What Does Cerebras's Price Assume About the Lease That Has Not Started?

Cerebras closed at $98.51. About $8.5 billion of data-center leases are signed and not on the books. The September hour is already billed.

Share
A live teal data hall and a glowing wafer cart, an amber-strapped lease folder, and an empty cage with an amber padlock. Overlay: THE UNSTARTED LEASE / Still off the books.

ANALYSIS · MEMBERS CONTINUE · 6 min free / 17 min full · Data as at 24 Nov 2026

In short

In short. Cerebras Class A closed at $98.51 at 16:00 ET on 23 November 2026. The 10-Q, issued 12 November, counts 243,003,364 common shares across three classes on 5 November, on our addition. About $8.5 billion of data-center lease payments are signed, start in 2026 and 2027, and are not on the 30 September balance sheet. The September cloud hour is already billed. Service credits on the late OpenAI capacity started on 1 October, and the filing prints no dollar for them. Our read: the close pays for an hour that has started and a lease that has not. The multiples are below. Not a rating.

Behind the break: who gets paid, three scenarios with the arithmetic shown, our read, the dates that would change it, and the checks.

The numbers that matter

Each row is a figure on a page we fetched. The close is the Class A print. Class B and Class N do not have a separate close on that page. Sums and ratios are in the members’ section. The lease figure and the remaining-performance figure are the filing’s approximations. Where a page is silent, this note says so.

LineFigureWhat the page is counting
Class A close$98.5123 November 2026, 16:00 ET. Prior close the same page, $82.67
Class A, B and N160,084,168 / 69,203,688 / 13,715,508Outstanding on 5 November 2026, cover of the 10-Q. Not the 23 November count
September equity$9,158.913 millionStockholders’ equity at 30 September 2026. Unaudited
Cash, restricted cash, treasuries$3,074.752 million / $444.042 million / $4,286.026 millionSame balance sheet. Three lines, not one pile
September revenue$210.809 millionQuarter ended 30 September. Hardware $68.881 million. Cloud and other services $141.928 million
September resultLoss of $161.218 millionNet loss. Nine-month loss $625.752 million. Gross profit $42.094 million
OpenAI, the quarter$72.4 millionArrangement revenue, net of a $3.2 million warrant reduction. Risk factor prints 34%
The other two named shares38% and 7%MBZUAI and G42, same quarter, risk factor. Not a combined invoice
Leases already on the books$756.875 million of future paymentsUndiscounted. Present value $621.139 million. Right-of-use asset $571.237 million
Leases not commencedAbout $8.5 billionUndiscounted payments. Start dates in 2026 and 2027. Absent from the balance sheet at 30 September
A later signatureAbout $217.8 millionFurther uncommenced leases signed in the fourth quarter, disclosed 12 November. Its own row
Customer bookAbout $26.1 billionRemaining performance obligations at 30 September. About 33% expected by 30 September 2028. Pass-through on uncommenced capacity is left out
The creditsNo dollarStarted 1 October 2026 on uncured OpenAI capacity. Outside the September $72.4 million

A Class A close, a three-class share count, a dollar of September equity and an undiscounted lease payment stay in their own columns. The filing does not print a market value.

Why does this close sit on a lease that has not started?

Cerebras sells a wafer-scale system and an inference hour on that wafer. The layer is the neocloud, on the Neoclouds shelf. Today’s Stack page reads the same 10-Q as a business. This note asks what the 23 November close assumes about the lease that has not started. It is a price. It is not a target.

The 10-Q evaluates subsequent events through 12 November and does not contain $98.51. The cover count is 5 November. We do not update it. Class A, Class B and Class N have the same economic rights, and Class B and Class N convert one for one into Class A, apart from votes. The exchange prints one price. Applying it to all three classes is our assumption. The members’ section also shows the Class A line alone.

Two neighbouring clocks stay out of the sum. Yesterday’s Wire is an L&T order bracket before a January 2027 switch-on. Today’s China pulse prices a new Awinic share at 43.69 yuan and leaves the purchase cheque blank. Neither is added to the $8.5 billion.

What has the September hour already billed?

The quarter ended 30 September 2026 recognised $210.809 million. Cloud and other services were $141.928 million. Hardware was $68.881 million. Of the cloud line, $141.691 million was recognised over time. Dedicated capacity is take-or-pay, the pattern in take-or-pay GPU contracts. The filing does not split that hour from on-demand.

OpenAI’s arrangement contributed $72.4 million after a $3.2 million warrant reduction. The risk factor prints OpenAI at 34%, MBZUAI at 38% and G42 at 7%. The result was a loss: gross profit $42.094 million, operating loss $224.149 million, net loss $161.218 million. Nine-month net loss was $625.752 million. Other income of $63.900 million was larger than gross profit. Basic loss per share is $0.67 on 238,885 thousand weighted-average shares, which is not the 5 November cover. The loan ratios are below.

What is still off the books?

Note 15 says non-cancelable data-center leases, with commencement in 2026 and 2027, had not started at 30 September, so they are not on the balance sheet. Undiscounted payments are approximately $8.5 billion. Leases already started show $756.875 million of future payments and a right-of-use asset of $571.237 million. A later paragraph adds approximately $217.8 million of further uncommenced leases, signed in the fourth quarter and kept in its own sentence.

The customer book is a different clock. Remaining performance obligations were approximately $26.1 billion. About 33% is expected by 30 September 2028, and 44% in the 24 months after that. Pass-through on capacity whose lease is not yet a right-of-use asset is excluded, and that dollar is not printed. The filing does not say the $8.5 billion is the missing piece. We do not subtract one from the other.

Delivery is already short. At 30 September, without adjustment for excused delays, less OpenAI capacity had been delivered than the agreement contemplates, and delays may run through a portion of 2027. Credits commenced on 1 October 2026. The filing prints no dollar for them. A tranche still uncured 90 days after the milestone can be terminated by either side. The company expects the capacity that becomes terminable in 2026 to be less than 5% of the 750 MW commitment. It does not say a tranche has been terminated.

The one-line read: the 23 November close is a Class A price on a company whose September hour is already recognised and whose largest new lease payments are still off the books. Landlords on commenced leases are already in the quarter’s cost. The uncommenced bill, and the OpenAI credits, have not been given a dollar inside the price. The arithmetic is below.

The free preview ends here. Below: who gets paid, the three scenarios, our read, and what would change it.