If Two Pledges Wait on 9 December Votes, Where Does Cash Stick?
Two hearings on 9 December still sit in front of a $50 billion Arizona plan and an approximately $24 billion Texas estimate. The $74 billion is our sum. The cash already described as received is $220 million.
ANALYSIS · MEMBERS CONTINUE · 6 min free / 17 min full · Data as at 13 Nov 2026
Two hearings fall on Wednesday 9 December 2026. Neither hearing is an approval. In Cochise County the Planning and Zoning Commission is scheduled to hear special-use application SU26-22 at 2:00 p.m. In the City of Starbase the City Commission is scheduled to consider a property-tax abatement and a related economic-development agreement at 7:00 p.m. SpaceX's Cochise County page says the company plans to invest $50 billion. The Starbase notice says the estimated capital investment for the initial phases is approximately $24 billion. Our arithmetic: 50 + 24 = 74. The $74 billion is that sum. It is not a line on either document.
Today's Taiwan pulse is a wafer already recognised, NT$586.89 billion for October. Today's Stack page is a tool invoice already recognised, €1,159.4 million to 30 September. Yesterday's Wire is the pledge. This page asks where cash sticks while the halls are still hearings. The clocks are different currencies and not the same customer. The layer is AI Data Centers.
In short
- The question: if a $50 billion Arizona plan and an approximately $24 billion Texas estimate are still in front of votes on 9 December, where does the cash stick?
- The $74 billion is our sum of those two figures. It is not a company total.
- The dollar this record shows as already received is $220 million that Brownsville said it received when the tract was de-annexed, as the Texas Tribune reported on 10 November. The $3.6 billion Arizona grid line is written in the future tense.
- The electric cooperative said on 10 November that no final power agreement exists, and that the member benefits are not guaranteed.
- Below the break: who gets paid, three scenarios with the arithmetic shown, and the dates that would move the view.
- Nothing here is a recommendation, and this page does not say what to do with any shares.
The numbers that matter
Arizona dollars are SpaceX's Cochise County page, read on 13 November 2026. The Texas estimate is the Starbase notice. The county process is Cochise County's page, updated 12 November. The $220 million is the Texas Tribune's report of the city, not a line on the notice. The wafer is TSMC's 10 November release. The film tool is ASM's 27 October release.
| What | Figure | Where it is from |
|---|---|---|
| Arizona investment | $50 billion | SpaceX Cochise County page, read 13 Nov 2026. The page says "plans to invest" and, in one answer, "committed to invest." |
| Texas initial phases | approximately $24 billion | City of Starbase notice for 9 Dec 2026. Initial phases, which may include later expansions. Not the value of the tax break. |
| Sum of the two | $74 billion | Our arithmetic: 50 + 24. Printed on neither page. |
| Arizona power | up to 6 gigawatts, and a 24 gigawatt-hour battery | SpaceX page. Nine buildings, about 493,000 square feet each. |
| Grid upgrades | $3.6 billion, future tense | SpaceX page. To be transferred to Arizona Electric Power Cooperative members at zero cost. |
| Member benefits, headlined | up to $260 million a year and up to $200 million a year | SpaceX page, at full build, subject to final negotiations. |
| Member benefits, later on the page | up to $190 million, up to $53 million, and up to $200 million a year | Same page. It does not reconcile this list with the $260 million line. |
| County hearing | SU26-22, 9 Dec 2026, 2:00 p.m. | Cochise County, updated 12 Nov 2026. Applicant Tombstone Resources L.L.C. About 747 acres. Gigawatts are the applicant's and are not verified. |
| Starbase hearing | 9 Dec 2026, 7:00 p.m. | City notice. Chapter 312 abatement and a Chapter 380 agreement. About 444 acres. No megawatts and no abatement percentage. |
| Power agreement | none final | SSVEC, 10 Nov 2026. A final agreement needs Arizona Corporation Commission review. |
| Described as received | $220 million | Texas Tribune, 10 Nov 2026, reporting Brownsville. Water and wastewater, tied to de-annexation. |
| October wafer | NT$586.89 billion | TSMC, 10 Nov 2026. Up 14.7 percent from September and 59.7 percent from a year earlier. No campus and no package line. |
| Film-tool quarter | €1,159.4 million | ASM, quarter to 30 Sep 2026. Equipment €936.4 million. Next quarter €1,230 million, plus or minus 5 percent, at constant currencies. |
The table does not split the $74 billion into buildings, power, and chips. That split is not in the documents.
Why do two hearings on one day matter?
A pledge is not a hall, and a hearing is not a yes.
Cochise County does not allow a data center by right. The commission can approve SU26-22, approve it with conditions, or deny it. That decision is final unless appealed, and it is not a building permit. The county says the gigawatts are the applicant's and are not verified. Packet comments are due at noon on 27 November, 14 days from today. The hearing is 26 days away.
The county applicant is Tombstone Resources L.L.C. SpaceX's page describes the campus. The cooperative describes a SpaceX town hall on that application. This page treats them as one project on those two sources, and it does not treat the county as having checked the power figure. Starbase is a different site: a gas plant and a super-compute facility, about 444 acres, with no abatement percentage and no megawatts in the notice. Arizona, on the company page, has no on-site power plant. The hearings share a date, not an hour, and not a power plan.
What does the record already show as received?
Brownsville's cheque, and almost nothing else. The Tribune reported that the city said it received $220 million for water and wastewater when the tract was de-annexed. The Starbase notice does not mention that cheque, so this page does not subtract it from the $24 billion. The $3.6 billion is a transfer the company says it will make. The cooperative said no final agreement has been reached.
What do the wafer and the film have to do with a hearing?
They have already paid someone else. TSMC's October release is one line, with no campus and no package. ASM's quarter is already recognised, and the company says supply chains are stretched. Neither release names these sites.
Do not add the three currencies. That would invent an exchange rate and a customer. The hearings can start a new hall-cash clock. They do not reopen October or the quarter to 30 September.
Our read, in one line
The $74 billion is our sum of two pledges still in front of hearings. The dollar this record shows as already received is Brownsville's $220 million. The grid gift, the member benefits, and any chip order are still ahead of a vote and, in Arizona, ahead of a power agreement the cooperative says does not exist. The worked cases are below.