Goodman Has 6.4 GW of Power Banked. What Does the Price Assume?

At A$26.39 Goodman trades about A$29.9 billion above book. That premium needs most of its 3.6 GW of secured power to become signed, sold halls, while only 100 MW of the 497 MW under way is leased. What the price assumes, arithmetic shown.

Share
POWER BANKED, HALLS UNSIGNED — Only 100 MW signed. Empty raised-floor equipment room in navy and teal, with an amber pool of light on the vacant floor marking the bind.
Illustrative photo of an empty raised-floor equipment room being fitted out (PEO ACWA / U.S. Army, CC BY 2.0, recoloured), not a Goodman site.

ANALYSIS · MEMBERS CONTINUE · 5 min free / 14 min full · Data as at 16 Oct 2026

Goodman Group, Australia's largest listed property group, has banked 6.4 gigawatts of power for data centres in 16 cities. About 0.5 GW is being built, and 100 MW of that is signed to a tenant. Within two weeks it withdrew a Sydney data centre proposal and met council and resident pushback at its largest Japanese campus. On 16 October its securities closed at A$26.39, down 15% since June. What does the price already assume?

In short

  • The question: what is Goodman's price already assuming about the lease step — the point where power is secured and capital is ready, but a hall still needs a signed tenant and a local licence before it earns?
  • The answer: Scenario B. At A$26.39, the price needs roughly 2.6–3.1 GW of halls to be built, signed and sold through at last year's earnings rate (ours). That is most of the 3.6 GW of secured power, and five to six times the 0.5 GW now under way. It gives nothing for the 2.8 GW still being procured
  • Why: the market pays about A$29.9 billion above book (ours). Spread over the whole power bank, that is about A$4.7 million per banked megawatt (ours), against about A$31 million of end value for a finished, fitted megawatt in Goodman's own pipeline
  • The stuck step: only 20% of the 497 MW under way is leased (ours, from Goodman's table). The share of all work in progress that is committed fell from 37% at 31 March to 25% at 30 June
  • Behind the wall: who gets paid, in order, while the leases wait · what one megawatt is worth · three scenarios, arithmetic shown · what the market could be right about · six practical takeaways · Members' FAQ
  • What would break it: the unsigned halls lease and the price still falls (then the discount is about rates, not the step)
  • Nothing here is a recommendation. This is a map of what the price requires, with the working shown

What's in this piece: the numbers that matter · why Goodman sits at the lease step · what A$26.39 already assumes · members from here · who gets paid while the leases wait · what one megawatt is worth · three scenarios, arithmetic shown · our read · what would change the view, with dates · practical takeaways · FAQ · references


The numbers that matter

What Figure Date What it tells us
Security price A$26.39 close; A$31.13 on 30 Jun; A$34.50 a year earlier ASX, 16 Oct 2026 Down 15% since June, 24% in a year
Net tangible assets A$11.79 a security; 2,044.8M securities 30 Jun 2026 Price is about 2.2x book (ours)
Earnings Operating EPS 129.9 cents, up 10.1%; FY27 target +9% 20 Aug 2026 About 20x trailing, 18.6x the FY27 target (ours)
Where earnings come from Development A$1,792M; management A$690M; property A$722M FY26 Development is about 56% of segment earnings (ours)
Power bank 6.4 GW in 16 cities: 3.6 GW secured, 2.8 GW in advanced procurement 30 Jun 2026 Up from 5.0 GW a year earlier
Data centres under way 497 MW in 10 projects, 8 cities; about 90% fully fitted; delivery 2027–2030 30 Jun 2026 About 8% of the bank (ours)
Signed 100 MW leased (Tokyo 50 MW for 20 years; Hong Kong 50 MW); 138 MW in advanced talks 30 Jun 2026 20% signed, 48% signed or close (ours)
Work in progress A$19.7B, 78% data centres; 25% committed, down from 37% at 31 Mar 30 Jun 2026 Building ahead of signatures
Licence Lane Cove withdrawn 28 Sep; Tsukuba council resolution 6 Oct; first residents' protest 8 Oct Sep–Oct 2026 The local gate is tightening
Rates Australian cash rate raised to 4.60% 29 Sep 2026 Dearer money for buyers of halls
The clocks RBA 3 Nov; AGM 19 Nov; Australian data centre partnership due by 31 Dec 2026 The first dated checks

AI Data Centers — Goodman's power bank against what is built and signed

Chart 1 — From power bank to signed hall: 6.4 GW banked, 3.6 GW secured, 497 MW under way, 100 MW leased. Second Order arithmetic from Goodman's FY26 results. Education only.


Why does Goodman sit at the lease step?

Goodman built its name on warehouses near big cities. In recent years it has turned that land, and the grid connections that come with it, into the raw material for data centres. Its power bank covers 6.4 GW in 16 cities, from Tokyo and Hong Kong to Paris and Los Angeles, and data centres are 78% of its development book. The AI Data Centers layer shows where landlords and developers sit on our map.

On the map, power is usually the step that binds. Goodman has much of that solved. It also has the money: gearing of 6.5%, A$6.4 billion of its own cash and undrawn lines, and A$12.4 billion across its partnerships. About 90% of the halls under construction sit inside those partnerships.

What it does not yet have is the signature. Of the 497 MW under way, 100 MW is leased: a 50 MW Tokyo building let for 20 years to a hyperscale customer, and a 50 MW Hong Kong shell let to one customer. Another 138 MW is in advanced talks. The rest, about 259 MW, is in negotiations or early customer contact (ours). Goodman is building fitted halls and signing as it goes; it links the drop in its committed share, from 37% to 25% in one quarter, to the growing data centre book.

The second gate is the licence. On 28 September Goodman withdrew its Lane Cove West proposal in Sydney, citing policy changes and community feedback, as our New South Wales Pulse covered. A week later, in Tsukuba, north of Tokyo, the city council unanimously asked the city to press Goodman for an open public briefing. Two days after that, residents held their first protest outside the site. Tsukuba is the campus with 1,000 MW of utility power secured. Its first 50 MW building is the one already leased. The other 950 MW is what is at stake.

So Goodman's stuck step is not power or money. It is the lease, and behind it the local licence for the next phase. Our Amazon piece saw permission from the buyer's side; this is the developer's.

What does A$26.39 already assume?

A developer's price is book value plus what the pipeline is expected to earn. Three answers compete:

  1. The bank stays banked. Only the 497 MW under way becomes signed, sold halls by 2030; later phases stall on licences
  2. Secured power converts. Most of the 3.6 GW with power in hand is built, signed and sold through at about last year's earnings rate. The 2.8 GW in procurement is a bonus, not a base
  3. The whole bank converts. All 6.4 GW turns into halls

A tip sheet would pick a side. Analysis asks which answer the price already needs.

Our read, in one line: the price already assumes Scenario B. At A$26.39 the market pays about A$29.9 billion above book; after a plain value for the fee platform, that premium needs roughly 2.6–3.1 GW of halls built and sold through at last year's earnings rate — most of the 3.6 GW of secured power, and five to six times what is under way — while giving nothing for the 2.8 GW still being procured. The price is betting on signatures that only 100 MW has so far. The scenarios and the arithmetic are below.


The free preview ends here.

—— Still to read · ~9 of 14 minutes ——

MEMBERS CONTINUE HERE

  • Who gets paid, in order, while the leases wait
  • What one megawatt is worth
  • Three scenarios with the arithmetic
  • What the market could be right about
  • Six practical takeaways