What Does SoftBank Do? The Advance Before the Lease
SoftBank has $54.6 billion of cost in OpenAI against a $99.6 billion fair value, and it has booked a ¥597,248 million loss on power-equipment advances, while the half-year report prints no lease revenue from the campuses.
STACK · Hyperscalers · Status: The advance · Last reviewed: 20 Nov 2026
SoftBank has $54.6 billion of cost in OpenAI against a $99.6 billion fair value, and it has booked a ¥597,248 million loss on power-equipment advances, while the half-year report prints no lease revenue from the campuses.
In short. SoftBank Group does not sell the hour. For the six months to 30 September 2026 the OpenAI stake was left at the March valuation, so it produced no gain and no loss, and Silver Bands 7 wrote off advances on power equipment that left the plan. The sales the report prints are the telecom segment and Arm. The stuck step is the advance, not the cash.
The campuses sit inside Stargate. The unpaid queue is a purchase commitment. The version that does become a bill is a cloud commitment. A hyperscaler is the buyer that sets the spend. This half, SoftBank is the cheque and the equipment queue.
Numbers that matter
Rows are from the consolidated financial report for the six months ended 30 September 2026, issued in Tokyo on 10 November 2026, unless the row says otherwise. Profit-and-loss dollars use the September quarter's average rate of ¥160.12 per dollar. The rate at 30 September is ¥157.35. The 12 November slide uses its own round dollars.
| Number | What it is | Why it matters |
|---|---|---|
| ¥597,248 million | Loss on the realignment of US power-equipment procurement. Also printed as $3.73 billion. ¥457,030 million ($2.85 billion) is non-refundable advances. ¥140,218 million ($0.88 billion) is contract modifications and settlements | The stuck cash. It sits in the September quarter. The presentation says the loss is unrelated to PORTS-Pike |
| $6.6 billion | Advance balance on the 12 November slide, after $2.9 billion off $9.5 billion paid by Silver Bands 7. $5.6 billion is tagged to the PORTS-Pike power project ($3.4 billion near term, $2.2 billion by the end of 2027). $1.0 billion is expected over time | Still an equipment advance. Not revenue, and not the yen figure on the balance sheet |
| $54.6 billion | OpenAI cost at 30 September. Fair value $99.6 billion. Cumulative gain $45.0 billion, none of it this fiscal year. Carrying amount ¥15,671.5 billion | No OpenAI gain or loss in the half. Cost became $64.6 billion on 1 October. No new fair value is printed |
| ¥1,725,796 million | Investment gain for the half. Intel was ¥1,062,815 million. The Vision Funds were ¥705,617 million, including a $3.6 billion (¥569,386 million) rise in ByteDance | A mark. The September quarter's investment line is a loss of ¥133,586 million |
| ¥1,115,337 million | Net loss to owners for the three months to 30 September. The six-month loss to owners is ¥768,007 million. Loss before tax for the half is ¥438,705 million | On our arithmetic the June quarter was a ¥347,330 million profit to owners. The loss is the equipment quarter |
| ¥7,432,165 million | Cash at 30 September, up ¥2,070,015 million. Banking subsidiaries held ¥512,259 million. Interest-bearing debt was ¥32,591,205 million | Cash is not the bind. September notes that funded the 1 October cheque were still in this cash |
¥457,030 million plus ¥140,218 million is the ¥597,248 million loss, and $3.73 billion at ¥160.12 matches it. The slide cuts the same payments a different way: $2.9 billion, the non-refundable slice rounded from $2.85 billion, comes off $9.5 billion and leaves $6.6 billion. The $0.88 billion of settlements sits outside that bridge, with cash expected from the third quarter. $9.48 billion minus $2.85 billion is $6.63 billion, which the slide rounds to $6.6 billion. A wider balance-sheet bucket, advances for power and AI data center assets, was ¥1,065,097 million, up ¥386,371 million ($2.52 billion). At ¥157.35 that is $6.77 billion. The company does not equate it with the slide.
What does it actually do?
Three jobs, three entities.
The stake is SVF2's OpenAI holding. Cost at 30 September was $2.2 billion from the year to March 2025, $32.4 billion from the year to March 2026, $10.0 billion on 1 April 2026 and $10.0 billion on 1 July 2026. Those four sum to $54.6 billion. Fair value was $99.6 billion, so the gain is $45.0 billion, and the presentation says none of it was booked this half because the valuation stayed at the 31 March mark. ¥15,671.5 billion divided by ¥157.35 is $99.60 billion. The yen carrying amount is the fair value at the closing rate.
On 1 October SVF2 paid another $10.0 billion. The $30.0 billion follow-on promised on 27 February is complete, cost is $64.6 billion, and the stated interest is about 13% at that date. The note builds the percentage on a diluted count that assumes the $122 billion February round is issued and that excludes the Foundation's warrants, treasury stock and unissued incentive shares. Each tranche used a $730.0 billion pre-money valuation. $64.6 billion divided by $730 billion is not that percentage.
The equipment is Silver Bands 7, a subsidiary the company and SVF2 have invested in. The 12 November slide says it is separate from SB Energy. It signed capacity reservations and purchase contracts for power-generation gear. On the 10 November call, Kazuko Kimiwada said that gear includes gas turbines, transmission and substation equipment, and reservations of turbine manufacturing capacity. Cumulative payments through 30 September were ¥1,500,886 million, printed as $9.48 billion and rounded on the slide to $9.5 billion. The yen divided by $9.48 billion is ¥158.32 per dollar, a blend of payment dates, not the closing rate.
The lease is Energy Global's. Warrants were granted to OpenAI in January 2026 under the Milam County lease, and some were forfeited in August 2026 when the PORTS-Pike lease was executed. The accounts use the same date: warrant terms were amended in August "in conjunction with the execution of new data center lease agreements with OpenAI." The report prints no gigawatts, no term of years, and no start date for lease revenue. We do not borrow those from other pages.
Net sales were ¥4,235,037 million. The telecom segment was ¥3,798,146 million. AI Computing, Arm plus Ampere and Graphcore, was ¥373,595 million ($2,330 million) and lost ¥322,050 million. Together the two segments are ¥4,171,741 million, 98.5% of sales. Arm bills licenses and royalties. That invoice is not the hall.
How does it make money?
Of the ¥1,725,796 million investment gain, the holding-company book was ¥1,078,337 million and Intel was ¥1,062,815 million of it. Intel's reported price moved from $44.13 to $120.23, and the share carrying amount was ¥1,645,060 million. The Vision Funds were ¥705,617 million. No gain or loss was recorded on OpenAI. The September investment line was a loss of ¥133,586 million, so the half's gain was earlier: ¥1,859,382 million in the June quarter, on our arithmetic.
Finance cost was ¥790,662 million, up ¥450,644 million. The September quarter was ¥461,917 million. Holding-company interest, including the OpenAI-linked loan, was ¥676,389 million, up ¥407,217 million, from more debt and from writing off unamortized fees when the bridges were repaid early. Those bridges were $10.0 billion in April and $10.0 billion in July, both repaid by 15 September. The undrawn $10.0 billion was cancelled on 30 September. September's foreign-currency notes funded the 1 October cheque of $10.0 billion, or ¥1,579.6 billion. A separate August loan of $10.0 billion for two years, "using OpenAI shares," is secured by cash rather than by a pledge, with a margin call on the preferred stock, and the parent guarantees it. The balance was ¥1,543.7 billion, $9.81 billion at ¥157.35.
The warrant is the cost of the signature, taken before any lease sales. The half's derivative loss was ¥433,293 million, including ¥321,891 million on Intel prepaid forwards and ¥203,802 million on the Energy Global warrants. The September quarter's derivative loss was ¥41,708 million, so ¥391,585 million of the half's loss sat in the June quarter. The warrant liability ended at ¥541,801 million, down ¥41,161 million: the August amendment cut $2.4 billion from the lease-incentive asset, and a higher Energy Global value offset most of that on the liability. NVIDIA paid a $1.5 billion advance under a share-issuance agreement. The liability is ¥262,250 million, printed as $1.7 billion of fair value, $1.67 billion at ¥157.35.
Cash moved to OpenAI ($20.0 billion in the half, $10.0 billion on 1 October), to suppliers who kept the non-refundable advances, and to lenders, whose finance cost exceeded the equipment loss. No campus sales line came back.
What limits it?
The limit is a queue paid before the plan was finished. On 10 November Yoshimitsu Goto said scarce equipment is sometimes booked before due diligence is done, that this decision was confirmed at the end of the quarter, and that he did not see another asset of the same kind still missing. He also said strategy is discussed daily. Kimiwada said a portion of the spend is meant to be recovered, and that a higher gear price is unlikely to become a gain.
The rebate is the same limit in a number. Silver Bands 7 can receive up to $2.1 billion over ten years on future purchases, subject to conditions. The amount could not be fixed at 30 September, so nothing was booked.
The lease was executed in August and is unbilled. Sales growth in the report is the telecom segment and Arm. "To be recouped" means the advance is still assigned to equipment, $3.4 billion near term and $2.2 billion by the end of 2027. Goto said he knew of no delay at Milam County or in France. This report gives neither site a capacity or a date.
Cash does not clear it. Interest-bearing debt is ¥32,591,205 million, of which the parent's own debt is ¥23,898.9 billion. Owners' equity is ¥16,396,610 million on assets of ¥69,387,194 million, 23.6%, which divides to 23.63%. DigitalBridge closed on 30 September for $3.1 billion (¥477,400 million, provisional goodwill ¥276,290 million). Its results start next quarter. That acquisition is not this loss.
Who else does this?
Oracle leases campuses, owns the chips and sells the hour. These accounts show the advance and the incentive. Anthropic has its cloud minimums in a prospectus. OpenAI's revenue is not taken from secondhand reports. A Vision Funds loss on Silver Bands 7 sits inside ¥364,387 million that also includes PayPay, and it is eliminated. The consolidated loss is ¥597,248 million, once.
What would change this view?
A lease-revenue line, with a yen amount, would change it. A write-down of the $6.6 billion, or a slip past the end of 2027 on the $2.2 billion slice, would change it. Booking any of the $2.1 billion of rebates would change the recovery. A new OpenAI valuation in the December quarter would change the mark, not the equipment. Mark Agne said Anthropic's listing would be one input among several. Goto said no decision had been made on another follow-on round. The $10.0 billion paid on 1 October raises cost. The report does not say it raises fair value by the same amount.
Two later notes sit outside this report. The PJM study is a grid filing, not this advance. The Malaysia seed was signed in November and releases money as milestones hit. Neither figure belongs in the table.
Practical takeaways
Read ¥1,725,796 million as Intel and the funds. OpenAI's mark did not move. Read ¥597,248 million as the queue that left the plan, and $6.6 billion as advances still assigned to equipment. Read $99.6 billion as 30 September fair value and $64.6 billion as cost after 1 October. The stuck step is the non-refundable advance and the unbilled lease. This is a reading of company documents, not a recommendation.
FAQ
What does SoftBank do in this layer?
SoftBank Group does not sell the computing hour. For the six months to 30 September 2026 it holds OpenAI at a fair value of $99.6 billion, and Silver Bands 7 has paid for power-generation equipment for US AI data centers. The sales lines the report prints are the telecom segment and Arm.
Where did the ¥597.2 billion go?
The report records ¥597,248 million, also stated as $3.73 billion, for the six months to 30 September 2026. ¥457,030 million is non-refundable advances for capacity and equipment that left the revised plan. ¥140,218 million is contract modifications and settlements. The 12 November slide takes $2.9 billion off a $9.5 billion advance balance and leaves $6.6 billion.
Is that loss the Ohio campus?
The investor presentation says the $3.7 billion loss is completely unrelated to PORTS-Pike. The 12 November slide assigns $5.6 billion of the remaining $6.6 billion to the PORTS-Pike power project, $3.4 billion in the near term and $2.2 billion by the end of 2027, and $1.0 billion to be recouped over time. Silver Bands 7 is a separate entity from SB Energy.
Did the campuses pay SoftBank this half?
The report does not print a lease-revenue line for the campuses. OpenAI received the investment cash, $20.0 billion in the half and $10.0 billion on 1 October. Fair value was left unchanged, so the half records no gain or loss on OpenAI. Energy Global recorded a ¥203,802 million derivative loss on warrants granted to OpenAI as a lease incentive.
Is the cash the limit?
No. Cash was ¥7,432,165 million at 30 September 2026, and interest-bearing debt was ¥32,591,205 million. The stuck step is the advance that cannot be refunded, and a lease that has been signed and is not yet a sales line.
Keep reading on the map
The mechanism is Stargate, with the purchase commitment under the advance and the cloud commitment as the form that becomes a bill. The matching door is Markets · US, where the equipment and the OpenAI stake sit. On this folder, Oracle sells the hour and Anthropic owes a cloud minimum. The short note is the Catalyst on the equipment loss. The folder is Hyperscalers.
How we check this
The sums we rely on: ¥457,030 million plus ¥140,218 million equals ¥597,248 million, and $3.73 billion times ¥160.12 is ¥597.25 billion. ¥1,500,886 million over the report's $9.48 billion is ¥158.32 per dollar, so we do not restate those payments at ¥160.12. Slide arithmetic is $9.5 minus $2.9 equals $6.6, $3.4 plus $2.2 equals $5.6, and $5.6 plus $1.0 equals $6.6. $9.48 minus $2.85 equals $6.63. OpenAI is $54.6 plus $45.0 equals $99.6, then plus $10.0 equals $64.6. The cost pieces $2.2, $32.4, $10.0 and $10.0 sum to $54.6. ¥15,671.5 billion over ¥157.35 is $99.60 billion.
September's other loss of ¥669,923 million against the half's ¥663,829 million leaves June a ¥6,094 million other gain, so the equipment charge is a September item, beside ¥72,675 million of other September losses. Owners' half-year loss of ¥768,007 million and September loss of ¥1,115,337 million leave June a ¥347,330 million profit. Derivative loss of ¥433,293 million minus ¥41,708 million leaves ¥391,585 million in June, and the two named pieces exceed the net by ¥92,400 million.
Sources
SoftBank Group, consolidated financial report for the six months ended 30 September 2026, Tokyo, 10 November 2026.
SoftBank Group, earnings presentation for the same period, including the page that says the $3.7 billion loss is unrelated to PORTS-Pike.
SoftBank Group, updated equipment slide, as of 12 November 2026, for the $9.5 / $2.9 / $6.6 billion bridge and the line that Silver Bands 7 is separate from SB Energy.
SoftBank Group, investor briefing Q&A, 10 November 2026. The file says later slides were revised and that this transcript follows the 10 November materials. We use it for the spoken answers and the 12 November slide for the allocation.
SoftBank Group, press release on the third OpenAI tranche, 1 October 2026.