# What Does Fermi America Do? Project Matador Power Campus
- URL: https://www.sotkn.com/stack/ai-data-centers/what-does-fermi-america-do/
- Published: 2026-11-23T13:28:44.000Z
- Updated: 2026-11-23T13:28:44.000Z
- Description: Fermi Inc., trading as Fermi America (FRMI), is building Project Matador, a private-power AI data center campus in the Texas Panhandle. At 30 September 2026 it had $315.5M of cash, $999.9M of debt, no revenue and no signed tenant lease. A hyperscaler signed a 600 MW letter of intent.
- Author: Sean
- Tags: #layer-ai-data-centers

Fermi Inc. (Nasdaq and London: FRMI) trades as Fermi America. It was formed in January 2025 and has not earned any revenue. It is building one project, called Project Matador, on land leased from the Texas Tech University System in Carson County, in the Texas Panhandle. The idea is to put its own power plant next to the data centers, so a big AI tenant does not have to wait for the public grid. The company says the site is designed for up to 11 GW of power, and up to about 17 GW if it wins more permits and land. Today the real numbers are smaller. At 30 September 2026 it had $315.5 million of cash, $999.9 million of debt, and no signed tenant lease. In November it lost one tenant, TensorWave, and signed a non-binding letter of intent with another, an unnamed investment-grade hyperscaler, for about 600 MW. That tenant has paid money up front. It has not yet signed a lease.

`AI DATA CENTERS` · `Data as at 30 Sep 2026; events to 23 Nov 2026` · `Next update: after Fermi's fourth-quarter 2026 results (date not given in its filings at 23 Nov 2026)`  
**Affects:** AI Data Centers · US power · Texas Panhandle · natural gas and nuclear

Fermi sits on the [AI Data Centers layer](https://www.sotkn.com/stack/ai-data-centers/) as a power-first developer. It is not a miner turned landlord like [Galaxy Digital](https://www.sotkn.com/stack/ai-data-centers/what-does-galaxy-digital-do/), [Core Scientific](https://www.sotkn.com/stack/ai-data-centers/what-does-core-scientific-do/) or [Keel Infrastructure](https://www.sotkn.com/stack/ai-data-centers/what-does-keel-infrastructure-do/). It is not a landlord with many halls like [Equinix](https://www.sotkn.com/stack/ai-data-centers/what-does-equinix-do/) or [Digital Realty](https://www.sotkn.com/stack/ai-data-centers/what-does-digital-realty-do/). It is a developer that owns a very large piece of land, a pile of power equipment, a lot of debt and a long list of conditions. The one thing it does not yet own is a signed lease. This page covers what Fermi is building, how it plans to be paid, how it is funded, and which dates in the next few weeks matter.

**In short:** Fermi plans to earn money by leasing powered land and data center space at Project Matador to hyperscale tenants for 15 to 20 years, with its own gas and, later, nuclear power behind them. It has no revenue today. At 30 September 2026 it held $315.5 million of cash (including restricted cash) against $999.9 million of debt, and said that, before its own plans are counted, its cash was not enough for the next twelve months. On 10 November it signed a non-binding letter of intent with an unnamed hyperscaler for about 600 MW and received a $200 million prepayment commitment. The stuck step is a signed lease: its ground lease with Texas Tech needs a tenant of at least 200 MW by 31 December 2026, or an extension.

*Education only, not advice to buy or sell any security. Figures are from Fermi Inc.'s filings with the US Securities and Exchange Commission: its quarterly report on Form 10-Q for the period to 30 September 2026, filed 12 November 2026; its third-quarter 2026 results release and investor presentation (8-K, 12 November 2026); its 14 October 2026 TensorWave fact sheet (8-K); its 16 October 2026 8-K on its MUFG loan; and its 23 November 2026 8-K on the customer prepayment. Fermi reports in US dollars under US GAAP. MW and GW mean gross power unless stated, not the IT load a tenant would get.*

## Numbers that matter

Cash

$315.5M

Cash $286.3M plus restricted cash $29.2M · 30 Sep 2026

**Thin**

Debt

$999.9M

Face value of four borrowings, $958.4M after costs · 30 Sep 2026

**Heavy**

Revenue

None

Formed Jan 2025; the 10-Q says no revenue until leased capacity is delivered

**Pre-revenue**

Signed tenant lease

None

600 MW hyperscaler letter of intent is non-binding · 10 Nov 2026

**Bind**

Customer prepayment

$200M

Agreed with the unnamed hyperscaler; the 23 Nov 8-K says it has been funded

**Cushion**

Power capacity (company)

2.2 GW

Includes 200 MW from Xcel Energy and six turbines due in 2028 · company slides, 12 Nov 2026

**Plan**

Spend planned, next 12 months

$2–3B

Company estimate for building out Matador, if leases are signed · 10-Q

**Needs funding**

Q3 2026 net loss

$141.6M

$142.2M of overhead, $87.3M of it stock-based or paid in shares · three months to 30 Sep 2026

**Loss**

Status chips are Second Order's read. Cash, debt, loss, capacity and spending are Fermi's own figures from its 10-Q, results release and slides. The $87.3M split and the cash-to-debt gap are our arithmetic (see below). Capacity figures are gross power, not the IT load a tenant would get.

## What does Fermi America actually do?

It is building a private power plant and a very large data center campus on one piece of Texas land, then trying to lease it to hyperscale tenants. It sells nothing today.

**From a land and power developer with no revenue to, if it works, a landlord with 15 to 20 year leases.**

1. **It holds the land.** In May 2025 it signed a 99-year ground lease with the Texas Tech University System. The lease started in September 2025 for about 4,523 acres, and the 10-Q says a further 713-acre tract is to be added. With nearby land it owns, has under contract or holds options on, the company says the campus would reach about 8,400 acres.
2. **It buys its own power equipment.** The 10-Q lists Siemens contracts for three SGT6-5000F and six SGT-800 gas turbine units, with about $126.2 million still to pay at 30 September 2026\. It also has a lease with Mobile Power Solutions LLC that starts fixed payments once it commences, and an electric service contract with $5.0 million of fixed reservation payments due in the next twelve months.
3. **It plans gas now and nuclear later.** The 10-Q says the company plans four Westinghouse AP1000 nuclear units, one commissioned in each of 2034, 2035, 2036 and 2037\. The first unit has slipped about a year. The nuclear regulator's draft environmental review was open for comment until 23 November 2026.
4. **It hunts for tenants first and builds second.** Fermi says it will sequence spending with signed leases. The 10-Q says vertical construction starts only after a definitive tenant lease and a notice to proceed from Texas Tech. Its sales pitch is speed to power: land, permits and generation already in hand.
5. **It is changing how it sells.** The company's slides call the first product 'Powered Land+': power and land, with the tenant building the data center itself. The 10 November hyperscaler letter of intent is for 'powered land', not a finished data hall. Fermi's own illustrative range puts this at $3.9 to $5.1 million of capital per MW, against $12.1 to $15.0 million for a turnkey data center. Those are company estimates from market deals, not forecasts.

| Piece of Matador                 | What the filings say                                                                                                  | Where it stands                                                                                                         |
| -------------------------------- | --------------------------------------------------------------------------------------------------------------------- | ----------------------------------------------------------------------------------------------------------------------- |
| Land                             | 99-year Texas Tech ground lease, about 4,523 acres started Sep 2025; campus planned at about 8,400 acres with options | Vertical construction needs a notice to proceed from Texas Tech by 31 Dec 2026, which needs a tenant of at least 200 MW |
| Gas turbines                     | Three SGT6-5000F and six SGT-800 units on Siemens contracts; $126.2M still to pay at 30 Sep 2026                      | Company slides show units arriving on site; no power sold yet                                                           |
| Utility power                    | The slides count 200 MW from Xcel Energy under an electric service agreement for 2027                                 | Credit support for the electric service must be posted before service starts; none posted at 30 Sep 2026                |
| Third-party gas plant (Hillcore) | Hillcore would build, own and run up to about 2.6 GW on a 400-acre part of the site; an initial block of about 360 MW | Framework only; deadline for final documents moved to 18 Dec 2026                                                       |
| Nuclear                          | Four AP1000 units planned, 2034 to 2037; FEED study done July 2026                                                    | Draft environmental review out; comments ran to 23 Nov 2026; first unit slipped about a year                            |
| Air permit                       | Slides show a 6 GW permit issued by Texas regulators and 5 GW more filed                                              | A court petition challenges the permits for the west campus; the 10-Q says no docket activity since 14 May 2026         |

The size claims have layers. The 10-Q says Project Matador is designed to deliver up to 11 GW of power, and about 17 GW if more land closes and more permits arrive. The company's own slides count 2.2 GW as total capacity today, and that count includes 200 MW from a utility and six turbines expected in 2028\. The 10-Q says the energy and floor-space figures are unaudited and outside its auditor's review. We use the lower, nearer-term numbers and label the big ones as plans.

Fermi does not report any rent, any megawatt of leased power, or any energized data center. It does not give a date for first power at a data hall that we can tie to a signed lease. We do not estimate one.

Fermi has deferred its plan to become a real estate investment trust. It is taxed as a normal company, at least through 2026.

---

## How does Fermi America make money?

It does not yet. The plan is rent and power charges from long leases. The only cash so far has come from lenders, investors and one customer prepayment.

- **Rent and power charges under long leases.** The company's slides talk about running the site over 15 to 20 year leases with investment-grade hyperscalers, priced as fixed charges per kilowatt. In the TensorWave sheet, natural gas and variable power charges were passed through to the tenant. These are plans. No lease for Matador is in force today.
- **What a tenant deal looked like: TensorWave.** On 14 October 2026 Fermi released a fact sheet on a 15-year, 222 MW phase-one lease with TensorWave, backed by credit support from AMD. It said the lease was worth $6.5 billion over 15 years, with 156 MW of critical IT capacity and delivery from the fourth quarter of 2027\. It said power equipment would cost $3 to $4 million per MW and the data center $10 to $12 million per critical MW. That lease ended on 10 November 2026 (see below), so the figures are history, not revenue.
- **What the current tenant has done: prepay.** On 12 November Fermi said an unnamed investment-grade hyperscaler had agreed a $200 million prepayment, plus a $15 million early construction agreement. A $90 million steel and materials sale to the tenant is still being finalized. The 23 November 8-K says the customer prepay obligations have been met and the money has been funded. That 8-K does not give an amount, so we rely on the $200 million in the 12 November release.
- **Power as a service.** Fermi's slides describe selling power, powered land, powered shell or a turnkey hall, with power under all of them. Under the Hillcore plan, Fermi would buy power from Hillcore's plant on a take-or-pay basis and pass the fixed charge on to tenants. Fermi's guarantee of its payments would be capped at twelve months of those charges.

Costs are rising while revenue is zero. Third-quarter net loss was $141.6 million. General and administrative expense was $142.2 million, including $65.8 million of stock-based pay and $21.5 million of advisory fees paid in shares. Together those two items are $87.3 million, about 61% of overhead (our arithmetic). The nine-month net loss was $356.1 million. These are mostly non-cash, but they dilute shareholders. The company had 646,953,440 shares outstanding on 5 November 2026.

Cash used in operations was $110.6 million over nine months, about $12.3 million a month (our arithmetic: $110.6 million ÷ 9). Investment in property, plant and equipment was $759.5 million over the same period, and net equipment and buildings stood at about $1.67 billion on the balance sheet. The gap was funded by $979.8 million of new debt, partly offset by repaying a $144.3 million loan from Macquarie.

The prepayment matters because it is the first time a big tenant has put cash in. It is a deposit, not rent. The filings do not say how or whether it is refunded if no lease is signed, and we do not guess.

---

## What limits it?

No signed lease. A thin cash pile next to $1.0 billion of debt. A string of December dates. A long list of leadership and legal noise.

1. **No signed tenant lease, and the last one fell through.** The 10-Q lists the risk that Fermi may not sign a definitive lease with the hyperscaler, and says terms could differ from the letter of intent. The TensorWave lease, announced on 14 October as a binding 15-year deal, ended on 10 November because its closing date of 31 October passed without an extension. The AMD credit support agreement ended with it. The filings we read do not say why the deal did not close.
2. **The ground lease has a deadline.** The Texas Tech lease needs a notice to proceed by 31 December 2026 before vertical construction. Texas Tech can end the lease if it is not issued. The notice depends on, among other things, a signed lease with a phase-one tenant for at least 200 MW. The 10-Q says that condition has not been met and that Fermi is talking to Texas Tech about an extension. Fermi's 12 November release quotes Texas Tech's chancellor saying the university remains committed to the project. Fermi also owes $9.0 million into a lease escrow by 31 December 2026.
3. **Cash is small next to debt and spending plans.** At 30 September 2026 Fermi held $315.5 million of cash including restricted cash. Debt was $999.9 million at face value: $444.9 million of turbine financing from MUFG and others, $431.3 million of 5.00% convertible notes due July 2031, $91.5 million of high-voltage equipment loans and $32.3 million of a second turbine loan. Cash covers about 32% of debt, and the gap is $684.4 million (our arithmetic: $999.9 million − $315.5 million). Fermi says it expects to spend about $2 to $3 billion over the next twelve months if leases arrive. That is about 6 to 10 times today's cash (our arithmetic: $2 to $3 billion ÷ $315.5 million). The 10-Q says that, before management's plans, its cash is not enough for the next twelve months and that this raised substantial doubt about its ability to continue. Management concluded its plans, such as unused loan capacity, equipment sales and sequencing spending, relieve that doubt. The $200 million prepayment came after 30 September.
4. **Lender dates and conditions.** The MUFG turbine loan has an event of default if Fermi has not arranged a fully committed financing for the first phase, enough for at least 400 MW of generation, by 10 February 2027\. The 9 October amendment removed a separate deadline to sign a 400 MW lease by 10 November 2026\. Fermi believes this avoids about $22 million of extra principal payments in the fourth quarter of 2026, $19 million in the first quarter of 2027 and $15 million in the second. It paid $25 million in amendment fees. The 10-Q says draws under the loan could be made until the nine-month anniversary of the February closing, and that $444.9 million was outstanding at 30 September. The Keystone high-voltage loan requires prepayment if an approved customer agreement is not received by 31 December 2026, and a minimum of $20 million of liquidity.
5. **Big power plans are far away.** The 10-Q puts nuclear units at 2034 to 2037, with the first slipping a year. The Hillcore gas plant is a framework with an 18 December 2026 deadline for signed documents. A natural gas contract needs credit support by the earlier of Fermi electing to start deliveries or 31 December 2026\. A court petition seeks to overturn air permits for the west campus. Fermi says the challenge is without merit.
6. **People and legal noise.** The board removed Toby Neugebauer as chief executive in April 2026 and ended his employment for cause. Lee McIntire became CEO on 11 August 2026\. The chief nuclear construction officer left on 12 October. The company reports a federal subpoena in July and an SEC document request in August about Matador, the company and former managers, and says neither contains an allegation of wrongdoing. The 10-Q also says votes in November 2026 favored limits on data center building in many places, which could reduce tenant demand.

Where the filings are silent we say so. Fermi does not name the hyperscaler, give a rent per MW for the letter of intent, say whether the $200 million is refundable, name a first power date tied to a signed lease, say why TensorWave did not close, or give the date of its fourth-quarter results. We do not estimate any of those.

---

## Who else does this?

Roles, not a league table.

| Company                                                                                                                                                                                                                                                                            | What it does                                                  | What makes it different                                                             |
| ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | ------------------------------------------------------------- | ----------------------------------------------------------------------------------- |
| **Fermi America**                                                                                                                                                                                                                                                                  | Private-power AI campus in the Texas Panhandle                | No revenue; 600 MW hyperscaler letter of intent; $200M prepayment; no signed lease  |
| **[Galaxy Digital](https://www.sotkn.com/stack/ai-data-centers/what-does-galaxy-digital-do/)**                                                                                                                                                                                     | Helios AI campus in West Texas plus a crypto finance business | 526 MW leased to CoreWeave, 133 MW live                                             |
| **[Applied Digital](https://www.sotkn.com/stack/ai-data-centers/what-does-applied-digital-do/)**                                                                                                                                                                                   | North Dakota AI campuses                                      | Funds builds with project debt against long leases                                  |
| **[Keel Infrastructure](https://www.sotkn.com/stack/ai-data-centers/what-does-keel-infrastructure-do/) / [Hut 8](https://www.sotkn.com/stack/ai-data-centers/what-does-hut-8-do/) / [Core Scientific](https://www.sotkn.com/stack/ai-data-centers/what-does-core-scientific-do/)** | Former miners turning power sites into leased halls           | Start from existing sites and grid connections; read each page for tenant and stage |
| **[Equinix](https://www.sotkn.com/stack/ai-data-centers/what-does-equinix-do/) / [Digital Realty](https://www.sotkn.com/stack/ai-data-centers/what-does-digital-realty-do/)**                                                                                                      | Global data-center landlords                                  | Many tenants and cities, investment-grade funding, rent already coming in           |

What separates Fermi is the order of events. Most of the companies above had a lease before they raised large sums. Fermi has raised and spent first, and is now trying to turn a pipeline of prospects into leases. Its CEO said on 12 November that if prospects convert, they would fill its 2.2 GW. That is the company's view. The filings show equipment, land, loans and one prepayment, not yet a lease.

---

## What would change this view?

The read on the model weakens if:

- Fermi signs a definitive lease with the hyperscaler, with a named or described tenant, megawatts, term and rent.
- Texas Tech issues the notice to proceed, or extends the 31 December 2026 deadline in writing.
- Fermi closes the Hillcore documents by 18 December 2026, or the date slips again.
- Fermi arranges committed financing for the first 400 MW before the 10 February 2027 loan date, or the lenders waive it again.
- Cash falls far faster than the $12.3 million a month of operating cash use seen over nine months, or Fermi sells new stock or debt before a lease is signed.

The read holds while a signed lease, the Texas Tech notice and committed project financing arrive before the cash and the loan dates run out.

---

## Practical takeaways

- Fermi America is Fermi Inc. (FRMI), a pre-revenue developer of Project Matador, a private-power AI campus in Carson County, Texas.
- At 30 September 2026 it held $315.5 million of cash and $999.9 million of debt, and the 10-Q says its cash alone is not enough for the next twelve months without its plans.
- It has no signed tenant lease. TensorWave's lease ended on 10 November 2026, and a 600 MW hyperscaler letter of intent is non-binding.
- The hyperscaler agreed a $200 million prepayment, and the 23 November 8-K says the prepay obligations have been funded.
- The key date is 31 December 2026: Texas Tech's notice to proceed needs a signed tenant of at least 200 MW, or an extension.
- Third-quarter overhead of $142.2 million was about 61% stock-based pay and share-paid fees (our arithmetic).

---

## FAQ

**What does Fermi America do?**  
Fermi America is the trading name of Fermi Inc. (FRMI). It is developing Project Matador, a large private-power AI data center campus on leased land in the Texas Panhandle. It plans to lease powered land and data center space to hyperscale tenants, backed by its own gas power and, later, nuclear. It has no revenue yet.

**Is Fermi America a REIT?**  
Not at the moment. Fermi said it intended to elect REIT status, then deferred the election. The 10-Q says it has no REIT election in place and expects to be taxed as a normal company at least through 2026.

**Does Fermi America have a tenant?**  
Not under a signed lease. On 10 November 2026 it signed a non-binding letter of intent with an unnamed investment-grade hyperscaler for about 600 MW of powered land, with a $200 million prepayment agreement and a $15 million early construction agreement. Its earlier lease with TensorWave ended on 10 November 2026.

**What happened to the TensorWave lease?**  
Fermi announced a 15-year lease with TensorWave on 14 October 2026, with AMD credit support. The closing date of 31 October passed without an extension, and the lease ended on 10 November 2026, together with the AMD credit support agreement. The filings do not give a reason.

**How much power does Fermi America have?**  
The company's slides show 2.2 GW of total capacity, including 200 MW from Xcel Energy and six turbines expected in 2028\. It says Project Matador is designed for up to 11 GW and could expand to about 17 GW with more land and permits. Those are plans, and the 10-Q says the figures are unaudited. It has not sold any power.

**Why does Fermi's filing mention going concern?**  
The 10-Q says that, before management's plans, its cash and restricted cash of $315.5 million were not enough for its obligations over the next twelve months, which raised substantial doubt. Management concluded its plans, including unused loan capacity and timing spending to leases, relieve that doubt. It said there is no guarantee those plans work.

---

## Keep reading on the map

- **The layers:** [AI Data Centers](https://www.sotkn.com/stack/ai-data-centers/) · [Neoclouds](https://www.sotkn.com/stack/neoclouds/) · [Hyperscalers](https://www.sotkn.com/stack/hyperscalers/)
- **The terms:** [What Is an AI Data Center?](https://www.sotkn.com/explained/what-is-an-ai-data-center/) · [Data Center Leases Explained](https://www.sotkn.com/explained/data-center-lease-explained/) · [Data Center Financing Explained](https://www.sotkn.com/explained/data-center-financing-explained/) · [Power Purchase Agreement Explained](https://www.sotkn.com/explained/power-purchase-agreement-explained/) · [How Much Power Does an AI Data Center Use?](https://www.sotkn.com/explained/how-much-power-does-an-ai-data-center-use/)
- **Other developers on the layer:** [What Does Galaxy Digital Do?](https://www.sotkn.com/stack/ai-data-centers/what-does-galaxy-digital-do/) · [What Does Applied Digital Do?](https://www.sotkn.com/stack/ai-data-centers/what-does-applied-digital-do/) · [What Does Keel Infrastructure Do?](https://www.sotkn.com/stack/ai-data-centers/what-does-keel-infrastructure-do/) · [What Does Hut 8 Do?](https://www.sotkn.com/stack/ai-data-centers/what-does-hut-8-do/)
- **The tenants and the market:** [What Does CoreWeave Do?](https://www.sotkn.com/stack/neoclouds/what-does-coreweave-do/) · [US Markets](https://www.sotkn.com/markets/us/)

For how builders borrow against a signed lease, read [Data Center Financing Explained](https://www.sotkn.com/explained/data-center-financing-explained/). This page stays the free Stack read of Fermi's data-center plan.

## Sean

Writes Second Order by TKN — a plain-English map of AI infrastructure. Who gets paid, where money sticks, which step is stuck. Not investment advice.

[Author page →](https://www.sotkn.com/author/sean/) · [Editorial standards →](https://www.sotkn.com/editorial-standards/)

## How we check this

Figures come from Fermi Inc.'s SEC filings listed below: its Form 10-Q for the quarter to 30 September 2026 (filed 12 November 2026), its third-quarter 2026 results release and investor presentation (Form 8-K, 12 November 2026), its TensorWave fact sheet (Form 8-K, 14 October 2026), its 8-K on the MUFG loan amendment (16 October 2026) and its 8-K on the customer prepayment (23 November 2026). Power, acreage and floor-space figures are the company's own and are unaudited; capacity plans, lease talks, delivery dates and market-rate ranges are company statements, not facts we can check. Where we work something out ourselves, the arithmetic is shown and labelled. Fermi does not name the hyperscaler, give rent for the letter of intent, or say whether the prepayment is refundable, so we leave those blank instead of estimating. We do not give a view on the shares or on any price.

**Last reviewed:** 23 Nov 2026 · **Next review:** after Fermi's fourth-quarter 2026 results, or sooner if a lease is signed or the Texas Tech deadline moves (dates not given in its filings at 23 Nov 2026)  
Spot an error? Tell us and we will correct it and note the change here.  
[Our editorial standards →](https://www.sotkn.com/editorial-standards/)

## References

1. Fermi Inc., [Form 10-Q for the quarter ended September 30, 2026](https://www.sec.gov/Archives/edgar/data/2071778/000207177826000058/frmi-20260930.htm?ref=sotkn.com) (company, SEC filing), 12 Nov 2026 — Cash, debt table, going concern, Texas Tech lease and deadline, Hillcore, nuclear, TensorWave termination, hyperscaler letter of intent, MUFG terms, commitments, losses, risk factors
2. Fermi Inc., [Fermi Q3 2026 Earnings Release (Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/2071778/000121390026118351/ea031197701ex99-1.htm?ref=sotkn.com) (company, results release), 12 Nov 2026 — Hyperscaler prepayment and agreements, TensorWave termination, Texas Tech statement, quarterly highlights
3. Fermi Inc., [Investor Presentation, November 12, 2026 (Exhibit 99.2)](https://www.sec.gov/Archives/edgar/data/2071778/000121390026118351/ea031197701ex99-2.htm?ref=sotkn.com) (company, investor presentation), 12 Nov 2026 — 2.2 GW capacity, Xcel power, air permits, Powered Land+ model and illustrative capital ranges
4. Fermi Inc., [TensorWave Fact Sheet, dated October 14, 2026 (Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/2071778/000121390026109227/ea030854601ex99-1.htm?ref=sotkn.com) (company, fact sheet), 14 Oct 2026 — TensorWave lease terms, $6.5B contracted revenue claim, 222 MW and 156 MW, unit cost estimates
5. Fermi Inc., [Form 8-K, MUFG loan amendment](https://www.sec.gov/Archives/edgar/data/2071778/000121390026109980/ea0308831-8k%5Ffermi.htm?ref=sotkn.com) (company, SEC filing), 16 Oct 2026 — Removal of the 400 MW lease covenant, avoided principal payments, $25M amendment fees
6. Fermi Inc., [Form 8-K, customer prepay agreement fulfilled](https://www.sec.gov/Archives/edgar/data/2071778/000121390026122877/ea0313210-8k%5Ffermi.htm?ref=sotkn.com) (company, SEC filing), 23 Nov 2026 — Customer prepayment obligations fulfilled and funded