# Amazon starts its $7B Indiana campus; the gas plant comes in 2030
- URL: https://www.sotkn.com/wire/amazon-7b-indiana-campus-gas-plant-2030-wire/
- Published: 2026-11-14T23:37:33.000Z
- Updated: 2026-11-14T23:37:33.000Z
- Description: Amazon broke ground on its $7 billion Wheatfield campus in Indiana on 12 November. Its utility contract starts in 2027 and rises to 2,400 MW by 2032, but the gas plant built to serve it is now due in 2030, so batteries and bought capacity bridge the gap.
- Author: Sean
- Tags: #desk-wire

`WIRE` · `HYPERSCALERS` · `UNITED STATES` · Reported 12 Nov 2026 (groundbreaking, Wheatfield, Indiana)

**Amazon** broke ground on Thursday 12 November on a **US$7 billion** data center campus at Wheatfield in Jasper County, Indiana, on land it bought from the local utility, **NIPSCO**. The site sits next to NIPSCO's Schahfer generating station, where the utility's generation arm is building a gas plant to serve Amazon. That plant is now expected to start commercial operation in **2030**. On the [Hyperscalers layer](https://www.sotkn.com/stack/hyperscalers/), the halls start first and the firm power comes later.

## What happened

The campus

**US$7bn Project Rise at Wheatfield, about 250 permanent jobs**

Part of about US$33bn Amazon is putting into data centers at New Carlisle, Hobart and Wheatfield; Ryan Companies is the general contractor

The power contract

**Up to 2,400 MW for Amazon by the end of 2032**

A 15-year NIPSCO contract approved by Indiana's regulator on 17 June 2026, with service starting from 2027

The plant

**Gas plant now expected to start in 2030**

NiSource's 28 October quarterly filing cites a change to construction plans; the site is at grading and civil works

The county

**More than US$700m of payments over 35 years**

Paid in place of property tax under a 10-year abatement Jasper County approved in June

## Why cash cares

A data center earns nothing until its halls have firm power. Amazon has the land, the tax deal and a builder on site at Wheatfield. What it does not yet have is the plant that is meant to run its northern Indiana campuses around the clock. NiSource, NIPSCO's parent, said in its 28 October quarterly filing that the gas-fired combined-cycle plant for Amazon is now expected to reach commercial operation during 2030\. Its earlier window for the whole package was 2028 to 2032.

The contract does not wait for the plant. Under the deal Indiana's regulator approved in June, NIPSCO serves Amazon's data centers in the state from 2027, rising to up to **2,400 MW** by the end of 2032\. Voltgrid News, reading NiSource's filings, reports a fixed capacity charge from January 2027, guaranteed by Amazon.com. So Amazon starts paying for capacity roughly **three years** before the main plant is due to run.

Start with the size. NiSource says that at full ramp in 2032 it expects to use about **4,920 MW** of capacity to serve its three data center customers: Amazon, Alphabet and Microsoft. At the end of 2025 it owned about 3,967 MW and bought about 1,200 MW more under contracts. On our arithmetic, the data center load alone needs about **95%** as much capacity as NIPSCO's whole supply today, and Amazon's 2,400 MW is about **49%** of that data center total. The regulator's order plans **3,000 MW** of new capacity for Amazon's 2,400 MW, about **1.25 times** the load.

Wheatfield is about **21%** of the roughly US$33 billion Amazon is investing across its three northern Indiana campuses, on our arithmetic. At about 250 permanent jobs, that is roughly **US$28 million** of investment per job.

![Amazon's Indiana power: the campus starts in 2026, the contract from 2027, the gas plant in 2030](https://storage.ghost.io/c/cd/10/cd10e222-131f-4ba4-b4a9-ca4214e8c12d/content/images/2026/11/amazon-indiana-campus-before-plant-print.png)

**Figure: the campus starts before the plant.** Campus figures from The Times of Northwest Indiana (12 November 2026) and Data Center Digest (14 November 2026); contract terms from the Indiana regulator's 17 June 2026 order; plant timing, bridge resources and capacity from NiSource's quarterly filing of 28 October 2026\. Shares, ratios and per-job figures are our arithmetic.

## The step that is still open

The stuck step is the power block. NiSource says the gas site has its major permits, its engineering contractor has full notice to proceed, and work so far is site preparation, mass grading and civil works for the power block that comes later. Voltgrid reports two units of 1,300 MW each, and that NiSource's chief commercial officer said only one of them is moving to 2030\. NiSource has not said when the other unit is due.

Until then, Amazon's load is meant to be carried by what NiSource calls pool resources. A **400 MW** and a **100 MW** battery are being built at the site. NIPSCO has bought about **US$174.6 million** of market capacity for 2028 to 2030\. GenCo, the generation arm, has signed a capacity agreement for 2028 to 2040 worth about US$1.1 billion that still needs regulatory approval, and a battery toll of 600 MW with its first phase due by 1 December 2027\. Those resources serve all three data center customers, not Amazon alone.

## The second-order read

**Who gets paid.** NiSource, through GenCo. It expects to invest about **US$8.0 billion** in data center projects from 2027 to 2033, about **20%** of its US$40.0 billion capital plan on our arithmetic, with returns set by its contracts with Amazon, Alphabet and Microsoft. Blackstone Infrastructure owns 19.9% of GenCo's parent. Jasper County gets more than US$700 million over 35 years, about **US$20 million a year** on average. NIPSCO's existing customers get the land sale proceeds as bill credits, plus an estimated US$1.1 billion from an existing system charge Amazon pays over the contract.

**Who funds the wait.** Amazon. It pays for capacity from 2027 while the plant meant to serve it is still being built. Under the settlement, transmission study and upgrade costs also sit with GenCo or Amazon rather than NIPSCO's other customers.

**Who waits.** The halls. Amazon can pour concrete at Wheatfield now, but how fast it fills them depends on how much firm power the pool and batteries can deliver before 2030.

**Stuck step.** The combined-cycle power block at Schahfer, still at grading, with commercial operation now targeted for 2030.

## Three cautions

The filings do not say how many of the 2,400 MW go to Wheatfield rather than Hobart or New Carlisle. The contract covers Amazon's data centers in NIPSCO's area as a group.

The 2030 date is NiSource's target, and the company says it is an optimisation, not a delay. Some of the bridge resources, including the US$1.1 billion capacity agreement, are still awaiting approval.

Amazon has a one-time option, until 31 March 2029, to cut its commitment by **1,200 MW** from January 2032, which is half the contract. The shares, ratios, per-job and per-year figures are our arithmetic on reported numbers.

## What to watch

- **Fourth quarter of 2026:** Indiana's order on an amendment that would raise Amazon's commitment to 2,800 MW, and federal orders on GenCo's affiliate power contracts.
- **2027:** a 345 kV substation at the Amazon site, which NiSource expects in service next year, and the first phase of the 600 MW battery by 1 December.
- **31 March 2029:** the last date for Amazon's option to cut 1,200 MW.
- **2030:** the target for commercial operation of the first gas unit at Schahfer.

*Read: [the Hyperscalers layer](https://www.sotkn.com/stack/hyperscalers/), [What does Amazon do?](https://www.sotkn.com/stack/hyperscalers/what-does-amazon-do/), [How do hyperscalers buy power?](https://www.sotkn.com/stack/hyperscalers/how-do-hyperscalers-buy-power/), [NiSource signs Microsoft to 1,100 MW of Indiana data center power](https://www.sotkn.com/wire/nisource-microsoft-1100-mw-indiana-data-center-power-wire/) and [Amazon backs 960 MW Indiana nuclear plan](https://www.sotkn.com/wire/amazon-aep-x-energy-960-mw-indiana-nuclear-data-center-power-wire/)*

---

**Get the Wire.** A free brief every day, here and in your inbox. **[Subscribe free →](https://www.sotkn.com/#/portal/signup)**

If this Wire saved you a search, tip Second Order → [sotkn.com/support](https://www.sotkn.com/#/portal/support)

Not investment advice. Do your own research. The data center share of NIPSCO's supply, Amazon's share, the new-capacity ratio, Wheatfield's share, investment per job, GenCo's share of the capital plan and the county's yearly average are our arithmetic on reported figures.

## References

1. [The Times of Northwest Indiana, "Amazon breaks ground on $7 billion data center in Northwest Indiana"](https://nwitimes.com/news/local/article%5F1be3262b-0381-4cea-bef4-a8bef7bb4c3a.html?ref=sotkn.com), 12 Nov 2026\. Groundbreaking, jobs, land sale and the US$33bn Indiana total.
2. [Data Center Digest, "Amazon Breaks Ground on $7 Billion Jasper County, Indiana Data Center"](https://www.datacenterdigest.net/amazon-breaks-ground-on-7-billion-jasper-county-indiana-data-center/?ref=sotkn.com), 14 Nov 2026\. Site size, general contractor and county payments.
3. [NiSource Inc., Form 10-Q for the quarter ended 30 September 2026](https://www.sec.gov/Archives/edgar/data/1111711/000111171126000100/nix-20260930.htm?ref=sotkn.com), 28 Oct 2026\. Plant timing, batteries, bridge capacity, 4,920 MW, capital plan and Amazon's reduction option.
4. [Voltgrid News, "NIPSCO GenCo Gas Plant for Amazon Now Expected in 2030"](https://voltgridnews.com/story/nipsco-genco-gas-plant-for-amazon-now-expected-in-2030?ref=sotkn.com), 31 Oct 2026\. Unit sizes, capacity charge timing and earnings call comments.
5. [DataCenterData, "IURC Cause 46322: NIPSCO special contract for Amazon data centers"](https://datacenterdata.com/insights/policy/a/in-iurc-cause-46322-nipsco-genco-amazon-special-contract/?ref=sotkn.com), read 3 Nov 2026\. Summary of the 17 June 2026 order: 2,400 MW, 3,000 MW new capacity, existing system charge and transmission costs.
6. [NiSource, "Regulatory approvals underscore strength of NiSource's customer-focused data center strategy"](https://www.nisource.com/news/article/regulatory-approvals-underscore-strength-of-nisource-s-customer-focused-data-center-strategy-supporting-growth-in-indiana?ref=sotkn.com), 23 Jun 2026\. Approval of the Amazon contract and generation resources.