What Does Cerebras Do? The Lease That Has Not Started
Cerebras sells wafer-scale systems and a dedicated inference hour, and about $8.5 billion of the data-center leases behind the next hour are signed and have not started.
STACK · Neoclouds · Status: Tightening · Last reviewed: 24 Nov 2026
Cerebras sells wafer-scale systems and a dedicated inference hour, and about $8.5 billion of the data-center leases behind the next hour are signed and have not started.
In short. In the quarter ended 30 September 2026, GAAP revenue was $210.809 million. Cloud and other services were $141.928 million, 67.3% on our arithmetic, and hardware was $68.881 million. OpenAI contributed $72.4 million after a $3.2 million warrant reduction. The risk factor prints OpenAI at 34%, MBZUAI at 38%, and G42 at 7%. About $8.5 billion of data-center lease payments are signed and have not commenced. Service credits on the late OpenAI capacity began on 1 October.
A neocloud turns a signed block of compute into a billed hour. Start with who the neoclouds are if the layer is new. Figures are from the unaudited Form 10-Q filed 12 November 2026 and from the earnings release furnished that day. The Form 8-K says the release is not filed for Exchange Act liability. Sums, shares and the megawatt check are ours.
Numbers that matter
| Number | What it is | Why it matters |
|---|---|---|
| $141.928 million | Cloud and other services, quarter ended 30 September 2026, against $38.920 million a year earlier | 67.3% of $210.809 million. The release says 265%. The thousands rise 264.7% |
| $68.881 million | Hardware, same quarter, against $96.794 million a year earlier | Down 28.8% on our arithmetic. Recognised when the system transfers |
| $34.503 million | Cloud gross profit. Hardware gross profit was $7.591 million. Total gross profit $42.094 million | Margins 24.3% and 11.0%. 42,094 / 210,809 is 19.97%. The bridge prints 20.0% |
| $16.360 million | Pass-through revenue, all inside the cloud line, from the furnished bridge | Gross profit left on that slice is $0.488 million, 3.0% on our arithmetic |
| $72.4 million | OpenAI arrangement revenue, net of a $3.2 million warrant reduction | The risk factor prints 34%. $72.4 million is 34.3% of the quarter. Both prints stand |
| $8.5 billion | Undiscounted payments on data-center leases signed and not commenced | Absent from the balance sheet. Commenced leases already show $756.875 million of future payments |
| $26.1 billion | Remaining performance obligations at 30 September | Pass-through is inside this figure only where the data-center lease is already on the books |
| $7.805 billion | Cash $3,074.752 million, restricted cash $444.042 million, investments $4,286.026 million | Our sum. The release rounds it to $7.8 billion. This pile is not the stuck step |
Statement lines are the unaudited 10-Q, in thousands. Pass-through, the margin print and the $7.8 billion rounding are from the furnished release. The $8.5 billion and the $26.1 billion are the filing's approximations.
What does it actually do?
It designs a processor the size of a full silicon wafer, the Wafer-Scale Engine, and sells the system or the hour. The 10-Q says TSMC produces every wafer, with no formal long-term allocation. The hour is GPU-as-a-service on a chip the neocloud designs itself. Hardware is recognised when control transfers, generally on shipment, delivery or acceptance. Dedicated cloud capacity is take-or-pay, the pattern in take-or-pay GPU contracts, recognised over the term whether the hour is full. On-demand is tokens, prepaid bundles, or a training job. The filing does not split the $141.928 million between the two. It does split the clock: $141.691 million over time, and $0.237 million at a point in time. One segment. The chief executive reads net income. Pass-through hall costs sit inside the cloud line, and the company says they are not the core offering. The May 2026 offering brought net proceeds of $6,232.511 million.
How does it make money?
On the hour already being delivered, and on the system already shipped. Interest and dividend income was $81.578 million, against gross profit of $42.094 million. Operating loss was $224.149 million, of which research and development was $177.842 million. Net loss was $161.218 million.
The warrant comes off the bill before gross profit is struck. The quarter's reduction was $36.4 million. The furnished bridge prints $36.424 million, with $19.346 million against cloud and $17.078 million against hardware. OpenAI's piece is $3.2 million. The other $33.2 million, on our arithmetic, is not given a customer name. The warrant asset still to run off is $140.174 million current plus $951.800 million long-term, $1.092 billion on our arithmetic, which the filing rounds to $1.1 billion, through October 2031.
The pass-through bridge removes $16.360 million of cloud revenue and $0.488 million of gross profit. Implied cost is $15.872 million, so about three cents of gross profit stay with Cerebras. Core revenue is $230.873 million and core cloud revenue is $144.914 million. Core operating loss is $33.108 million, core net income is $29.823 million, and core adjusted EBITDA is a loss of $3.314 million. Those add back $155.105 million of stock-based pay and the warrant, and they strip the pass-through. GAAP remains the $161.218 million loss.
OpenAI is the customer and the lender. The December 2025 agreement commits OpenAI to buy 750 MW of inference capacity over three or four years, extendable to five, plus an option on another 1.25 GW, up to 2.0 GW by the end of 2030. The option is not inside the 750 MW, and the warrant tranches on that extra capacity were not treated as probable. In January 2026 OpenAI funded a secured loan. The note prints $1,004.571 million received. No cash has been repaid. Non-cash credits were $175.489 million, 17.5% of principal received. Outstanding principal is $829.082 million, of which $706.518 million is classified current, 85.2% on our arithmetic. The coupon is 6%. A further non-cash interest charge, $18.568 million this quarter, was added to deferred revenue. See prepayment: the customer funded the build, and the payback is the hour.
Amortised instalments start after the final tranche of the initial 250 MW, one third of the 750 MW on our arithmetic. The $706.518 million current portion is the 30 September classification, and the filing does not tie it to that start date. Nine-month operating cash outflow was $388.894 million and equipment purchases were $1,046.059 million.
What limits it?
The lease that has not started. At 30 September, data-center leases commencing in 2026 and 2027 had been signed and had not commenced, so they are off the balance sheet. Undiscounted payments are about $8.5 billion. Leases already commenced show $756.875 million of future payments and a right-of-use asset of $571.237 million. About $8.5 billion is about eleven times those commenced payments. The filing prints neither the megawatts nor a statement that these leases are the OpenAI halls.
The OpenAI shortfall is the same step. As of 30 September, without adjustment for excused delays, Cerebras had delivered less capacity than the agreement contemplates. On its forecasts, delays may continue through a portion of 2027, and data-center schedules are described as highly unpredictable. A shortfall that is not excused, and is still uncured 30 days after a milestone, earns service credits that offset later monthly fees. Credits commenced on 1 October 2026. They are outside the September $72.4 million, and the filing prints no dollar for them. Each day of delay also shortens that tranche's term by a day. If a shortfall is still uncured 90 days after the milestone, either side can terminate the tranche. Cerebras expects the capacity that becomes terminable in 2026 to be less than 5% of the commitment, which is less than 37.5 MW on our arithmetic. The filing does not say a tranche has been terminated.
The $26.1 billion includes pass-through only where the data-center lease is already a right-of-use asset. A significant amount is the OpenAI agreement. Pass-through on the rest of the committed capacity is left out, and the excluded dollar is not printed. About 33% is expected by 30 September 2028, about $8.6 billion on our arithmetic. The filing says rent, maintenance, power and other obligations under long-term data-center agreements may continue even if customer commitments are reduced, deferred or terminated. Lease cost this quarter was $69.018 million, including $31.469 million on leases shorter than a year. That short-term cost is not the $8.5 billion. A further $217.8 million of uncommenced leases was signed in the fourth quarter, before the 12 November filing, and sits in its own row.
The 12 November release says 700 gross megawatts of data-center capacity are secured for delivery by the end of 2027, with further contracts in Norway and Finland. Those sentences are not in the 10-Q. They are not added to the 750 MW, and they are not a reading of the $8.5 billion.
MBZUAI was 38% of the quarter, OpenAI 34%, and G42 7%, together 79% on our arithmetic. The concentration table prints 38% and 34% as Customer A and Customer B, and a year earlier the 70% and 14% lines match MBZUAI and G42. See customer concentration. Receivables are Customer B at 64% and Customer C at 16%. Customer A is under 10% of receivables. United States billing was $130.800 million, 62.0%. Europe, Middle East and Africa was $79.760 million, 37.8%.
We mark the status Tightening. The cloud hour is the larger bill, and it is being recognised. The next halls are signed and have not started, delivery to OpenAI is already short, and credits are accruing with no dollar printed.
Who else does this?
CoreWeave bills a reserved Nvidia hour once the cluster is live. Cerebras bills a wafer it designs, and the hour on that wafer. Runpod bills by the second. Cerebras dedicated capacity bills a term. Corvex is the small shape of this page: leases signed, not commenced, and a bill that waits on acceptance. Corvex's uncommenced payments were about $73.9 million.
The 10-Q says a second-half Oracle agreement is for hardware and a Microsoft agreement is for cloud inference, with milestones before that service starts. The release adds Oracle Cloud Infrastructure in 2027 and an unnamed top-three hyperscaler deal, with no prices, so neither is inside the $141.928 million. Oracle, Microsoft and Amazon are those doors. SoftBank is the equity cheque into OpenAI. Who sells the inference hour is who sells AI inference, and the US door is US markets.
What would change this view?
- Easing. The $8.5 billion leases commence and show up as right-of-use assets, with a megawatt count and a statement of whether they sit under the 750 MW. Service credits are printed in dollars and are small against the cloud bill. A delivered tranche cures the shortfall before any of it is terminated.
- Tightening. Commencement slips further into 2027. A tranche stays uncured for 90 days and is terminated, which would cut remaining performance obligations. The loan is called for cash because the agreement ends for a reason other than OpenAI's uncured breach. MBZUAI, OpenAI or G42 steps back.
- A different model. OpenAI takes systems instead of the cloud hour. The filing says the mix can move with the deployment option. Cerebras would be paid on shipment, and the pass-through inside the cloud line would shrink.
Practical takeaways
Keep the clocks in separate rows. The $141.928 million is the cloud bill already recognised. The $72.4 million is OpenAI for the quarter, and the 1 October credits come off later months. The $8.5 billion has not started. The $217.8 million is a later signature. The $26.1 billion leaves out pass-through where no lease is on the books. The $7.805 billion is the float. The foundry is paid for the wafer. The landlord is paid on the lease, including when the customer is late. The warrant took $36.4 million off this quarter. Cerebras is paid on the hour that has started.
FAQ
What does Cerebras do?
Cerebras designs a wafer-scale processor and sells it as a system the customer runs, or as cloud capacity, dedicated or on demand. Dedicated capacity is billed whether it is fully used. In the quarter ended 30 September 2026, cloud and other services were $141.928 million and hardware was $68.881 million.
How does Cerebras make money?
It recognises hardware when control of the system transfers, and dedicated cloud capacity over the service term. Cloud gross profit was $34.503 million and hardware gross profit was $7.591 million. A $36.4 million warrant amortisation reduced recognised revenue. GAAP net loss was $161.218 million.
How much of the September 2026 quarter was the cloud?
Cloud and other services were $141.928 million, 67.3% of GAAP revenue of $210.809 million, on our arithmetic. Of that line, $141.691 million was recognised over time. The filing does not split dedicated capacity from on-demand.
Why is about $8.5 billion missing from the balance sheet?
Those are undiscounted payments on data-center leases that have been signed and have not commenced, with start dates in 2026 and 2027. A lease goes on the balance sheet at commencement. The filing does not print the megawatts, and it does not say the leases are the OpenAI halls.
What limits Cerebras?
Delivery of the halls. Less OpenAI capacity had been delivered by 30 September than the agreement contemplates, delays may run through a portion of 2027, and service credits began on 1 October with no dollar printed. About $8.5 billion of leases have not started. Cash, restricted cash and investments were $7.805 billion on our arithmetic.
Is this a recommendation to buy or sell Cerebras shares?
No. This page explains how Cerebras makes money and which step is stuck. It gives no buy or sell calls. Not investment advice. Do your own research.
Keep reading on the map
Layer: Neoclouds on The Stack. Also CoreWeave and Corvex. Explained: GPU-as-a-service, take-or-pay GPU contracts, prepayments and customer concentration. Markets: the US door. The 14 November note on the same filing is Cerebras is late on OpenAI's 750 MW, and credits now accrue.
Get the Wire — short daily notes when compute, chips and GPU financing move.
Not investment advice. Do your own research.
How we check this
Quarterly figures are from the unaudited Form 10-Q filed 12 November 2026. Pass-through and the core totals are from the release furnished the same day, which the 8-K says is not filed for Exchange Act liability. Named customer shares are from the risk factors. The 700 megawatt sentence is from the release. The $8.5 billion and the $217.8 million are separate signatures. There is no quarterly cash-flow statement, and no printed dollar for the credits or the excluded pass-through. Sums, percentages and the 37.5 MW check are our arithmetic. Who gets paid, and the stuck step, are our read. The featured image is a generic hall and wafer, not Cerebras hardware.
Last reviewed: 24 Nov 2026. Next review: when Cerebras prints a dollar for the service credits, or when an uncommenced lease commences, and no later than the annual report for 2026.
Spot an error? Tell us and we will correct it and note the change here.
Sources
- Cerebras Systems Inc., Form 10-Q for the quarter ended 30 September 2026, filed 12 November 2026. Revenue, cost, loss, the OpenAI agreement, customer shares, the loan, warrants, leases, remaining performance obligations, and the delivery shortfall.
- Cerebras Systems Inc., Form 8-K, filed 12 November 2026. Item 2.02 furnishes the earnings release and says the exhibit is not filed for Exchange Act liability.
- Cerebras Systems Inc., earnings release, Exhibit 99.1, 12 November 2026. The core bridge, pass-through of $16.360 million, the $7.8 billion rounding, the outlook, and the 700 megawatt sentence.
Writes Second Order by TKN — a plain-English map of AI infrastructure and semiconductors for non-specialist investors. Focus: who gets paid, where money sticks, and which step is stuck.