Data Center Leases Explained: Rent Starts When the Power Does
A data center lease rents powered capacity, priced per kilowatt a month, not per square foot. The money arrives late: rent starts when the hall is powered and handed over, so the gap between signed and billing is the stuck step.
EXPLAINED · Mechanism · Last reviewed: 15 Oct 2026 · Next review: after Digital Realty's third-quarter 2026 results
A data center lease is a contract to rent powered capacity in a data center, measured in kilowatts or megawatts of IT load and priced per kilowatt a month, rather than floor space priced per square foot. The landlord gets paid when the lease commences, meaning the hall is powered and handed over, not when it is signed: at Digital Realty the average gap was nine months in the second quarter of 2026.
In short. A data center lease rents power, not floor space: the tenant pays per kilowatt of IT load per month. Big AI and cloud tenants lease whole halls for roughly nine to 15 years at lower rents; small tenants pay more per kilowatt on shorter leases. The catch is timing. Rent starts when the hall is powered and handed over, not when the lease is signed. Digital Realty had $1.9 billion a year of rent signed but not started at the end of June 2026, and NEXTDC had 740 MW contracted but only 175 MW billing. The stuck step is the gap between the two, and power sets how long it lasts.
Why an investor cares: a landlord’s headline number is usually what it has signed. Its income is what has commenced. The space between the two is where AI data center money waits, and how long it waits depends on when the power arrives. This page builds on what an AI data center is and explains the contract that turns a powered hall into rent.
What is a data center lease?
A contract that rents capacity to run servers. The unit is power: a tenant leases, say, 10 MW of critical IT load, meaning the electricity its servers can draw, along with the space, cooling and backup power needed to keep them running. Floor area matters far less than in an office or a warehouse, because what is scarce is a powered, cooled hall.
Three kinds of lease cover most of the market. In a powered shell the landlord delivers the building and the grid connection and the tenant does the fit-out. In a fully fitted single-tenant lease the landlord delivers a finished hall to one tenant. In colocation the landlord runs a finished building and rents racks, cages or suites to many tenants.
| Powered shell | Fully fitted, one tenant (wholesale) | Colocation | |
|---|---|---|---|
| What the landlord delivers | Land, building and a utility power connection | A finished hall: power distribution, cooling, backup power | A finished hall it runs, shared by many tenants |
| What the tenant brings | The fit-out, then its servers | Its servers | Its servers, in a rack, cage or suite |
| Who pays running costs | The tenant, usually on a triple-net lease | Mostly the tenant (triple-net is common) | The landlord, inside the rent |
| Typical size | Whole building, tens to hundreds of MW | Over 1 MW, often a whole hall | A few kW up to about 1 MW |
| Rent per kW a month | Lowest | $157 on Digital Realty's new leases over 1 MW, Q2 2026 | $280 on its new leases up to 1 MW, Q2 2026 |
| Lease length | Long; Keppel DC REIT's shell-and-core leases have 6.8 years left | 8.8 years on Digital Realty's new big leases; 15 years at Applied Digital | 4.1 years on Digital Realty's new small leases; 2.8 years left at Keppel DC REIT |
From Digital Realty, Keppel DC REIT and Applied Digital filings, listed under References. "Lowest" is a description, not a reported figure.
How is a data center lease priced?
Per kilowatt of IT load per month. Size sets the price. In the second quarter of 2026, Digital Realty’s new leases of up to 1 MW paid $280 per kilowatt a month, and its new leases over 1 MW paid $157, about 44% less (our arithmetic). The big tenants bought that discount with time: their leases averaged 8.8 years, against 4.1 for small ones.
The largest AI leases go further. Applied Digital signed a 210 MW, 15-year lease at its Delta Forge 2 campus with an investment-grade hyperscaler, worth about $5.2 billion over the base term. That works out at about $138 per kilowatt a month averaged over the 15 years (our arithmetic, $5.2 billion divided by 210,000 kilowatts and 180 months). How the two kinds of hall compare is in hyperscale vs colocation data centers.
Rent usually steps up each year under escalators written into the lease, and many leases carry renewal options. Applied Digital says its leases are worth about $36 billion over their initial terms, and about $86 billion if every renewal option is used.
What is a powered shell data center?
A building with the land, structure and utility power connection in place, but without the fit-out: no power distribution to the racks, no cooling plant inside the hall, no backup generators or batteries. The tenant pays a lower rent and spends its own money finishing the hall to its own design. Digital Realty sells this product under the name Powered Base Building, alongside a finished version it calls Turn-Key Flex.
Why a tenant would choose it: the biggest AI tenants want control over how racks are cooled and powered, because their hardware changes every couple of years. Why a landlord would offer it: less capital at risk per megawatt, and the scarce part, the grid connection, is still the landlord’s to sell.
When does the rent start?
When the lease commences, not when it is signed. Commencement means the space is ready and the tenant takes control of it. Before that, a signed lease is a promise of future rent and nothing more on the income statement.
Digital Realty shows the gap in its numbers. Leases it signed in the second quarter of 2026 had an average gap of nine months before commencement. At 30 June it had a record $1.9 billion a year of rent signed but not commenced, counting its joint-venture partners’ share, or $1.4 billion at its own share. In July it signed two more hyperscale leases worth $410 million a year, including partners.
| Digital Realty, second quarter of 2026 | Figure |
|---|---|
| New leases signed, yearly rent (incl. partners' share) | $307m |
| Two hyperscale leases signed in July, yearly rent (incl. partners' share) | $410m |
| Signed but not commenced at 30 June, yearly rent | $1.9bn incl. partners; $1.4bn its own share |
| Average gap from signing to commencement (Q2 leases) | 9 months |
| Rent per kW a month, new leases up to 1 MW / over 1 MW | $280 / $157 |
| Average lease term, new leases up to 1 MW / over 1 MW | 4.1 / 8.8 years |
| Cash rent change on renewals, up to 1 MW / over 1 MW | +5.2% / +66.7% |
Digital Realty’s second-quarter 2026 earnings release and financial supplement. Rents are GAAP rent per kilowatt per month for new leases.
NEXTDC, the Australian landlord, shows the same thing in megawatts. At 30 June 2026 it had 740.1 MW contracted on a pro forma basis, 287.9 MW built and 175.0 MW billing. Under a quarter of what it had signed was paying (our arithmetic). Its accounts spell out the rule: the M3 Melbourne lease commenced during the year, so its income was recognised; the S4 Sydney agreement was signed during the year but had not commenced by 30 June, so it produced no lease income. More on that landlord in what NEXTDC does.

Why is the gap between signed and billing the stuck step?
Because the date a hall goes live is set by power, and power is the slowest part to arrive. A lease can be signed in a week. The grid connection, substation and switchgear behind it can take years, which is why building an AI data center takes about two years even when the money is ready.
Applied Digital’s Polaris Forge 1 campus in North Dakota is a clear example. It is fully leased to CoreWeave for 400 MW of critical IT load. On 2 October 2026 the company said 250 MW was operational after its latest three 25 MW halls came online. The other 150 MW is signed, financed and still being built.
Meanwhile the landlord’s builders get paid first. In the quarter to 31 August 2026, Applied Digital booked $183.5 million of revenue for fitting out tenants’ halls, almost three times its $65.8 million of base rent (our arithmetic), plus $13.3 million of costs recharged to tenants. Fit-out revenue is one-off; base rent is the 15-year stream. See what Applied Digital does.
Our view: for an AI data center landlord, signed megawatts measure demand and billing megawatts measure income. The ratio between them, and how fast it closes, tells you more than either number alone. A landlord with a big backlog and slow power is a landlord whose income arrives later than the headline suggests.
Who pays for power and running costs?
It depends on the lease type. In a triple-net lease the tenant pays rent plus the building’s running costs, such as power, maintenance, property tax and insurance. In a colocation contract the tenant pays rent and the landlord carries the costs.
Keppel DC REIT, the Singapore-listed landlord, sets this out asset by asset. Its colocation clients pay rent and the owner bears the expenses and runs the facility. Its shell-and-core tenants pay rent and all outgoings and run their own space. Its fully fitted single-tenant leases sit in between: the client pays rent, runs the facility and pays the outgoings, except insurance on the building shell. Across the portfolio it says most electricity costs can be recovered from clients under their contracts. See what Keppel DC REIT does.
Lease length follows the same split. At 30 June 2026, Keppel DC REIT’s colocation contracts made up 74.1% of its rent with an average of 2.8 years left, single-tenant halls 21.0% with 9.1 years left, and shell-and-core 4.9% with 6.8 years left.
Who gets paid, and when?
- Builders and equipment suppliers, first. Before any rent, the landlord or tenant pays for the shell, the electrical gear, the cooling and the fit-out. NEXTDC spent A$3.4 billion in its 2026 financial year and plans A$5.25 billion to A$5.75 billion in 2027, principally on capacity its customers have already contracted.
- The landlord, at commencement. Rent starts when the hall is handed over, then steps up under escalators. Digital Realty’s nine-month average gap is the wait.
- The landlord again, at renewal. Old leases on powered halls reprice. Digital Realty’s expiring leases over 1 MW renewed 66.7% higher in cash rent in the second quarter of 2026, from $159 to $265 per kilowatt a month. See what Digital Realty does.
- The tenant, only once its servers run. A hyperscaler or neocloud pays rent from commencement but earns nothing until its chips are installed and sold as cloud hours. That gap sits on the tenant’s side, covered in GPU utilization explained.

How does it work in Singapore and Australia?
- Singapore: short leases, rationed power. Most of Keppel DC REIT’s rent comes from colocation contracts with under three years left, so renewals reprice quickly; its renewals in the first half of 2026 started about 10% higher. New power is allocated by the government: on 21 August 2026 the EDB and IMDA gave the latest 200 MW to four operators, Digital Realty, Equinix, Keppel Data Centres and ST Telemedia Global Data Centres, 50 MW each. Our Singapore Pulse covers that allocation.
- Australia: a big order book converting over four years. NEXTDC says every megawatt in its 565.1 MW Forward Order Book is a binding customer contract. It expects 197 MW to start billing in its 2027 financial year and 221 MW in 2028, together 74% of the book. It now books its large hyperscale agreements as operating leases.
What would prove this wrong?
- The gap closes fast. If Digital Realty’s signing-to-commencement lag falls well below nine months, or NEXTDC converts its order book ahead of schedule, power is no longer the slow step.
- Signed leases get cancelled. A backlog only counts if tenants stay. Terminations before commencement would show that signed demand was softer than it looked.
- Renewal jumps fade. If big-lease renewals go back to single-digit increases, powered halls are no longer scarce enough to set the price.
What to check next
Digital Realty’s third-quarter 2026 results will show whether its signed-but-not-commenced backlog is still growing or starting to convert. Applied Digital’s next update will show whether the last 150 MW at Polaris Forge 1 comes online. NEXTDC’s next update will show how much of the 197 MW due in its 2027 financial year is billing.
Common misconceptions
- People assume a signed lease is revenue. Actually rent starts at commencement; NEXTDC’s S4 Sydney agreement produced no lease income in the year it was signed.
- People assume data centers are rented by the square foot. Actually the unit is the kilowatt of IT load, priced per month.
- People assume a lower rent per kilowatt means a worse lease for the landlord. Actually the big leases run roughly twice as long, and reprice sharply at renewal when power is scarce.
FAQ
What is a data center lease?
A contract to rent powered capacity in a data center. The tenant rents kilowatts or megawatts of IT load, with the space, cooling and backup power needed to run it, and pays a monthly rent per kilowatt. Big AI and cloud tenants sign long leases: Digital Realty's new leases over 1 MW averaged 8.8 years in the second quarter of 2026, and Applied Digital's latest runs 15 years.
How are data center leases priced?
Per kilowatt of IT load per month. In the second quarter of 2026, Digital Realty's new leases of up to 1 MW paid $280 per kilowatt a month and its new leases over 1 MW paid $157. Applied Digital's 15-year, 210 MW lease works out at about $138 per kilowatt a month averaged over the term (our arithmetic).
What is a powered shell data center?
A building with land, structure and a utility power connection in place, but without the fit-out inside, such as the power distribution, cooling and backup systems for the servers. The tenant pays a lower rent and fits out the hall itself. Digital Realty sells this product as Powered Base Building.
When does a data center lease start paying rent?
When the lease commences, which means the hall is ready and the tenant takes control of it, not when the contract is signed. Digital Realty's leases signed in the second quarter of 2026 had an average gap of nine months before commencement.
What is a triple-net data center lease?
A lease where the tenant pays rent plus the building's running costs, such as power, maintenance, property tax and insurance. Keppel DC REIT uses triple-net leases for its shell-and-core and single-tenant halls, while its colocation clients pay rent only and the landlord carries the costs.
How long is a data center lease?
It depends on size. Digital Realty's new leases over 1 MW averaged 8.8 years in the second quarter of 2026, against 4.1 years for smaller ones. The largest AI leases can run 15 years, like Applied Digital's 210 MW lease at Delta Forge 2.
Is this a list of stocks to buy or sell?
No. Second Order Explained pages explain how the money moves. They do not give buy or sell calls.
Related: what is an AI data center; hyperscale vs colocation data centers; capex vs opex; what Equinix does; what Digital Core REIT does.
Stack doors
Layer: AI Data Centers. Also: Hyperscalers, Neoclouds, Semiconductors. Markets: US, Singapore, Australia.
Get the Wire — short daily notes when data center leases, power and build dates move.
How we check this
Rents, lease terms, backlogs and megawatts come from Digital Realty’s SEC filing, NEXTDC’s ASX release, Keppel DC REIT’s SGX filing, Applied Digital’s results releases and Singapore’s EDB and IMDA, listed under References. Each was re-checked on 15 Oct 2026. Where we work something out ourselves, such as rent per kilowatt from a total contract value, it is labelled “our arithmetic”. Landlords define their terms differently: Digital Realty reports rent per kilowatt and backlog including its joint-venture partners’ share, and NEXTDC reports contracted megawatts on a pro forma basis. We say which basis each number uses. This page explains how the money moves. It does not give buy or sell calls.
Last reviewed: 15 Oct 2026 · Next review: after Digital Realty's third-quarter 2026 results
Spot an error? Tell us and we will correct it and note the change here.
References
- Digital Realty — Second quarter 2026 earnings release and financial supplement (SEC Form 8-K exhibit, 23 Jul 2026) — bookings, signed-but-not-commenced backlog, signing-to-commencement lag, rent per kW, lease terms, renewals and leasing costs by deal size
- NEXTDC — FY26 results (ASX release, 27 Aug 2026) — contracted, built and billing MW; Forward Order Book and conversion timetable; S4 lease signed but not commenced
- Keppel DC REIT — 1H 2026 results presentation (SGX filing, 23 Jul 2026) — lease types and who pays which costs; lease lengths and share of rent by contract type; power cost recovery
- Applied Digital — Fiscal first quarter 2027 results (7 Oct 2026) — 1.41 GW leased, about $36 billion contracted; 210 MW 15-year lease; base rent vs fit-out vs recoveries
- Applied Digital — Brings an additional 75 MW online at Polaris Forge 1 (2 Oct 2026) — 250 MW operational against 400 MW contracted
- Wikimedia Commons — Inside Google datacenter during construction (2007), photo by erwinboogert, CC BY-SA 3.0 — featured image base photo
- EDB and IMDA — Fact sheet: four data centre proposals selected in DC-CFA2 (21 Aug 2026) — Singapore's 200 MW allocation to four operators