Digital Realty's $10B Japan plan: 193 MW to 700 MW

Digital Realty plans to spend another $10 billion in Japan over ten years to grow from 193 MW to about 700 MW, but since 1 October Tokyo's grid cancels large power applications not paid for within three months, so the grid connection, not the money, sets the pace.

Share
Steel high-voltage transmission tower and power lines at dusk over flat farmland in Ibaraki, Japan, graded navy, the tower and lines lit amber; overlay reads 193 to 700 MW.
Illustrative image: a 275 kV transmission tower in Ibaraki, Japan. Photo by Σ64 via Wikimedia Commons, CC BY 3.0 (cropped, colour-graded, text added).

Digital Realty plans to spend another $10 billion in Japan over ten years to take its capacity there from 193 MW to about 700 MW, and because Japan's grid operators now cancel large power applications that are not paid for on time, the pace of that build will be set less by the money than by how fast each new hall can get a funded grid connection in Tokyo and Osaka.

What happened?

  • The plan. On 15 November 2026, Nikkei Asia published an interview with Digital Realty chief executive Andy Power, conducted in October. He said the company will spend $10 billion in Japan over the next decade, working with Mitsubishi Corp., its joint venture partner, and aiming to nearly quadruple its scale in the country. Japan is its top investment destination in Asia.
  • The numbers. Digital Realty has 193 MW of data center capacity in Japan, mostly around Tokyo and Osaka. The extra $10 billion would take that to around 700 MW. It has invested $4 billion in Japan so far, including projects still in development. Globally it has around 3,000 MW and plans to add another 9,000 MW.
  • The customers. Its Japanese customer base is approaching 100 companies, including Amazon Web Services and Microsoft, financial institutions and autonomous driving developers. Power said Japan will prioritise facilities for inference, the work of answering queries with trained AI models, and that the company will soon start doing business with a Japanese AI model developer.
  • The nearest hall. On 7 October 2026 Digital Realty said MC Digital Realty had started building KIX15, a 24 MW data center at its KIX campus in Ibaraki City, Osaka Prefecture, due to start operating in the fourth quarter of 2028. On completion the joint venture will have 10 data centers in Japan with about 220 MW of IT capacity.

Why does it matter?

The direct signal: Japan is where a large landlord is adding AI-era capacity outside the US. Nikkei puts Asia Pacific, including Japan, at about 10% of Digital Realty's revenue. Yet in the third quarter, Asia Pacific signed $283.4 million of the $604.4 million of annualised rent on new leases at Digital Realty's share, or about 47% (our arithmetic), across 79.7 MW, more than the Americas' 75.6 MW. Money is following signatures that are already there.

The second-order signal: in Tokyo, the grid now charges for holding a place in the queue. TEPCO Power Grid, which runs the Tokyo-area grid, had new supply rules approved on 22 July 2026 that took effect on 1 October. For extra-high-voltage customers, the supply level large data centers connect at, the construction cost contribution for grid work must be paid within three months of supply approval, or the application is cancelled. An application that changes for the customer's own reasons before approval is also cancelled. TEPCO Power Grid said the aim is to stop capacity being reserved and then only partly used. Kansai Transmission and Distribution, which serves Osaka, had the same kind of change approved the same day.

Historical pattern. Grids across Asia Pacific are setting terms for large data center loads one market at a time. Malaysia's charges on booked but unused power, covered in our Malaysia Markets Pulse, target the same problem as Tokyo's rule: capacity reserved on paper and not built. Australia's 30 MW connection standard, in our Catalyst on the ride-through rule, sets technical terms instead. Either way, the grid now decides more of the timetable than it did a year ago.

Who gets paid while it waits. The grid company is paid first. A developer now has to fund the contribution within three months of approval, often years before a tenant pays rent. Digital Realty's own leases show the gap: new leases signed in the third quarter start, on average, 17 months after signing. The builders on halls like KIX15 are paid on the construction schedule, and Mitsubishi, as a 50/50 partner, shares the capital. Digital Realty's rent, and the inference capacity its customers want, waits for the hall to be energised.

What does it change?

Near term (to the end of 2026): nothing in the plan is in a filing yet. Nikkei does not say how the $10 billion splits between Digital Realty and Mitsubishi, which sites are involved, or whether the 700 MW is IT load or utility supply, so there is no fair cost per megawatt to work out. What is fixed is the calendar for each new site in Tokyo: once a grid connection is approved, the money for the grid work has to be in place within three months.

For the AI Data Centers layer: the plan needs about 507 MW more than today's 193 MW, or roughly 51 MW a year over ten years (our arithmetic). KIX15, the only new hall with a date, is 24 MW and takes about two years from groundbreaking to service. Reaching 700 MW means finishing the equivalent of about two KIX15-sized halls a year, every year, for a decade (our arithmetic). Our AI Data Centers layer tracks the landlords racing for the same Tokyo and Osaka grid: Nikkei notes AirTrunk plans to invest as much as $30 billion in Japan over five years, and NTT Data is planning a large AI data center for Anthropic.

Longer term (from April 2027): Japan's energy agency has a second rule under consideration for the start of fiscal 2027. For customers with a final contracted power of 30 MW or more, a supply start postponed by more than a year would trigger a cost settlement, and capacity reserved for a delayed phase would be released, according to working group materials from 10 June 2026 summarised by grid consultancy Grid Work. TEPCO Power Grid's published standard construction periods run to about 120 months where a new substation is needed, and its map for large applications splits areas into five-year and ten-year zones. A ten-year spending plan meets a ten-year grid queue.

Metric Value Source name Date
Planned extra investment in Japan $10 billion over ten years, with Mitsubishi Nikkei Asia 15 Nov 2026
Japan capacity today 193 MW, mostly Tokyo and Osaka Nikkei Asia 15 Nov 2026
Japan capacity target About 700 MW (about 507 MW more, our arithmetic) Nikkei Asia 15 Nov 2026
Invested in Japan so far $4 billion, including projects in development Nikkei Asia 15 Nov 2026
KIX15 24 MW, construction started, operating in Q4 2028 Digital Realty 7 Oct 2026
Joint venture portfolio after KIX15 10 data centers, about 220 MW of IT capacity Digital Realty 7 Oct 2026
Asia Pacific new leases, Q3 $283.4 million annualised rent, 79.7 MW, at Digital Realty's share Digital Realty Q3 2026 results 29 Oct 2026
Lag from signing to lease start, Q3 17 months on average Digital Realty Q3 2026 results 29 Oct 2026
Tokyo grid payment deadline Contribution within 3 months of supply approval, or application cancelled; in force 1 Oct 2026 TEPCO Power Grid 22 Jul 2026

What should we watch next?

  • 17 to 18 November 2026: Digital Realty is listed at Nareit's REITworld annual conference in Atlanta. Listen for whether management repeats the $10 billion and 700 MW figures and names Japanese sites or dates.
  • 7 December 2026: Digital Realty at the Wells Fargo TMT Summit. A split of the $10 billion between Digital Realty and Mitsubishi, or a grid approval for a new Tokyo site, would firm up the plan.
  • The fourth-quarter results (date not yet announced): Asia Pacific leasing and the size of the signed-but-not-started backlog, which was a record $2.5 billion of annualised rent at 100% share at the end of September, will show whether Japan signings keep pace.
  • April 2027: whether Japan adopts the cost settlement for delayed connections of 30 MW or more as proposed.
  • What would weaken the catalyst: no confirmation from Digital Realty itself, a smaller share for Digital Realty once the Mitsubishi split is known, or sites that slip into TEPCO Power Grid's ten-year zones. What would strengthen it: a named site with grid supply approval and a contribution paid.

Also on the tape

  • 13 Nov: Digi Power X said its 15 MW first phase at Columbiana, Alabama, leased to Cerebras for about $402 million over ten years, should open to the tenant on 15 December, with billing from January 2027 (Digi Power X third-quarter release).
  • 13 Nov: Malaysia's Digital Ministry said data centres' actual peak electricity demand was 1,370 MW in August, against 2,346 MW contracted, with 4,272 MW allocated to data centres until 2030 (The Star).
  • 15 Nov: Quantum DC has put its 1,200 MW Tungkillo data centre application in the Adelaide Hills on hold, and South Australia's energy minister said the state will not license data centres until they have almost no impact on the grid (ABC News).

FAQ

How much is Digital Realty investing in Japan?
Its chief executive told Nikkei Asia the company will spend another $10 billion over the next decade with Mitsubishi, on top of $4 billion invested so far, to take capacity from 193 MW to about 700 MW.

Has Digital Realty confirmed the plan in a filing?
Not yet. The figures come from the chief executive's interview with Nikkei Asia. The nearest confirmed project is KIX15, a 24 MW Osaka data center that Digital Realty announced on 7 October 2026, due to operate in the fourth quarter of 2028.

What changed in Japan's grid rules on 1 October 2026?
In the Tokyo area, a large customer must pay the construction cost contribution for grid work within three months of supply approval, or its application is cancelled. TEPCO Power Grid said the rule is meant to stop grid capacity being reserved and left unused.

Why does the grid matter more than the $10 billion?
Because each new hall needs its own grid connection before it can earn rent. In parts of the Tokyo area, a connection that needs a new substation can take about ten years to build.

Takeaway: Digital Realty has put $10 billion behind 700 MW in Japan, but in Tokyo and Osaka the timetable now belongs to the grid, which takes payment within three months and may take years to deliver.

References

  1. Nikkei Asia, Digital Realty Trust to spend $10bn more on Japan data centers: CEO, 15 Nov 2026.
  2. Digital Realty, Digital Realty Commences Construction of KIX15 Data Center, Expanding AI Infrastructure in Japan, 7 Oct 2026.
  3. Digital Realty, Digital Realty Reports Third Quarter 2026 Results, 29 Oct 2026.
  4. TEPCO Power Grid, Approval of the Wheeling Service Provisions (in Japanese), 22 Jul 2026.
  5. Grid Work, Data Center Supply Start Dates and Application Cancellation Rules (Effective October 1, 2026), 29 Sep 2026, updated 5 Oct 2026.
  6. Digital Realty, Investor events: Nareit REITworld 2026 and Wells Fargo 10th Annual TMT Summit, accessed 15 Nov 2026.
  7. Digi Power X Inc., Form 8-K Exhibit 99.1: third quarter 2026 results, 13 Nov 2026.
  8. The Star, 11 data centre projects approved as of October, nine already operational, says Digital Ministry, 13 Nov 2026.
  9. ABC News, Protesters drive home message to data centre company, 15 Nov 2026.