5.65 GW Plugged In, 1.26 GW Used: Who Gets Paid While Malaysia's Data Centres Fill
TNB had 42 data centre projects plugged into Malaysia's grid by June 2026, with room for 5.65 GW. They drew 1,256 MW. On 9 Oct the Budget papers said data centre demand could reach 12.9 GW by 2030. The power company is paid on the booking; halls get paid as they fill.