What Does Quake AI Do? The Profit That Leaves the Fleet Out
Quake AI is the cloud inside RUM Group, and the profit its chief executive reads is struck after the fleet's depreciation has been added back.
Quake AI is the cloud inside RUM Group, and the profit its chief executive reads is struck after the fleet's depreciation has been added back.
Numbers that matter
The quarter ended 30 September 2026. Form 10-Q was filed on 12 November 2026. The statements are unaudited. The earnings release is dated 11 November 2026. Where the release prints a figure the 10-Q does not, the sentence below says so.
| Figure | Where it sits | |
|---|---|---|
| Group revenue | $96,577,752 | Income statement, quarter |
| Quake AI, cloud | $68,164,982 | Note 4. One line |
| Rumble | $28,412,770 | Advertising $17,319,209 plus other services $11,093,561 |
| Quake adjusted EBITDA | $22,482,424 | Note 23. The measure the chief executive uses |
| Group adjusted EBITDA | $4,409,851 | Same note. Rumble $(11,130,169), corporate $(6,942,404) |
| Amortization and depreciation | $85,184,021 | Income statement. Added back in adjusted EBITDA |
| Property depreciation | $57,703,995 | Note 9. This quarter |
| Intangible amortization | $27,706,986 | Note 11. This quarter |
| Loss from operations | $84,640,282 | Income statement |
| Net loss | $89,854,446 | $79,916,367 to RUM Group, $9,938,079 to the minority |
| Northern Data contribution | Revenue $68,164,982. Pre-tax income $68,149,242 | Note 3. Differ by $15,740, our arithmetic |
| Data centers, gross | $791,793,810 | Note 9. Useful life 1 to 20 years |
| Advances and construction | $138,481,659 | Note 9. Not depreciated |
| Cash | $134,428,984 | Balance sheet. The MD&A rounds this to $134.4 million |
| Bitcoin at 30 September | 94.68 coins, fair value $7,911,739 | Note 8. Sold on 14 October for $7,755,736 |
| Note held by Tether | €317,533,401 principal. Carrying amount $358,837,827 | Note 14. Due 18 June 2031 |
On our arithmetic, $68,164,982 is 70.6 percent of $96,577,752. The release says Quake contributed more than 70 percent of revenue. The 10-Q prints the dollars. The release prints the phrase.
Nine-month cloud revenue is $78,257,575. Subtracting the quarter leaves $10,092,593, our arithmetic. Note 3 runs the nine-month Northern Data figures from 17 June 2026, so that difference is the stub through 30 June, not an earlier full quarter.
What does it actually do?
RUM Group, the listed company, formerly Rumble, has had two segments only since this quarter. Note 23 recasts the prior year, which was one segment.
Rumble is the video platform. Its policy note also puts cloud computing on spare Rumble servers inside other services, which are $11,093,561. No cloud dollar is broken out of that line.
Quake AI is the cloud the company owns, delivers and manages. Note 23 says the revenue is primarily GPU computing, sold as reserved capacity (a dedicated block, straight-line, invoiced monthly, paid in 10 to 20 days) or on-demand (billed on use). The same paragraph puts data-center hosting and colocation in that revenue. The MD&A overview adds blockchain infrastructure services. Note 4 then prints one Quake number, cloud of $68,164,982. The filing gives those pieces no separate dollars.
The business arrived by purchase. On 17 June 2026 RUM acquired about 85 percent of Northern Data. The release prints the starting stake as 85.2 percent. On 30 September RUM bought a further 8,256,155 shares from Tether and reached about 98 percent. Consideration was stock, pre-funded warrants and a euro note. Cash acquired was $51,036,334. The cash-flow line, net of that cash, is an inflow of $51,036,335. One dollar sits between the two prints. Non-cash consideration was $1,515,556,856. Property and equipment acquired was $887,260,497. Purchase accounting can still move until 17 June 2027.
At 30 September the data-center class, gross, is $791,793,810, useful life 1 to 20 years. Advances and assets under construction are $138,481,659, and that class is not depreciated. The filing does not say how much of the data-center class is GPUs, buildings or power gear, and it does not call the advances the Maysville site.
The release, and only the release, says the existing fleet is about 22,000 Nvidia GPUs and that utilization was about 85 percent for the quarter. The 10-Q does not print either figure. Utilization is a fullness reading. It is not a split of the $68,164,982.
How does it make money?
Customers pay the cloud bill. Reserved capacity bills every month of the term, whether the block is full. On-demand bills the hours that ran. Hosting and colocation bill with them, on the same line. The company is paid when it invoices. That is the neocloud shape in what a neocloud is, and the two clocks in reserved and on-demand GPUs. Here the filing stops before the split.
Beside that bill, Rumble sells attention. Advertising was $17,319,209, against $11,730,859 a year earlier. The MD&A puts the Rumble revenue change at $3.6 million: advertising up $5.6 million, other services down $2.0 million. That is the video clock.
The profit the chief executive reads is adjusted EBITDA. Note 23 says he is the chief operating decision maker, that he allocates on adjusted EBITDA, and that he does not evaluate the segments with asset information. The reconciliation builds that profit by adding amortization and depreciation, share-based pay, transaction costs, interest, other items and three fair-value lines back onto the loss before tax.
Quake's adjusted EBITDA is $22,482,424. The expenses inside that figure are cost of services $30,032,850, general and administrative $13,118,055, research and development $1,563,741, and sales and marketing $967,912. They sum to $45,682,558. Subtracted from $68,164,982 they leave $22,482,424. Our arithmetic matches the printed total. Those four lines are the costs that remain after depreciation and share-based pay have been left out. Nine-month Quake adjusted EBITDA is $24,712,205, so $2,229,781 of it, our arithmetic, sits in the 17 June to 30 June stub.
Group adjusted EBITDA is $4,409,851, which is Quake's $22,482,424 plus Rumble's loss of $11,130,169 plus a corporate loss of $6,942,404. The income statement then records amortization and depreciation of $85,184,021. Note 23 subtracts that same figure from adjusted EBITDA on the way to the loss before income taxes of $90,854,505. We footed the bridge, including share-based pay of $6,358,687 and the interest, fair-value and transaction lines. It lands on $90,854,505. The operating loss is $84,640,282. The net loss is $89,854,446.
Note 9's property depreciation is $57,703,995. Note 11's intangible amortization is $27,706,986. Together they are $85,410,981, or $226,960 above the income-statement line. The filing does not name that gap. A year earlier the income-statement line was $3,880,492, so the increase is $81,303,529, our arithmetic, and it is $13,138,547 larger than the cloud bill. The filing does not assign the increase to Quake. Property depreciation alone is $10,460,987 under the cloud bill. Those comparisons are ours.
Note 3 is a third clock. Northern Data's contributed pre-tax income is $68,149,242 on contributed revenue of $68,164,982. Since 17 June the contributed pre-tax income is $80,118,178, which is $1,860,603 above contributed revenue of $78,257,575, our arithmetic. The note lists no expenses inside either contribution, and it does not foot $68,149,242 to Quake's adjusted EBITDA or to the $85,184,021. The consolidated loss before tax stays $90,854,505. We leave that loss whole.
GAAP cost of services is $57,186,000. The segment table's combined cost of services is $56,072,579, a gap of $1,113,421 against share-based pay in that line of $1,113,422. One dollar is unnamed. The MD&A rounds the rise to $32.0 million, from a base of $25,219,331, and attributes $30.0 million of it to Quake data-center costs. The exact rise is $31,966,669. That $30.0 million and Quake's segment cost of $30,032,850 are left as two prints.
Customers paid the invoices. Tether was paid at the June close, in shares, warrants and the note: principal €317,533,401, due 18 June 2031, EURIBOR plus 3.0 percent, host effective rate about 5.92 percent, carrying amount $358,837,827. Tether may exchange it, up to five business days before 18 June 2027, at the greater of a 10-day average and $7.88. The filing estimates 45,756,240 shares. Creator minimums of about $28.0 million over 12 to 36 months are the video commitment.
What limits it?
- One cloud dollar covers reserved GPU time, on-demand GPU time, hosting, colocation and the blockchain phrase. The hour has no line of its own.
- The profit used to judge Quake adds depreciation back. Note 23 says depreciation is allocated. The printed segment table has no depreciation row, and the chief executive does not use asset information.
- Data-center life is 1 to 20 years. GPU depreciation elsewhere is often a stated five or six years. This filing does not isolate the GPU, so that life has no denominator here.
- Advances and construction of $138,481,659 are outside both depreciation and the $68,164,982. The filing does not name the site.
- Maysville, Georgia, is under development for an unnamed U.S. cloud customer. Pre-funded warrants for up to 50,808,408 shares vest with purchases, half on the current agreement and half on a later one. None had vested, so none of that fair value has reduced revenue. The risk factors say the build needs capital that may not be available on acceptable terms. The note prints no price and no megawatts.
- The release says part of a previously disclosed 250 megawatts, aimed at 2027, may slip past 2027. The 10-Q does not print 250 megawatts. That sentence, Maysville, and the $138,481,659 are separate.
- Purchase accounting is provisional through 17 June 2027. Goodwill from the deal is $411,503,140. Goodwill at 30 September is $413,780,068 after a currency move of $8,378,463, which is 20.7 percent of assets of $2,000,152,319, our arithmetic.
- There is no quarterly cash-flow statement. Nine-month operating cash used was $113,828,760 on the statement and $113,828,759 in the MD&A. Equipment purchases were $75,545,353 over those nine months. Both stay on the nine-month clock.
- The release's fourth-quarter outlook is group revenue of $88 million to $94 million. The top is $2,577,752 below this quarter, and the bottom is $8,577,752 below, our arithmetic. It has no segment.
Cash on the balance sheet is $134,428,984. Adding the bitcoin fair value gives $142,340,723, which is the release's $142.3 million of liquidity at 30 September. Note 24 records the sale of those coins on 14 October for $7,755,736, $156,003 under the quarter-end fair value, our arithmetic. Other digital assets, fair value $3,179,400, sit outside that liquidity line on purpose. The Tether note runs to 2031. The capital the risk factors flag is for halls still to be built, and the 10-Q does not price it.
Who else does this?
The job matches the other neoclouds on this folder: hold accelerators, place them, and bill the hour. What changes is the split the filing is willing to print.
| Company | What the latest filing separates | Where Quake's quarter is different |
|---|---|---|
| CoreWeave | Committed contracts and on-demand time | Quake prints one cloud line for reserved, on-demand, hosting and colocation |
| Nebius | An AI-cloud revenue that is almost the whole group | Quake is 70.6 percent of RUM on our arithmetic, and the rest is video |
| Cerebras | A cloud hour and a hardware shipment | Quake has no hardware revenue line in this quarter |
Quake's note says the company owns, delivers and manages the cloud. That is the renter's side. Maysville is a customer agreement at a site still being built, and it is outside this quarter's bill.
What would change this view?
- A split of the $68,164,982 among reserved GPU time, on-demand time, hosting and colocation.
- Quake's share of the $85,184,021 of depreciation, so the fleet is inside the profit the chief executive reads.
- A GPU life inside the 1-to-20-year data-center class.
- Maysville revenue, which would also start the warrant charge, plus a price and a megawatt on that agreement.
- A filing that dates the release's 250 megawatts, either still in 2027 or moved.
- A quarterly cash-flow statement, and a final purchase allocation. The measurement window runs to 17 June 2027.
Practical takeaways
- Use $68,164,982 as the cloud bill. Keep the release's "more than 70 percent" beside the 70.6 percent, and do not turn either into a GPU-hour share.
- Read Quake's $22,482,424 as adjusted EBITDA. The bridge puts $85,184,021 of depreciation back below it. The GAAP result is the loss.
- Keep Note 3's contributed pre-tax income of $68,149,242 away from both of those. The note does not foot it to them.
- Treat 22,000 GPUs, 85 percent utilization and the 250 megawatts as release sentences. They are not in the 10-Q.
- Date the bitcoin. It is in the 30 September liquidity figure. It was sold on 14 October.
- Treat the fourth-quarter range of $88 million to $94 million as a group outlook, below this quarter, with no segment.
This is a map of one quarter. It is not investment advice.
FAQ
Is Quake AI a neocloud?
It is RUM Group's cloud segment. Note 23 says it sells reserved and on-demand GPU computing, and that the same revenue includes hosting and colocation. The video platform is the other segment. Northern Data closed on 17 June 2026, so this is the first full quarter.
Is the $68,164,982 the GPU hour?
It is the cloud line. Reserved GPU capacity, on-demand GPU capacity, hosting and colocation are in it, and the overview also names blockchain infrastructure. No share is printed. The release's 85 percent utilization is a separate sentence.
Why is adjusted EBITDA positive when the company lost money?
Adjusted EBITDA adds amortization and depreciation back. Quake's figure is $22,482,424 and the group's is $4,409,851. Depreciation and amortization are $85,184,021. The operating loss is $84,640,282 and the net loss is $89,854,446. Note 23 says the chief executive allocates on the figure that excludes depreciation, and that he does not use asset information.
Is the $142.3 million liquidity still cash and bitcoin?
The release describes liquidity at 30 September: cash it rounds to $134.4 million, and 94.68 bitcoin it values at $7.9 million. The balance sheet prints cash of $134,428,984 and a bitcoin fair value of $7,911,739. Note 24 says those coins were sold on 14 October 2026 for $7,755,736. The sale is after the quarter.
Does this say what to buy?
No. It says who billed the quarter, which profit adds the fleet back, and which figures the filing leaves unsplit. That is not a recommendation.
Keep reading on the map
The mechanism is the hour, and the depreciation of the machine that supplies it. Start with what a neocloud is, then reserved against on-demand, then how a fleet becomes an annual expense. The buyer's door for a U.S. listing is the US markets hub. The peers on this folder are CoreWeave, which separates the committed hour, and Cerebras, which separates the hour from the hardware. This 10-Q has no Wire note.
How we check this
- The 10-Q comes first. Release-only figures are named as the release: about 22,000 GPUs, about 85 percent utilization, the 250 megawatts, the 85.2 percent stake, the fourth-quarter range, and the $142.3 million liquidity phrase.
- Quake's four cost lines were added before $22,482,424 was treated as a remainder, and the group bridge was footed from adjusted EBITDA to the loss before tax.
- Percentages, stubs and gaps are labelled as ours. Contributed pre-tax income, Quake adjusted EBITDA and consolidated depreciation stay three prints. The construction balance, Maysville and the 250 megawatts stay three prints.
- Nine-month cash figures stay on the nine-month clock. The bitcoin sale on 14 October stays after the quarter. Education only, with no recommendation.
Sources
- RUM Group Inc., Form 10-Q for the quarter ended 30 September 2026, filed 12 November 2026 (unaudited). Income statement, Notes 3, 4, 8, 9, 11, 14, 23 and 24, and the MD&A. SEC EDGAR.
- RUM Group Inc., earnings release dated 11 November 2026, Exhibit 99.1. The 22,000 GPUs, about 85 percent utilization, the 250 megawatts, the 85.2 percent stake, liquidity of $142.3 million, and the fourth-quarter revenue range of $88 million to $94 million. Exhibit 99.1.