Google takes Crusoe's Wyoming site with 702 MW of fuel cells

Google has bought Crusoe's unfinished Wyoming data center site and plans a $17 billion campus powered by 702 MW of Bloom fuel cells and new Black Hills gas plants, so the first money flows to the people who build the power, not to the developer who found the site.

Share
Row of grey Bloom fuel cell power modules beside a glass office building, graded navy with one amber glow; overlay reads 702 MW of fuel cells.
Illustrative: Bloom Energy fuel cell modules, the technology behind the 702 MW plant AEP is building for Google in Wyoming. Photo: Bloom Energy, CC BY 2.0, via Wikimedia Commons.

Google has bought Crusoe's unfinished data center site in southeast Wyoming and plans to spend $17 billion building it out on power it is contracting itself, led by 702 MW of Bloom fuel cells, so the first cash in this project goes to the companies that build generation and wires, while the developer that found the site has stepped aside before a single rack was rented.

What happened?

  • The campus: On 5 November 2026 Google announced its first data center in Wyoming, a long-term $17 billion investment in Laramie County. Its partners are Tallgrass Energy, Black Hills Energy, American Electric Power (AEP) and Related Digital.
  • The site sale: On 6 November Crusoe said Google had acquired its southeast Wyoming site. Crusoe described the deal as the end of its pre-development work: site selection, government approvals and a hybrid power plan built with Tallgrass. Terms were not disclosed. TechCrunch reported that Google, which Crusoe had tried and failed to sign as a tenant, is taking over the development itself.
  • The main power source: Google says the project is contracted with AEP for a 702 MW fuel cell plant with carbon capture, which it calls the largest planned development of its kind. AEP said on 14 October it plans to invest about $4 billion in the plant under a 20-year power purchase agreement with Google, start construction in 2026 and be fully running by the end of 2028. The fuel cells are made by Bloom Energy.
  • The grid side: Black Hills said its agreements with Google, effective 30 September and running through 2048, cover up to 590 MW of grid-connected service, $1.8 billion of new company-owned gas generation (564 MW nameplate) and management of about 2.1 GW of third-party contracted resources through a private microgrid. Service is planned to start in late 2027 and reach peak load in 2030.

Why does it matter?

The direct signal: the hyperscaler is now its own power developer. Google is not waiting for a landlord to deliver a powered building. It is buying the land, signing the generation and paying for the wires. Black Hills says the agreements are structured so that Google bears all the costs of serving the campus for the life of the project, and Google says it will pay for 100% of the power it uses. In plain terms, this is a campus where the tenant writes the power plant's cheque.

The second-order signal: money moves to the power builders first. Look at when each party gets paid. AEP's return depends on a 20-year contract for a plant that is meant to start construction this year. Black Hills says it starts earning a return on its generation spend when construction begins in 2027, and that the project should add about $150 million of net income in 2030. Google has already given Black Hills $399 million of refundable advances to buy long lead-time equipment, which Black Hills expects to pay back by 30 June 2027. That is real money for turbines, engines and electrical gear, moving more than a year before the first megawatt of service.

The developer's lesson. Crusoe says it has more than 6 GW contracted and over 40 GW in its pipeline, and it is still building Google's campus in Armstrong County near Amarillo, Texas. But in Wyoming its role ended at the paperwork stage. TechCrunch reported that Google had raised concerns about the project's cost and timeline under Crusoe's management. Neither company has confirmed that. What is confirmed is the shape of the outcome: the value the developer created was the site, the approvals and the power plan, and it was realised as a sale, not as years of rent.

The pattern. This matches what we have seen across the AI data center layer this autumn. The scarce input is not the building. It is firm power that can be delivered on a date. Our power purchase agreement explainer covers how those contracts work; Wyoming is the version where the buyer also owns the campus that uses the power.

What does it change?

Near term (now to the end of 2027): the order book fills before the campus does. Fuel cells for AEP's plant, gas turbines and engines for Black Hills, and substation and line work for new transmission all have to be ordered and built first. Black Hills has asked Wyoming regulators to approve about $686 million of transmission projects for its large-load customers, including the $606 million Aeolus line filed on 2 November, two 230 kV lines of about 125 miles due for completion by mid-2029, and the $80 million South Cheyenne project, in service in phases from late 2027 through 2028.

Longer term (2028 to 2030): the test is delivery. AEP's plant is due to be fully running by the end of 2028, Black Hills' service ramps to peak load in 2030, and the carbon capture part is still a plan. Google says it will capture and store a large majority of the fuel cell plant's emissions at Tallgrass's Eastern Wyoming Sequestration Hub, but it has not published a capture rate. It is also only studying whether Tallgrass's combined-cycle turbines can be fitted with capture.

What the numbers do not tell us. The megawatt figures cannot simply be added. Black Hills counts a 2.7 GW resource mix including reserve margins, of which about 2.1 GW is third-party contracted resources it will manage. Neither company says whether AEP's 702 MW sits inside that 2.1 GW, so we treat the total power behind the campus as unknown rather than as a sum.

Our arithmetic on cost per megawatt. AEP's roughly $4 billion for 702 MW works out to about $5.7 million per megawatt of fuel cell capacity. Black Hills' $1.8 billion for 564 MW of gas generation works out to about $3.2 million per megawatt. These are generation costs only, before carbon capture equipment and before the data center itself, and the two plants do different jobs.

Metric Value Source name Date
Google campus investment $17 billion, Laramie County, Wyoming Google 5 Nov 2026
Site sale Crusoe site acquired by Google; terms not disclosed Crusoe 6 Nov 2026
Fuel cell plant 702 MW, about $4 billion, 20-year PPA, fully running by end-2028 AEP 14 Oct 2026
Grid-connected service Up to 590 MW; 564 MW of new gas for $1.8 billion Black Hills 6 Oct 2026
Resource mix 2.7 GW including reserves; about 2.1 GW third-party Black Hills 6 Oct 2026
Equipment advances from Google $399 million, refundable by 30 June 2027 Black Hills 6 Oct 2026
New transmission requested About $686 million, incl. $606 million Aeolus line Black Hills 4 Nov 2026
Cost per MW, fuel cells vs gas About $5.7 million vs $3.2 million (our arithmetic) AEP, Black Hills Nov 2026

What should we watch next?

  • 9 November 2026: the Wyoming Industrial Siting Council opens its contested case hearing on the permit for Black Hills' Cheyenne Prairie Generating Station expansion, the gas plant that backs the grid side of Google's campus, with a possible continuation on 10 November. A hearing is not an approval; a permit decision is the next confirmable step.
  • First quarter of 2027: Black Hills expects Wyoming's utility regulator to decide on its proposed large-load transmission cost mechanism, the rule that decides how new wires for data centers are paid for.
  • 30 June 2027: the date by which Black Hills expects to repay Google's $399 million of equipment advances, a marker that the generation build is financed and moving.
  • End of 2028: AEP's target for the 702 MW fuel cell plant to be fully running. A slip here, or a carbon capture design that changes the cost, would weaken the catalyst.
  • What would weaken it: a denied or delayed siting permit, a change in the AEP or Black Hills timelines, or Google cutting the size of the campus.

Also on the tape

  • 6 Nov: TeraWulf reported third-quarter revenue of $76.2 million, of which $63.0 million was data center lease revenue, and said contracted power at its Muskie campus in Kentucky has doubled to 1 GW, subject to state approval (TeraWulf).
  • 6 Nov: Equinix opened SG6, its sixth Singapore data center, with 8 MW in its first phase on an initial investment of about $290 million and up to 20 MW at full build-out (Equinix).
  • 4 Nov: Pure DC agreed a $780 million platform growth facility with a $1.1 billion accordion, a framework of about $1.9 billion to fund data centers across Europe and the Middle East (Pure DC).

FAQ

Who is building Google's Wyoming data center now?
Google is taking on the development itself, with Tallgrass Energy, Black Hills Energy, AEP and Related Digital as partners. Crusoe says its pre-development work is complete and the site has been sold to Google.

Where does the power come from?
From several sources at once: a 702 MW fuel cell plant owned mostly by AEP and built with Bloom Energy fuel cells, new Black Hills gas generation, third-party resources managed through a private microgrid, and gas generators run by Tallgrass and Black Hills. The fuel cells run on natural gas, with carbon capture planned.

Does this mean Crusoe lost money?
We do not know. The sale price was not disclosed. Crusoe frames the deal as completing its role, and it is still developing a separate Google campus in Texas.

When does the campus start drawing power?
Black Hills plans to begin energy service in late 2027 and reach the project's peak load in 2030. AEP expects its fuel cell plant to be fully running by the end of 2028.

One-line takeaway: In Wyoming the hyperscaler bought the site and signed the power plants itself, so the first cash goes to fuel cell, gas and transmission builders, and the clock to watch is the 9 November siting hearing and the 2027 to 2028 power dates.

References

  1. Google, Investing in Wyoming's infrastructure, energy and workforce, 5 Nov 2026.
  2. Crusoe, Crusoe announces Wyoming data center campus update, 6 Nov 2026.
  3. American Electric Power, AEP advances innovative energy solution for Google with 702MW of Bloom fuel cells, 14 Oct 2026.
  4. Black Hills Corp., Black Hills executes definitive agreements to serve Google's planned data center in Cheyenne (Form 8-K exhibit 99.1), 6 Oct 2026.
  5. Black Hills Corp., Black Hills reports 2026 third-quarter results (Form 8-K exhibit 99), 4 Nov 2026.
  6. Wyoming Department of Environmental Quality, Notice of errata on the Cheyenne Prairie Generating Station expansion permit hearing, DEQ/ISC 25-05, 13 Oct 2026.
  7. TechCrunch, Crusoe sells troubled Wyoming data center project to Google, 6 Nov 2026.