AirTrunk's $11B Andhra Pradesh plan: 1.8 GW waits on power
AirTrunk has signed an MoU with Andhra Pradesh for two campuses of up to 1.8 GW and about $11 billion near Visakhapatnam, but with the state asking campuses above 300 MW to run on at least 51% green power, electricity, not tenants, is the first step to win.
AirTrunk has signed an agreement with Andhra Pradesh for two campuses of up to 1.8 GW and about $11 billion near Visakhapatnam, and because the state's route for data centres this size lets an operator source its own power only if at least 51% of it is green, the first thing this plan has to win is electricity, not tenants.
What happened?
- The agreement. On 13 November 2026, on day two of the 31st CII Partnership Summit in Visakhapatnam, AirTrunk India and JCK Infra signed a memorandum of understanding with the state IT department, in front of Chief Minister N. Chandrababu Naidu. The state listed it as data centre campuses and telecom infrastructure of 1,400 MW, with a proposed investment of ₹1,03,018 crore and 3,120 jobs.
- The two sites. In a release dated 16 November, AirTrunk, whose major investor is Blackstone, said the agreement covers two proposed campuses in Anakapalli district: 400 MW at Rambilli and 1,400 MW at Tootipala. It said the projects could create more than 3,100 direct operational jobs and 4,700 indirect jobs.
- The filing. Bloomberg reported on 14 November that AirTrunk had submitted a detailed project report for the two campuses, with combined capacity of as much as 1.8 GW and about ₹1.03 lakh crore, or $11 billion, of investment. The proposal remains under consideration by state authorities.
- The size of it. AirTrunk's agreement was about 73% of the ₹1,41,585 crore signed across 12 agreements that day, according to Moneycontrol.
Why does it matter?
The direct signal: India is becoming a gigawatt market for AirTrunk. AirTrunk entered India in April 2026 by buying Lumina CloudInfra, which brought about 600 MW of planned capacity in Mumbai, Chennai and Hyderabad. After that deal it said it had more than 3 GW of operating and planned capacity across 20 campuses. The Andhra Pradesh proposal alone would be about 1.8 GW, or roughly 60% of that total again (our arithmetic), in one district.
The second-order signal: the state wants big campuses to bring their own power. In April 2026 the state decided to give Google, through its subsidiary Raiden Infotech, a deemed distribution licence for its $15 billion, 1 GW AI hub at three Visakhapatnam-area sites. That lets Google buy power directly from generators anywhere in India and build its own lines, paying standard transmission charges when it uses the state grid. The state's special chief secretary for energy told The Hindu that the policy is meant for new mega data centres above 300 MW, with at least 51% of their power from green sources. Both AirTrunk campuses are above that size. Whether AirTrunk takes the same route is not stated in the release, but the release does say AirTrunk will explore renewable energy generated in the state to help power the campuses.
One site name appears twice. Before it got its licence, Google had asked the local distribution company, APEPDCL, for a combined 540 MW connection across Tarluvada, Adavivaram and Rambilli. Rambilli is also where AirTrunk proposes its 400 MW campus. Two hyperscale builders now plan load in the same part of Anakapalli district.
Historical pattern. In Australia, AirTrunk's Kurri Kurri plan is waiting on new wind for its power, as covered in our Australia Markets Pulse. In Malaysia, the grid now charges for power that is booked and not used, as in our Malaysia Markets Pulse. Across Asia Pacific the same sequence repeats: land and capital come quickly, and the power supply sets the date.
Who gets paid while it waits. The first spending is on power: renewable developers selling into the state, and the companies that build high-tension lines. The state energy minister told The Hindu in April that Andhra Pradesh is pursuing, with the central government, a ₹22,000 crore green energy project of dedicated high-tension lines linking its renewable hubs to large users such as Google. On the same day as AirTrunk, GreenGen Renewable Energy signed for ₹8,000 crore and Indian Oil for ₹6,600 crore of renewable energy investment in the state. AirTrunk's own rent, and its tenants' compute, wait for approval and for powered halls.
What does it change?
Near term (to mid-2027): very little is fixed. An MoU and a project report are not a final investment decision, and AirTrunk has given no construction start, phasing or opening date. The two public numbers do not yet agree: the state's list says 1,400 MW, while AirTrunk's release and Bloomberg say up to 1.8 GW. The 1,400 MW figure matches the Tootipala campus alone, so one possibility is that the state counted one site, but no party has said so. Until that is cleared up, there is no fair cost per megawatt. For scale only, ₹1,03,018 crore over 1,800 MW is about ₹57 crore per MW, and over 1,400 MW about ₹74 crore per MW (our arithmetic).
For the AI Data Centers layer: the Visakhapatnam coast is turning into a cluster. Google's 1 GW hub and AirTrunk's proposed 1.8 GW add up to about 2.8 GW of proposed load in one region (our arithmetic), before Panchshil Realty's separate Anakapalli proposal. Our AI Data Centers layer tracks the landlords and hosts in this race; AirTrunk is one of the few Asia Pacific platforms now adding gigawatt sites in more than one country at once.
Longer term: water looks less binding than power. Naidu said on 13 November that the proposed data centres would need about 3.5 TMC ft of water while the state can supply up to 100 TMC ft to Visakhapatnam, mostly through the Polavaram project, and AirTrunk says it will use air cooling and industrial water from the Polavaram–Yeleru allocation rather than town supplies. The harder question is how many gigawatts of round-the-clock power, at least half of it green, can be contracted and carried to one district on a builder's timetable.
| Metric | Value | Source name | Date |
|---|---|---|---|
| Proposed campuses | 400 MW Rambilli and 1,400 MW Tootipala, Anakapalli district | AirTrunk | 16 Nov 2026 |
| Capacity in the state's list | 1,400 MW, data centre campuses and telecom infrastructure | Moneycontrol; Deccan Chronicle | 13 Nov 2026 |
| Proposed investment | ₹1,03,018 crore (about $11 billion) | Moneycontrol; Bloomberg via BusinessLine | 13–14 Nov 2026 |
| Share of the day's signings | About 73% of ₹1,41,585 crore across 12 agreements | Moneycontrol | 13 Nov 2026 |
| Jobs | 3,120 (state); more than 3,100 direct and 4,700 indirect (AirTrunk) | Moneycontrol; AirTrunk | 13 and 16 Nov 2026 |
| AirTrunk platform after Lumina | More than 3 GW operating and planned, 20 campuses | AirTrunk | 20 Apr 2026 |
| Google's Visakhapatnam hub | 1 GW, $15 billion; deemed distribution licence; at least 51% green power | The Hindu | 13 Apr 2026 |
| Water need vs supply | About 3.5 TMC ft needed vs up to 100 TMC ft available to Visakhapatnam | The Hindu | 13 Nov 2026 |
What should we watch next?
- State approval of the project report: whether Andhra Pradesh clears the detailed project report, and which capacity figure, 1,400 MW or 1.8 GW, it approves.
- The power route: whether AirTrunk applies for the same deemed distribution licence Google received, signs renewable supply in the state, or asks APEPDCL for a grid connection, and for how many megawatts at Rambilli.
- The transmission project: progress on the ₹22,000 crore green transmission corridor the state is pursuing with the central government.
- A first phase and a date: AirTrunk has named no construction start or opening year. A named first phase with a megawatt figure and a date would turn the proposal into a build.
- What would weaken the catalyst: a smaller approved capacity, no power route named within the next year, or the plan staying an MoU. What would strengthen it: a power purchase agreement or licence for Rambilli or Tootipala, and an anchor tenant.
Also on the tape
- 15 Nov: Three Oklahoma state representatives asked the Oklahoma Supreme Court to review the regulator's approval of OG&E's power agreements with Google subsidiary Alliance Site & Grid for three planned data centres (The Oklahoman).
- 13 Nov: Panchshil Realty presented proposals for a data centre in Anakapalli and an IT park in Visakhapatnam worth ₹49,311 crore, separate from AirTrunk's plan (Deccan Chronicle).
- 13 Nov: Commitments from the first two days of the CII Partnership Summit came to about ₹7.26 lakh crore, after Naidu said the state planned to sign 303 MoUs worth ₹9.89 lakh crore at the summit (Moneycontrol).
- 10 Nov: TSMC's board approved about US$40.93 billion of capital appropriations and investments of up to US$500 million each in Anthropic and OpenAI (TSMC).
FAQ
What did AirTrunk sign in Andhra Pradesh?
A memorandum of understanding with the state government, signed on 13 November 2026, for two proposed data centre campuses in Anakapalli district: 400 MW at Rambilli and 1,400 MW at Tootipala, with a proposed investment of ₹1,03,018 crore, about $11 billion.
Is it 1,400 MW or 1.8 GW?
Both numbers are in public. The state's list of agreements says 1,400 MW; AirTrunk's release lists two campuses that add up to 1.8 GW. No party has explained the difference yet, so treat 1.8 GW as the company's proposal and 1,400 MW as the state's figure.
Is the project approved?
No. AirTrunk has submitted a detailed project report, and the proposal is under consideration by state authorities. There is no construction start or opening date yet.
Why is power the stuck step?
The state's energy secretary has said its route for new mega data centres above 300 MW requires at least 51% of their power to come from green sources, and Google's 1 GW hub is getting its own distribution licence to buy that power directly. AirTrunk's campuses are larger than that threshold, so its power route has to be settled before the halls can be built.
Takeaway: AirTrunk has put up to 1.8 GW and about $11 billion on the Visakhapatnam coast, but until it names how it will get that much mostly green power to Anakapalli, it is a plan for power first and data centres second.
References
- AirTrunk, AirTrunk signs MoU for proposed data centre campuses in Andhra Pradesh, 16 Nov 2026.
- Moneycontrol, Andhra Pradesh signs Rs 1.42 lakh crore investment deals; AirTrunk-JCK Infra commits Rs 1.03 lakh crore, 13 Nov 2026.
- The Hindu BusinessLine (Bloomberg), Blackstone's AirTrunk plans to build mega data centres in Andhra Pradesh for over ₹1 lakh crore, 14 Nov 2026.
- Deccan Chronicle, CM Holds Investor Talks as AP Secures ₹1.41 Lakh Crore Commitments, 13 Nov 2026.
- The Hindu, Google to get 'Deemed DISCOM' status, 13 Apr 2026.
- The Hindu, Andhra Pradesh has enough water, power to meet needs of data centres, says Naidu, 13 Nov 2026.
- AirTrunk, AirTrunk Acquires Lumina CloudInfra, 20 Apr 2026.
- The Oklahoman, Lawmakers fight regulatory approval of Google data center power plan, 15 Nov 2026.
- TSMC, TSMC Board of Directors Meeting Resolutions, 10 Nov 2026.