What Does WhiteFiber Do? The Bill That Stops at the Switch

WhiteFiber sells GPU cloud hours and colocation in halls it owns, and on 3 November 2026 switchgear commissioning had interrupted the bill on the first 20 megawatts at NC-1.

Share
Open switchgear cabinet with amber bus bars in a dark data-hall aisle, beside unlit server racks.

WhiteFiber sells GPU cloud hours and colocation in halls it owns, and on 3 November 2026 the company said switchgear commissioning had interrupted the bill on the first 20 megawatts of its North Carolina campus.

NEOCLOUDS · Figures through the 3 November 2026 company release · Next check: third-quarter results, 10 November 2026

Affects: Neoclouds · United States

In short: WhiteFiber is a neocloud that also keeps the building. June-quarter revenue was $28.839 million, of which cloud was $23.806 million. The long contract is about $865 million of Nscale colocation at NC-1, and on 3 November switchgear had stopped the bill on the first 20 MW hall. Third-quarter figures, due 10 November, are not on this page.

Education only, not a recommendation to buy or sell any security. Figures are from WhiteFiber filings and company releases, dated below. A line marked our arithmetic is one filed number divided by another.

Numbers that matter

Figure Amount Dated What it counts
Revenue $28.839 million Quarter ended 30 June 2026 Cloud $23.806 million, colocation $4.726 million, other $0.307 million
Net loss $14.976 million Same quarter After $6.016 million of interest and a $0.749 million tax benefit
Remaining performance obligations $1,008.041 million 30 June 2026 Colocation $932.895 million, cloud $75.146 million
Contract liabilities $143.1 million 30 June 2026 Prepayments not yet earned
Cash $56.056 million 30 June 2026 Down from $114.441 million at 31 December 2025
Property, plant and equipment, net $651.085 million 30 June 2026 Up from $336.639 million at 31 December 2025
Debt, net carrying amount $305.800 million 30 June 2026 Sum of the four debt lines in the section below
NC-1 IT deployment About 35 MW operational of 40 MW Company release, 3 November 2026 Billing interrupted on the first 20 MW hall
NC-2 and NC-3 $60 million cash Closed 28 October 2026 Two sites. Not live halls

The table is from the Form 10-Q for the quarter ended 30 June 2026, filed 12 August 2026, and from the 3 November 2026 release. The debt row is our arithmetic, shown in full below.

Our arithmetic. Cloud was 82.5% of June-quarter revenue ($23.806 million ÷ $28.839 million). Colocation was 16.4%. Of the $1,008.041 million of remaining performance obligations, colocation was 92.5% and cloud was 7.5%. Revenue was 54.5% above the $18.662 million of the June 2025 quarter. Operational megawatts were 87.5% of the 40 MW contract. The 5 MW still offline were the other 12.5%.

The quarter that has been earned is a cloud business. The obligation in the accounts is a colocation business.

What does it actually do?

WhiteFiber runs two businesses, and the 10-Q keeps them on separate lines.

Cloud services means NVIDIA GPU servers billed as they train and run models. The 10-Q recognises that revenue over time, because the fee moves with the number of GPUs working and clears day by day. A later exhibit adds a Vera Rubin order that had not started.

Colocation means WhiteFiber owns the hall and hosts someone else's machines. The anchor is Nscale at NC-1 in Madison, North Carolina. The service order is about $865 million over 10 years for 40 MW of IT load, including escalators and installation charges. Electricity and some operating costs pass through to Nscale. The 10-Q names Nscale as the sole contracted tenant at that campus. What Nscale does is the tenant's side of the same contract. This page is the owner of the hall.

Bit Digital contributed the business, effective 6 August 2025. At 30 June 2026 a loan from Bit Digital still had $30 million of principal and a $29.306 million net carrying amount. The former parent is a lender.

Montreal's MTL-1 and MTL-3 are 4 MW and 7 MW gross on the September slide. Duke Energy had delivered 54 MW of gross utility power to NC-1, with efforts described toward 99 MW gross by May 2029.

On 28 October 2026 WhiteFiber paid $60 million cash for NC-2 and NC-3, about 55 miles from NC-1. It expects at least 60 MW of initial gross utility capacity, perhaps about 200 MW within seven years if confirmed, and targets first service in late 2027. The letters of intent are non-binding. Iceland, Atlanta and Sydney leases in the 10-Q are GPU capacity, separate from NC-1.

How does it make money?

Three payments show up, on three clocks.

The GPU hour. Direct cloud cost, before depreciation, was $9.963 million against $23.806 million of cloud revenue. Our arithmetic: 41.9% of cloud revenue. Depreciation for the whole company was $6.567 million, and the 10-Q does not split it. General and administrative expense was $14.811 million. The operating loss was $9.255 million.

The hall. Colocation revenue was $4.726 million. On the Nscale agreement the power bill passes through, so the fee that sticks is the colocation charge. The August 10-Q expected billing to start in the third quarter. The September presentation said initial billing had begun. On 3 November the company said switchgear had interrupted service and billing on the first 20 MW hall and pushed full run-rate billing past August.

The prepayment. Contract liabilities were $143.1 million at 30 June 2026, up from $79.6 million at 31 December 2025. That balance is deferred revenue and deposits for services that had not started. Only $0.7 million of June-quarter revenue came from contract liabilities already on the books at the quarter's start. Six-month operating cash flow was $89.1 million, and the filing ties a $63.6 million rise in deferred revenue to that cash, against a six-month net loss of $27.018 million. Customers paid before the work.

Our arithmetic: $17.909 million current plus $125.201 million non-current is $143.110 million, which is 4.96 times June-quarter revenue ($143.110 million ÷ $28.839 million). That multiple is cash collected, not revenue earned.

The September exhibit describes the newer cloud contracts and says the values stay subject to equipment delivery, acceptance and contract terms. Recent cloud total contract value, for wins since May 2026, is above $550 million.

Deployment, as the exhibit names it Contract value Term and timing in the exhibit
Paris, investment-grade technology customer More than $160 million 5 years; service then expected September 2026; customer prepayments and project-level financing
Owned H200 fleet; Modal Labs as end customer About $17 million 2 years; revenue began June 2026; no new GPU purchase
VR200, called the first Vera Rubin deployment About $108 million 3 years; service expected second quarter of 2027
Prime Intellect About $165 million Revenue expected November 2026; figure includes options on later years
A leading AI inference platform About $88 million 5 years; service expected December 2026

An Iceland deployment for an existing customer sits in the same total. About $16 million from a July 2026 win is inside the aggregate and has no row of its own. The only row the exhibit says had already started is the $17 million Modal order, on GPUs the company already owned.

Debt funds the wait. At 30 June 2026:

Instrument Net carrying amount
4.50% convertible notes due 2031, $230 million principal $222.594 million
Short-term debt, third parties $28.436 million
Short-term debt, Bit Digital $29.306 million
Long-term debt, third parties $25.464 million
Sum, our arithmetic $305.800 million

Quarterly interest was $4.578 million to third parties and $1.438 million to related parties, $6.016 million in total. That interest, with depreciation, takes the $9.255 million operating loss to the $14.976 million net loss.

A 15 July 2026 draw of about $26.2 million on a Canadian bank facility sits outside the $305.800 million. The 3 November release says NC-1 project financing is still being documented, with no assurance it closes. Spend on the first deployment is described as substantially complete. The open item is the loan.

What limits it?

Commissioning at NC-1 is the limit with a date on it.

Switchgear is the equipment that joins a hall to power already delivered to the site. The November release does not describe a missing grid interconnection. It says switchgear commissioning stopped service and billing on the first 20 MW hall and delayed full contracted billing past August. About 35 MW of 40 MW was operational. The last 5 MW was not. The release uses "operational" and "billing" for different facts. It does not say what share of the 35 MW was invoicing on 3 November. Until it does, $865 million is a contract value, not a run-rate.

The cloud headlines are a second book. Cloud remaining performance obligations were $75.146 million at 30 June. New orders through 12 August were $635.8 million over six months to three years. The September cloud total is above $550 million and still subject to acceptance. The three figures use different rules, they overlap, and the company has not published a bridge. Adding them would count the same work twice.

One customer was about 63% of revenue in the six months ended 30 June 2026. The filing does not name that customer. Three orders ended in the same window, including the original 2023 GPU customer, with what the company calls an approximately $5.1 million revenue impact. Seven customers were live as of the 10-Q. The September presentation, as of 31 August, counts more than 20 customers once agreements that are signed and not yet billing are included, and more than 7,500 GPUs contracted. A name that is not billing is outside the 63%.

Cash was $56.056 million on 30 June. The 28 October purchase was $60 million cash. No cash balance between those dates is in the documents read here. The scheduled check is the 10 November 2026 report.

The documents read here do not say whether the September and November start dates in that table were met. Cluster acceptance is what turns a contract value into a bill. A prepayment, a form of purchase commitment, moves the cash and leaves that step in place.

Who else does this?

Compare the clock, not a league table.

Company What it sells The clock on this page
WhiteFiber GPU hours, and colocation in its own halls Hours accrue daily. The NC-1 bill stopped at switchgear
CoreWeave Contracted AI compute at large scale Debt against the fleet, power as the growth clock
Nscale Neocloud capacity, and the NC-1 tenant Customer on this contract, not a second WhiteFiber
Runpod GPU time by the second The bill starts when a developer starts a machine

Most of WhiteFiber's signed balance is a hall lease, and Nscale is the tenant. The 7 November Wire note covers Bloomberg and CNBC reporting that Microsoft is narrowing suppliers, including Nscale. That is about Nscale's customer, not a WhiteFiber invoice. The market door is the United States.

What would change this view?

The picture is a GPU-hour business that is earning, a larger colocation contract that is not fully billing, and a wait funded by prepayments and debt. The 10 November 2026 results are the test.

It weakens if the 20 MW hall is still dark, the last 5 MW is still offline, cash after the $60 million purchase is thin, the NC-1 loan does not close, or the 63% customer leaves. It strengthens if NC-1 is on full contracted billing, cash covered the purchase, and cloud obligations now include contracts the June accounts left out. A binding tenant at NC-2 or NC-3 would change those sites. A letter of intent would leave them as land. This page is not a view on the share price.

Practical takeaways

  • June 2026 hours were 82.5% of revenue. Halls were 92.5% of remaining performance obligations.
  • The stuck step is switchgear at NC-1: about 35 MW of 40 MW operational on 3 November, and the first 20 MW hall's bill interrupted.
  • Contract liabilities of $143.1 million at 30 June are cash that is not yet revenue. Six-month operating cash flow was positive in a loss-making half.
  • Above $550 million, $635.8 million and $1,008.041 million are three different counts. Do not add them.
  • 10 November 2026 is the scheduled third-quarter report: billing, cash after the $60 million purchase, and whether the newer cloud contracts have started.

FAQ

What does WhiteFiber do?

WhiteFiber sells GPU cloud hours and colocation in data centres it owns. In the quarter ended 30 June 2026, cloud services were $23.806 million of $28.839 million of revenue. Nscale's colocation contract at NC-1 is about $865 million over 10 years for 40 MW.

How does WhiteFiber make money?

Cloud customers pay as the GPUs run. Nscale pays for the hall, with electricity passed through. Contract liabilities, the prepayments not yet earned, were $143.1 million at 30 June 2026. The quarter's net loss was $14.976 million.

Why did billing stop at NC-1?

On 3 November 2026 WhiteFiber said switchgear commissioning interrupted service and billing on the first 20 MW hall and delayed full run-rate billing past August. About 35 MW of the 40 MW contract was operational, and 5 MW was not. The release did not say how much of the 35 MW was billing.

Is the new cloud contract value already in the accounts?

The September 2026 presentation puts recent cloud contract value above $550 million, still subject to delivery and acceptance. Cloud remaining performance obligations at 30 June 2026 were $75.146 million of a $1,008.041 million total. The company has not bridged those figures, and they should not be added.

When is the next set of WhiteFiber figures?

WhiteFiber said third-quarter 2026 results will be reported on 10 November 2026. They were not available for this page. The checks are NC-1 billing, cash after the $60 million purchase, and whether the newer cloud contracts have started to be earned.

Keep reading on the map

How we check this

Figures come from the 30 June 2026 Form 10-Q, filed 12 August 2026, the 14 September 2026 investor presentation, and the 3 November 2026 NC-1 update. A later document that changes an earlier expectation is dated in the same sentence. Microsoft and Nscale reporting is labelled reported and is not a WhiteFiber revenue figure. Our arithmetic uses the two filed inputs named in the sentence. Third-quarter results were not out. The company set that report for 10 November 2026.

Last reviewed: 9 November 2026. Next review: the third-quarter 2026 results.

Spot an error and we will correct it and note the change here. Editorial standards. Author page.

Sources

  1. WhiteFiber, Inc., Form 10-Q for the quarter ended 30 June 2026, filed 12 August 2026, SEC EDGAR. Revenue, loss, debt, obligations, the Nscale agreement, concentration, and the July bank draw.
  2. WhiteFiber, Inc., Form 8-K filed 3 November 2026, SEC EDGAR. NC-2 and NC-3 closed 28 October 2026 for $60 million cash.
  3. WhiteFiber, Inc., Exhibit 99.1, 3 November 2026, SEC EDGAR. Switchgear stop on the first 20 MW hall, 35 MW of 40 MW operational, financing not assured, results on 10 November.
  4. WhiteFiber, Inc., September 2026 investor presentation, filed 14 September 2026, SEC EDGAR. Cloud contract values above $550 million, still subject to delivery and acceptance, plus the Duke Energy note and the 31 August customer count.