.sotkn.com/markets/us/us-kentucky-power-terawulf-gas-plant-bridge-november-2026/) · [Virginia 3 GW Pulse](https://www.sotkn.com/markets/us/us-virginia-3gw-data-center-first-power-october-2026/)
- [AI Data Centers on the Stack](https://www.sotkn.com/stack/ai-data-centers/) · [Digital Realty](https://www.sotkn.com/stack/ai-data-centers/what-does-digital-realty-do/) · [Equinix](https://www.sotkn.com/stack/ai-data-centers/what-does-equinix-do/)
- [What is an AI data center?](https://www.sotkn.com/explained/what-is-an-ai-data-center/) · [Where AI data centers are located](https://www.sotkn.com/explained/where-are-ai-data-centers-located/) · [How long a build takes](https://www.sotkn.com/explained/how-long-does-it-take-to-build-an-ai-data-center/) · [Contracted power](https://www.sotkn.com/explained/contracted-power-explained/)
- [All Markets doors](https://www.sotkn.com/markets/) — Taiwan, Korea, US, China, Singapore, Australia, Malaysia

**Get the Wire.** Second Order’s free daily brief on what moved in the AI chip map. [Read the Wire →](https://www.sotkn.com/the-wire/) · [Subscribe free →](https://www.sotkn.com/#/portal/signup)

**Members’ Analysis (teaser):** When the stuck step moves, where does cash stick? The free line: whoever clears the bind is paid before whoever waits on it. [Read the Analysis →](https://www.sotkn.com/analysis/where-does-the-stuck-step-move/)

**How we check this.** The process, the three new services, the curtailment order, the 50 MW netting limit, the load forecast and build-time figures, and every effective date come from PJM's filing in FERC docket ER27-531 of 16 November 2026\. The Large Computational Load definition, the 10 GW figure, the three load drop events and the January dates come from PJM's filing in docket ER27-522 the same day. The draft ride-through table, the 16 January 2028 deadline for existing sites and the 2027 ramp-rate timeline come from PJM's Planning Committee slides of 6 October 2026\. The detailed curtailment buckets and the capacity table come from PJM's workshop slides of 5 October 2026, which PJM calls a work in progress. The two-years-to-one summary and the point about states billing large loads come from PJM's Inside Lines post of 16 November. Anything we worked out ourselves is labelled “our arithmetic”. Nothing here has been approved by FERC yet. Share prices, valuations, broker ratings and price targets are left out on purpose. The references we used are listed at the end. [Our editorial standards →](https://www.sotkn.com/editorial-standards/)

Not investment advice. Do your own research.

---

### References

1. PJM Interconnection, Proposed Tariff Revisions for Large Loads and Additional Compliance with Co-Location Order, FERC Docket No. ER27-531-000, 16 Nov 2026\. [pjm.com](https://www.pjm.com/-/media/DotCom/documents/ferc/filings/2026/20261116-er27-531-000.pdf?ref=sotkn.com) — Fast Energization Process (studies in 12 months, screening of about four months, readiness deposits, window opening late November 2027, first cycle finishing 2029); Interim NITS, Firm and Non-Firm Contract Demand service and curtailment order; 50 MW netting limit; 32 GW peak growth with 30 GW from data centers; 12-18 month build times; effective date 16 March 2027; 60-day comment period and 120-day order request.
2. PJM Interconnection, Proposal to Address Operational Requirements for Large Computational Load and Establish an Annual Transmission Service Reporting Requirement, FERC Docket No. ER27-522-000, 16 Nov 2026\. [pjm.com](https://www.pjm.com/-/media/DotCom/documents/ferc/filings/2026/20261116-er27-522-000.pdf?ref=sotkn.com) — Large Computational Load defined as a Large Load with 25 MW or more behind power electronic conversion equipment; ride-through framework effective 16 January 2027; existing sites given a year; about 10 GW of computational load in PJM; load transfer events of about 1.5 GW, 1.8 GW and 3.9 GW; Manual work in 2027.
3. PJM Inside Lines, PJM Plan Would Cut Interconnection Process Time in Half, 16 Nov 2026\. [insidelines.pjm.com](https://insidelines.pjm.com/pjm-proposal-would-cut-interconnection-process-time-in-half/?ref=sotkn.com) — two years to one; readiness and financial requirements moved earlier; states given the costs of data center driven upgrades so they can bill large loads; ride-through so sites stay connected instead of switching to backup power.
4. PJM, Large Computational Load (LCL) Ride-Through Requirements: PJM Interconnection Proposal, Planning Committee, 6 Oct 2026\. [pjm.com](https://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2026/20261006/20261006-item-07-b---1-lcl-ride-through-requirements-solution---presentation.pdf?ref=sotkn.com) — draft voltage and frequency ride-through table; new projects from 16 January 2027; existing sites by the later of 16 January 2028 or one year after commercial operation; 90-day acceleration for risky sites; ramp-rate work in 2027.
5. PJM, Operationalizing Flexible Large Loads: Curtailment Overview, Co-located Load Order Workshop, 5 Oct 2026\. [pjm.com](https://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20261005/20261005-item-02---operationalizing-flexible-large-loads-curtailment-overview---presentation.pdf?ref=sotkn.com) — conceptual curtailment order (non-firm contract demand and interim service cut before emergency steps); flexible services left out of capacity procurement and capacity costs; 24x7 control centre requirement.