What Does KT Do? The Hall Dated 2027

KT gets paid on the phone, the card and a cloud subsidiary of KRW 268.2 billion, while the six AI halls on its own slide are dated 2027, 2028 and 2029.

Share
What Does KT Do? The Hall Dated 2027

STACK · Hyperscalers · Status: Dated · Last reviewed: 26 Nov 2026

KT gets paid on the phone, the card and a cloud subsidiary of KRW 268.2 billion, while the six AI halls on its own slide are dated 2027, 2028 and 2029.

In short. KT is a Korean phone company with a card business, media subsidiaries and kt cloud. In the quarter the 10 November 2026 exhibit labels 3Q26, group revenue was KRW 6,997.5 billion and operating income KRW 505.3 billion. kt cloud was KRW 268.2 billion, 3.8% of the group on our arithmetic, with Gasan utilization and design-and-build in one line. The stuck step is the next hall: Bucheon in 2027, three sites in 2028, Ansan in 2029. Token Factory launched on 30 October, after the quarter closed.

A hyperscaler, in the usual telling, is a cloud that buys the chips. Here the subscriber and the cardholder pay, and a subsidiary bills a hall that is already open. Who the hyperscalers are is the layer. This page is one ledger. Speed-to-power is the clock that separates a dated opening from a live bill.

Numbers that matter

The figures are from KT's earnings presentation, Exhibit 99.1 to the Form 6-K furnished on 10 November 2026. The exhibit says the numbers follow K-IFRS. It is a company presentation, and it is not an auditor's report. KT's fiscal year ends in December, so the 3Q26 column is the quarter ended 30 September 2026. Anything we divide or add is marked as our arithmetic.

NumberWhat it isWhy it matters
KRW 6,997.5bnGroup operating revenue, quarter ended 30 September 2026. Operating income KRW 505.3bn. Net income KRW 367.3bnThe group sets the size of the page. The cloud subsidiary does not
KRW 1,666.8bnKT separate wireless service revenue, down 3.9% from a year earlierThe phone bill on the parent. Still the largest named service line
KRW 268.2bnkt cloud revenue. The slide prints +7.7% year on year and +1.0% from JuneGasan utilization and design-and-build, in one line. 3.8% of the group on our arithmetic
KRW 393.3bnCombined KT AX and kt cloud for the quarter. The 2026 cumulative bar is KRW 1,111.9bnMixes the subsidiary with subsea cable, contact centers and AI/IT. Token Factory is outside it
KRW 1,599bnCapex executed through the quarter: KRW 1,228.2bn at KT and KRW 370.9bn at major subsidiariesThe subsidiary slice includes finance, media, cloud and real estate. It is not a hall budget
KRW 3,042.4bnCash and cash equivalents, 30 September 2026Beside short-term borrowings of KRW 3,797.5bn and long-term borrowings of KRW 7,302.3bn. Not the bind
2027–2029Six AIDC sites: Bucheon in 2027, Gaebong, Gunsan and Yongin in 2028, Ansan in 2029The further 1 GW is a demand-driven mark around 2031. None of these sites is inside the September cloud line

Service revenue was KRW 5,880.9 billion and sale of goods KRW 1,116.6 billion. They add to revenue. Operating income of KRW 505.3 billion is that revenue minus expense of KRW 6,492.2 billion, a printed margin of 7.2%. The 8.6% margin is operating income over service revenue. Pretax income was KRW 499.3 billion, tax KRW 132.0 billion, net income KRW 367.3 billion. EBITDA was KRW 1,428.3 billion. The KRW 923.0 billion gap to operating income is our arithmetic, and the exhibit does not label it. From June, goods rose KRW 359.6 billion and service revenue fell KRW 42.0 billion. Revenue rose KRW 317.6 billion. The increase is a handset quarter.

Parent revenue was KRW 4,987.8 billion, service KRW 4,106.1 billion plus handsets KRW 881.7 billion, and separate operating income was KRW 299.3 billion. Wireless, fixed line and B2B add to KRW 3,972.1 billion, leaving KRW 134.0 billion of separate service revenue unnamed. Fixed line adds exactly: broadband KRW 637.4 billion, media KRW 521.5 billion, telephony KRW 149.3 billion. Wireless service plus interconnection of KRW 71.1 billion is KRW 0.1 billion under the printed wireless total.

The combined AX bar is KRW 393.3 billion, up 9.8% from KRW 358.1 billion and 6.9% from June's KRW 367.8 billion. Minus kt cloud, the parent slice is KRW 125.1 billion on our arithmetic, against KRW 109.1 billion a year earlier and KRW 102.4 billion in June. The slide calls that slice subsea cable, AICC and AI/IT, and prints no won split. The three 2026 bars, including a first quarter of KRW 350.8 billion that the cloud row does not break out, add to the printed cumulative of KRW 1,111.9 billion, up 11.9% from KRW 993.4 billion. Against group revenue for the three quarters, KRW 20,455.8 billion, that stack is 5.4%. It mixes a subsidiary with a parent slice, so the 5.4% is a scale check and not a segment share. Capex through the quarter is KRW 1,228.2 billion at KT plus KRW 370.9 billion at the major subsidiaries, KRW 1,599.1 billion, printed as KRW 1,599 billion. The subsidiary piece includes finance, media, cloud and real estate. Enterprise internet, KRW 392.0 billion, stays off the B2B line.

What does it actually do?

KT sells mobile service, a fixed line, a business line and handsets. 5G handsets are 11,170 thousand and other handsets 2,211 thousand. Divided, that is the slide's 83.5%. A count excluding IoT ends September at 14,831 thousand, against an appendix total of 30,061 thousand. Quarterly ARPU is KRW 34,394, down 2.6% from a year earlier. July through September print KRW 33,963, KRW 34,507 and KRW 34,711, and average to the quarter.

Five subsidiaries have their own revenue. BC Card was KRW 903.8 billion, more than three times kt cloud. kt skylife was KRW 249.0 billion, the content group KRW 171.8 billion, kt cloud KRW 268.2 billion and kt estate KRW 260.0 billion. Estate, tied on the slide to hotels and a development, rose KRW 73.1 billion from a year earlier. kt cloud rose KRW 19.2 billion. The larger increase is the property book. The slide prints the cloud's move from June as +1.0%. The won move is KRW 2.8 billion, 1.1% at one decimal, and both stay. The causes named are Gasan, a data center the slide dates to November 2025, and design-and-build. One line holds the open hall and the construction bill.

The roadmap is a list of dates. A further 1 GW, demand-driven, around 2031. Bucheon 1 and 2 in 2027, Gaebong, Gunsan and Yongin in 2028, Ansan in 2029, with further sites still in decision. Another 90 Tbps of subsea capacity around 2031, and leased cable the slide expects to sell out this year. Token Factory launched on 30 October 2026, with 500 or more models and OpenRouter named as a partner. A Palantir contract in financial services is dated August 2026. No won figure is attached to any of them.

How does it make money?

What repeats is the service bill, and it fell 0.7% while handsets carried the revenue increase. Parent wireless service fell 3.9%. The slide names a customer-appreciation program from February through July 2026 and churn during a penalty waiver. July is inside this quarter, and the months are not split. Fixed line fell 1.8%. B2B service of KRW 925.9 billion is down 0.7% from a year earlier. The parent AX slice is cable, contact center and AI or IT work, unsplit. Token Factory launched on 30 October, so it is outside this revenue, and the August Palantir contract has no price.

Operating income fell 6.1% from a year earlier, to a level the slide ties to that base and to a lower separate profit. Separate operating income was KRW 299.3 billion, from KRW 340.9 billion. Subsidiaries' contribution was KRW 206.2 billion, from KRW 197.3 billion: the printed +4.5%, and +40.0% once KRW 50.0 billion for the Gwangjin-gu project is taken out of the earlier bar. 197.3 minus 50.0 is 147.3, and 206.2 divided by 147.3 is the 40.0%. Group operating income minus the separate figure is KRW 206.0 billion, KRW 0.2 billion from the printed contribution. Below that, the non-operating result swung from income of KRW 55.3 billion to a loss of KRW 6.0 billion. The operating decline of KRW 32.9 billion plus that swing of KRW 61.3 billion lands within KRW 0.1 billion of the KRW 94.1 billion drop in pretax income. An equity-method loss of KRW 5.1 billion is inside that block.

The dividend was set after the quarter: KRW 600 a share, record 28 October 2026, payment 12 November 2026. The stated full-year minimum is KRW 2,400. Four quarters at KRW 600 would match it. The exhibit does not fix the other quarters and prints no share count. The buyback of KRW 250 billion is the FY26 plan. Its trust ran until 9 September 2026. Cash spent under the trust is not on the exhibit.

What limits it?

The limit is a hall with a year and without a September invoice. Bucheon is 2027, three sites are 2028, Ansan is 2029, and the further 1 GW is a demand-driven mark around 2031. The exhibit prints no megawatts. Inside the cloud line, Gasan utilization and design-and-build share KRW 268.2 billion. One is a bill for a hall already taking load. The other can be paid while the work is still a job. That mix is the stuck step inside the number. The dated sites are the stuck step outside it.

Cumulative orders are up more than 20%, with the growth called B2B and data-center driven, and there is no won book and no quarter in which it becomes revenue. B2B service revenue is down 0.7% from a year earlier. Token Factory is an October launch. Leased subsea capacity is "expected" to sell out this year, beside a 2031 capacity mark, and there is no cable revenue line. The Palantir contract is unpriced.

Cash is open: KRW 3,042.4 billion, little changed from June's KRW 3,049.8 billion, beside borrowings of KRW 3,797.5 billion short term and KRW 7,302.3 billion long term. The sum is KRW 11,099.8 billion on our arithmetic. Cash is 11.3 times one quarter of kt cloud. It does not put Bucheon on the invoice. Contract liabilities of KRW 262.0 billion are not described as a hall prepayment. Inventories of KRW 870.1 billion sit next to the handset book, where separate inventories are KRW 409.8 billion. Tangible assets fell KRW 77.1 billion in the quarter. That move and the nine-month capex line are different clocks.

Who else does this?

SK Telecom is the other large Korean phone bill with a data-center line. In its September quarter that line mixed a GPU hour with cable traffic, and the company said the hour paused while contracts lengthened. KT's cloud line rose 7.7%, and the mix is a hall dated November 2025 plus design-and-build. The ledgers are different.

Naver is building a factory on a partner's money and has named one customer for part of the power. KT's exhibit names six future sites and names no tenant, no megawatt and no price. The August contract and the October platform are unpriced. How hyperscalers buy power is the page for a signature on the watt before the plant is live. This exhibit does not show that signature.

What would change this view?

A split of the KRW 268.2 billion would show whether kt cloud was paid for a running hall or for construction. An order book in won, and the quarter it becomes revenue, would show whether "up more than 20%" is a bill. A cloud line that names Bucheon would mean the roadmap had become an invoice. A price on Token Factory or the Palantir contract, or a megawatt on a KT filing, would put those steps on the ledger. This exhibit has none. On these numbers the open item is the dated hall.

Practical takeaways

  • Read KRW 6,997.5 billion as the group and KRW 268.2 billion as kt cloud, 3.8% on our arithmetic.
  • Leave Gasan and design-and-build together until the company splits them. Token Factory launched on 30 October, after this bill.
  • The six sites are dated 2027, 2028 and 2029. The further 1 GW is around 2031. The exhibit prints no megawatts.
  • BC Card at KRW 903.8 billion is a larger subsidiary invoice than the cloud. Estate's revenue rose more than kt cloud's.
  • Cash of KRW 3,042.4 billion sits beside borrowings of KRW 11,099.8 billion on our arithmetic. The open item is the next hall.
  • The KRW 600 dividend records on 28 October and pays on 12 November, with no share count on the exhibit.

FAQ

What does KT do?
KT runs a Korean phone network and, beside it, a card company, a media group and a cloud subsidiary. In the quarter the exhibit labels 3Q26, group operating revenue was KRW 6,997.5 billion and kt cloud revenue was KRW 268.2 billion.

How big is the cloud line?
kt cloud was KRW 268.2 billion, 3.8% of group operating revenue on our arithmetic. The slide credits Gasan data-center utilization and a design-and-build business, and it does not split them.

When do the next AI halls open?
The exhibit dates six sites: Bucheon 1 and 2 in 2027, Gaebong, Gunsan and Yongin in 2028, and Ansan in 2029. A further 1 GW is a demand-driven mark around 2031. None of those openings is inside the September cloud line.

Is Token Factory in this quarter?
No. The slide says Token Factory launched on 30 October 2026, after the quarter ended. It offers 500 or more models, with OpenRouter named as a partner. It prints no price, and this page leaves it out of the KRW 268.2 billion.

Is cash the limit?
No. Cash and cash equivalents were KRW 3,042.4 billion. Short-term borrowings were KRW 3,797.5 billion and long-term borrowings were KRW 7,302.3 billion. The stuck step is the hall dated 2027, and a cloud line that still mixes a running hall with construction.

Is this a recommendation to invest in KT?
No. This page explains how KT gets paid and which step is stuck. It is not a forecast and not advice to buy or sell.

Keep reading on the map

The layer is who the hyperscalers are. The clock on a hall that has a date and is waiting on a bill is speed-to-power. The Korea door is Markets / Korea. The 22 November Wire on the 50 MW grid-review pass is the draft rule for AI halls outside the capital region. This exhibit prints no megawatts and does not say which of the six sites would use that pass, so this page does not put Bucheon or the later sites on either side of the 50 MW line. The other Korean ledgers here are SK Telecom and Naver.

How we check this

One exhibit is the source. We re-add the lines that claim to add, and every other division is ours. Where our one-decimal figure and the slide differ, as on kt cloud's change from June, both stay. Megawatts from a call report stay off. The buyback stays a plan. The EBITDA gap stays unlabeled. The 6-K is the copy used here.

Sean

Writes Second Order by TKN on who gets paid, where money sticks, and which step is stuck.

Author page → · Editorial standards →

Sources

  1. KT Corporation — 3Q26 earnings presentation, Exhibit 99.1 to Form 6-K (furnished 10 Nov 2026) — K-IFRS income statement and balance sheet, the cloud and AX lines, capex, the dated halls, Token Factory, and the dividend
  2. KT Corporation — Form 6-K cover (10 Nov 2026) — the exhibit index and the IR office signature on the furnishing