Seven Tenants Barred: Who Gets Paid While Malaysia’s Data Centres Check Who Rents Their Halls

The US added seven Megaspeed-linked firms to its Entity List on 23 November. A day later Malaysia said all data centre operators will be told not to host, lease space to or serve them. Halls for US clients keep getting paid. Stuck step: the tenant check.

Share
Malaysia data centre tenant ban: a photoreal night view down a cyan-lit data hall where one chained server cage glows amber, under the words seven firms barred
Seven firms barred. · Illustration, not a real site. · sotkn.com

Malaysia has told its data centre owners to stop serving seven firms that the US blacklisted on 23 November. The firms are tied to Megaspeed, a Singapore GPU cloud the US suspects of letting advanced AI chips reach users it has not allowed. One of its Malaysian arms, Speedmatrix, was renting space in Malaysian halls with its own servers and chips. Landlords whose halls are let to US clients keep getting paid, and builders keep winning work. The stuck step is the tenant check: knowing who really stands behind each server cage.

MALAYSIA · AI DATA CENTRES · TENANTS · Data as at 25 Nov 2026 (US rule filed 23 Nov; MITI 13 and 24 Nov; YTL 20 Nov; MIDA 17 Nov; Bursa filings 23–24 Nov) · Next update: when MIDA's notice to operators is public, or Customs reports on the chip re-export check
Affects: AI Data Centers — Markets: Malaysia · Singapore · China · US

Education only, not advice to buy or sell any security. RM is the Malaysian ringgit. The Entity List is a US government list of foreign companies that need a special US licence before anyone can send them US-made goods, software or technology. A colocation data centre rents out space, power, cooling and network links; the tenant brings and owns the servers. For the basics, see colocation explained. Our own sums are labelled.

The numbers that matter this week

Firms added to the US Entity List

7

Three listed under Malaysia, three under Singapore, one under Thailand · 23 Nov 2026

Filed

Malaysian companies among them

2

Speedmatrix and MSFusion, per MITI · PT Megaspeed is not a Malaysian entity, MIDA says

New

US licence policy for the seven

Denial

Licence needed for all items under US export rules · presumption of denial

Rule

Grace period for goods already shipped

30 days

Shipments en route on the filing day may finish by about 23 Dec 2026 (our arithmetic)

Clock

Approved data centre and cloud investment

RM123.5bn

86 projects, Jan–Sep 2026 · 35.2% of all approvals · MIDA

Paid

Who is behind each cage

The check

MIDA notice coming to every operator · landlords must know their tenants

Stuck step

Figures from the US final rule FR Doc. 2026-23999, MITI (13 and 24 Nov 2026) and MIDA (17 Nov 2026). Status chips are Second Order’s read.

On this page: What happened · The seven firms · Why it reaches a hall · What a landlord rents · Who gets paid · Our math · What is stuck? · How big · Other rules · Dates next · What would change this · FAQ

What happened, and why does it matter for Malaysia’s data centres?

Two things happened in two days. On Monday 23 November 2026 the US Commerce Department's Bureau of Industry and Security filed a final rule that adds seven companies to the Entity List. It says they pose a significant risk of diverting advanced computing items to users or uses the US has not allowed. The rule took effect on the day it was filed for public inspection and was printed in the Federal Register on 25 November.

On Tuesday 24 November Malaysia answered. The Ministry of Investment, Trade and Industry (MITI) said two of the seven are Malaysian companies: Speedmatrix Sdn Bhd and MSFusion Sdn Bhd. It said Speedmatrix is a wholly owned subsidiary of Megaspeed International Pte Ltd, which is incorporated in Singapore. Then came the line that matters for anyone who owns a data hall. MITI said the Malaysian Investment Development Authority (MIDA) will send a notice to all data centre operators in Malaysia, telling them about the listing and advising them not to host, lease space to or provide services to any of the seven.

That is new. Until now, the rules from Washington were about chips: who may ship them and who needs a licence to receive them. This notice is about rooms. It asks the landlord, not the chip seller, to turn certain customers away. MITI added that Malaysia “will not allow itself to be used as a channel to circumvent export controls” and that action will be taken against anyone who breaks the law.

It matters because data halls are now one of Malaysia's biggest businesses. MIDA said on 17 November that data centre and cloud projects took RM123.5 billion of approved investment in the first nine months of 2026, across 86 projects. That is 35.2% of everything approved, up from 29.4% a year earlier. Most of the halls sit in Johor, across the causeway from Singapore. For why the region became a hub, see where AI data centers are located.

Who are the seven firms, and where are they?

Chart of the seven firms the US added to its Entity List on 23 November 2026: three listed under Malaysia, three under Singapore and one under Thailand
Who the US listed on 23 November. · Education only.

The US rule groups them by the country where they sit. Every one gets the same treatment: a licence is needed for all items subject to US export rules, and licence requests will be reviewed with a presumption of denial. In plain words, a US supplier, or anyone passing on US-made goods, has to ask first, and should expect a no.

Listed under Malaysia

Speedmatrix Sdn BhdMegaspeed's Malaysian subsidiary, per MITI
MSFusion Sdn BhdMalaysian company, per MITI
PT Megaspeed InternationalNot a Malaysian entity, MIDA says
Addresses in the ruleJohor Bahru, Iskandar Puteri, Kota Tinggi, Klang, Kuala Lumpur

Listed under Singapore

Megaspeed International Pte LtdParent of Speedmatrix, per MITI
Swiftdata Pte LtdSingapore address
Apex Enterprise Solutions (Singapore)Singapore address

Listed under Thailand

Megaspeed (Thailand) Co LtdAlso known as 7Road International
Licence policy, all sevenPresumption of denial

One detail is worth slowing down for. The US lists PT Megaspeed International under Malaysia, with the same Johor and Klang addresses it gives for Speedmatrix. MITI says MIDA's records show PT Megaspeed is not an entity in Malaysia and is not a data centre operator or tenant there. So the two governments already describe one of the seven differently. That gap is small, but it is exactly the kind of gap a landlord's tenant check has to close.

The addresses tell you something too. The Malaysian entries point to offices in Johor Bahru and Iskandar Puteri, an industrial park in Kota Tinggi, a shop address in Klang and a tower in Kuala Lumpur's Tun Razak Exchange. None of them is named as a data centre. That fits what MITI said on 13 November: these firms were tenants inside other people's halls, not hall owners.

Why does a US blacklist reach a Malaysian data hall?

Because of how the business works. MITI's statement of 13 November set it out. Speedmatrix is a tenant at data centres in Malaysia. As a tenant, it brings its own servers and AI chips into the country. Bringing AI chips into Malaysia does not need a permit or a licence. Sending high-performance US AI chips out of Malaysia, or through it, has needed a MITI permit since July 2025, under the Strategic Trade Act 2010.

So the chips can come in freely, sit in a rented cage, and be used from anywhere over the internet. The worry in Washington is the last part: computing power sold to users the US would never have licensed to receive the chips. MITI said it never cleared Megaspeed or Speedmatrix, that its visits to data centres were routine checks and not approvals, and that it is working with the Royal Malaysian Customs Department to find out whether any chips brought in were later sent abroad, and whether that was legal.

There is a tension in Malaysia's own words. On 13 November MITI said Malaysia does not enforce export controls that other countries impose on their own, though companies are expected to take them into account. On 24 November it went a step further and asked every operator to turn the seven away. The notice is worded as advice. It does not, on what MITI has published, create a new law. But it lands on landlords who need US chips for their other tenants, US hyperscalers as customers and Malaysian approvals for their next hall. Few will treat it as optional.

The US rule also has a short grace period. Goods that were already on their way on the filing day, under real orders, may still be delivered under the old rules, as long as the shipment is finished within 30 days. On our arithmetic that runs to about 23 December 2026. After that, anything covered by US export rules needs a licence.

What does a data centre landlord actually rent, and what changes?

A colocation landlord sells four things: floor space, power, cooling and network links. The tenant brings the servers, owns them and runs them. Big tenants take whole halls on long leases; smaller ones rent cages or racks. For the difference, see retail versus wholesale colocation and hyperscale versus colocation.

That split is the core of the landlords' defence. YTL, which runs data centres in Johor, put it plainly on 20 November, after press reports linked it to the Nvidia controversy. It called those reports “completely untrue”. It said its Johor business provides co-location — space, power, cooling and connectivity — to multiple global customers, including hyperscalers from the US, under arrangements that comply with Malaysian law and US trade controls. It said the new US remote-access rule of 19 November does not affect its co-location services, because that rule targets importers of GPUs and companies that sell computing to D:5 customers, the US group of arms-embargoed countries that includes China.

The 24 November notice changes the question a landlord has to answer. It is no longer only “do I import or sell restricted chips?” It is also “is anyone in my building on this list, or owned by someone who is?” A landlord cannot see into a tenant's servers. It can see the lease, the company that signs it, the people who badge in, the power the cage draws and who pays the bill. That is where the work now sits.

It also changes the value of a lease. A long lease to a US cloud giant now carries a second benefit beyond steady rent: it is easy to explain to both governments. A short lease to a GPU reseller with a parent abroad carries a new risk. For how these contracts are written, see data center leases explained.

Who gets paid now?

Infographic: who gets paid in Malaysia after the US Entity List additions, from landlords with US clients and builders to the power company, with the tenant check as the stuck step
Who gets paid / stuck step in Malaysia. · Education only.

Landlords with US-headquartered tenants

Who: Colocation owners in Johor and around Kuala Lumpur whose halls are let to US hyperscalers
Paid: Rent keeps coming. YTL says its US hyperscaler customers and its co-location service are unaffected by the new US rules

Paid

Builders of halls for US clients

Who: Main contractors and subcontractors on new hyperscale halls
Paid: KJTS won RM68 million on 23 November, after RM48 million on 19 November, from Gamuda Engineering for mechanical work on two Port Dickson halls for a US-headquartered tech company. Sum Technology took a RM48 million fit-out award for a Selangor hall on 23 November

Paid

The power company

Who: Tenaga Nasional, which supplies most of Peninsular Malaysia
Paid: Bills whatever load keeps running. A dark cage draws little; a new US hall draws a lot

Paid

Hosts of the seven firms

Who: Whichever operators rented space to Speedmatrix and MSFusion. MITI has not named them
Paid: Lose a paying tenant and must stop service. Racks the tenant owns stay its property, but US-made support and parts now need a licence

Waits

The tenant check

Who: Every landlord in Malaysia, once MIDA's notice arrives
Paid: Needs to know who owns and uses each cage. Until that is routine, every new GPU tenant is slower to sign

Stuck step

The builders' filings say a lot in a few lines. KJTS's Bursa announcement of 23 November describes a second hyperscale data centre in Port Dickson for “a multinational technology company headquartered in the United States”. Its two awards from Gamuda Engineering now add up to RM116 million. The work on the second hall has two milestones: phase 1 substantial completion on 22 April 2028 and phase 2 on 22 July 2028. Sum Technology's award, dated 23 November, covers mechanical, electrical, process utilities and fire fighting work for a hall in Selangor, at about RM48 million. It did not name the customer.

Put next to the blacklist, these filings show where the money is flowing this week. It is going into halls for customers that both governments are comfortable with. It is not flowing to the hosts of the listed firms.

Our arithmetic: what the numbers say

  • Grace period. The rule was filed for public inspection on 23 November and gives goods already shipped 30 days. Our arithmetic: about 23 December 2026.
  • Malaysia's share of the list. Three of seven listings carry a Malaysian destination, about 43%. Only two of those three are Malaysian companies, on MITI's count.
  • Export growth. Data centre service exports went from RM2.8 billion in 2024 to RM11.7 billion in 2025, as the Digital Minister told Parliament. Our arithmetic: about 4.2 times in one year.
  • Average approved project. RM123.5 billion across 86 data centre and cloud projects. Our arithmetic: about RM1.4 billion each. Some are far larger and many smaller.
  • Builders this week. KJTS RM116 million across two Port Dickson halls, plus Sum Technology about RM48 million in Selangor. Our arithmetic: about RM164 million of new fit-out work disclosed in five days, all for halls whose owners or clients the filings either name as US-headquartered or keep confidential.
  • Second Port Dickson hall clock. From the 23 November award to 22 July 2028 is about 20 months on our arithmetic.

None of this tells us how many megawatts the seven firms used. Nobody has published that. For how much power an AI tenant can draw in one hall, see what is an AI data center.

Chart of Malaysia's data centre service exports, up from RM2.8 billion in 2024 to RM11.7 billion in 2025, about 4.2 times
What Malaysia sells from its halls. · Education only.

What is the stuck step? The tenant check

The stuck step is not power this time, and not land or water. It is paperwork about people: knowing who really owns and uses the servers in each cage. Three things make it slow.

  • Ownership chains move. Speedmatrix is owned from Singapore. The US and Malaysia already describe PT Megaspeed differently. A landlord checking a tenant against a list of seven names also has to check parents, sister companies and aliases — the US rule lists four aliases for Megaspeed International alone.
  • The notice is not yet public. MITI said MIDA “will be issuing” it. Until operators see the text, they do not know whether it asks only about the seven, or about anyone linked to them, or what proof MIDA wants.
  • The use is invisible from the hallway. A landlord sees power draw and badges, not who logs in to the servers from abroad. The US concern is remote use. Closing that gap needs the tenant's help, or rules that make tenants report.

Malaysia has already signalled that the last part is coming. Earlier this month ministers said operators will have to report their power use and the AI chips they bring in, and that a data centre bill is being prepared. We covered that in Malaysia's booked-power charge and GPU disclosure. The 24 November notice is the first time that idea has been aimed at named tenants.

Until the check is routine, the cost shows up as time. A new GPU tenant takes longer to sign. A landlord with US hyperscalers in the building will ask more questions of a small GPU cloud next door. That favours big, well-known tenants, and it slows the fastest-growing kind of demand in Johor: GPU clouds that rent their chips onward. For what those firms do, see GPU cloud providers explained.

How big is the business that has to run this check?

Big, and growing faster than almost anything else in the economy. Digital Minister Gobind Singh Deo told the Dewan Rakyat on 24 November that data centre service exports reached RM11.7 billion in 2025, up from RM2.8 billion in 2024. He said 55 centres are already operating and 117 data centre projects have been recorded. He also said approvals look at what a hall does, not only how big it is — whether it produces computing power for AI, and the skilled jobs that come with it.

MIDA's 17 November release adds the pipeline. Of RM350.4 billion of investment approved from January to September 2026, RM123.5 billion was for data centres and cloud, up 44.5% on a year earlier. MIDA named AirTrunk and Princeton Digital Group among approved data centre projects, said Johor has set up a council to screen data centre proposals, and said the national Data Centre Task Force requires at least 30% local content in new halls.

Set against that, two Malaysian names on a US list is a small number. The point is what it asks of the other operators. A market that grew this fast on tenants arriving with their own chips now has to prove who those tenants are. For the power side of the same boom, see Malaysia's reserve margin and data halls and TNB's 9,000 MW plan.

How does this fit the other US rules hitting the region?

It is the third step in a week. On 19 November the US remote-access rule started: a licence for advanced AI chips going to data centres in Malaysia, Singapore, Indonesia, Thailand and Brazil, unless the buyer is headquartered in the US and reports monthly. We traced that in the 90-day licence gate for South-East Asian data centres. For what it means for Singapore's own buyers, see same hall, two rulebooks; for Chinese labs using chips abroad, see China's offshore-chip licence.

The licence rule works on chips. The Entity List works on names. Malaysia's notice works on rooms. Each step moves the check closer to the landlord. A landlord that sells only space, power and cooling may still fall outside the chip rules, as YTL argues. But it cannot fall outside a government notice that names its tenants.

There is a regional angle too. Three of the seven are listed under Singapore, including Megaspeed's parent. Some of the region's biggest operators run halls on both sides of the causeway. For the Singapore side of the map, see the Singapore Markets door; for the companies that own halls across Asia, see AI Data Centers on the Stack.

Which dates test this read?

Calendar of dates that test the read: 19 November US remote-access rule, 23 November Entity List, 24 November MIDA notice, about 23 December end of the shipping grace period, and Port Dickson phases in April and July 2028
Dates that test the read. · Education only.
  • 13 Nov 2026: MITI says Speedmatrix is a tenant, never cleared, and starts a Customs check on re-exports.
  • 19 Nov 2026: US remote-access licence rule for South-East Asian data centres takes effect.
  • 23 Nov 2026: Seven firms added to the Entity List; effective on filing.
  • 24 Nov 2026: MITI says MIDA will notify all operators not to host the seven.
  • About 23 Dec 2026: 30-day grace period for goods already shipped ends (our arithmetic).
  • Not dated: MIDA's notice text, the Customs finding, and the data centre bill.
  • 22 Apr and 22 Jul 2028: Phase 1 and phase 2 completion for KJTS's second Port Dickson hall.

What would change this view?

  • MIDA's notice goes wider than seven names — for example, a duty to check owners and end users of every GPU tenant. The stuck step would get heavier.
  • Customs finds chips were re-exported from a named hall — the landlord, not just the tenant, would be in the story, and lenders would ask harder questions.
  • A hall owner names the seven as former tenants and shows the space re-let — the cost would be short and small.
  • The data centre bill makes GPU and user reporting a tenant duty — the check would become routine, and the bind would ease.
  • More Malaysian names are added to the US list — the check would become a standing cost of every GPU lease.

Practical takeaways

  • The US added seven Megaspeed-linked firms to the Entity List on 23 November 2026, with a presumption of denial
  • Three are listed under Malaysia; MITI says two are Malaysian companies, Speedmatrix and MSFusion
  • MITI says MIDA will tell all data centre operators not to host, lease space to or serve the seven
  • Speedmatrix was a tenant in Malaysian halls with its own servers and chips, MITI said on 13 November
  • Halls for US clients keep getting built: KJTS RM116 million in Port Dickson, Sum Technology RM48 million in Selangor
  • Landlords with US tenants are paid first. Stuck step: the tenant check

FAQ

What did Malaysia tell data centre operators on 24 November 2026?
The Ministry of Investment, Trade and Industry said the Malaysian Investment Development Authority (MIDA) will send a notice to every data centre operator in Malaysia. The notice tells them about seven firms the US added to its Entity List on 23 November, and advises them not to host, lease space to or provide services to any of the seven. Two of the seven, Speedmatrix Sdn Bhd and MSFusion Sdn Bhd, are Malaysian companies.

Which seven firms did the US add to the Entity List?
Under Malaysia: MSFusion Sdn Bhd, PT Megaspeed International and Speedmatrix Sdn Bhd. Under Singapore: Apex Enterprise Solutions (Singapore) Private Limited, Megaspeed International Pte Ltd and Swiftdata Pte Ltd. Under Thailand: Megaspeed (Thailand) Co Ltd. The US says they pose a significant risk of diverting advanced computing items to users or uses it has not allowed. US exporters now need a licence to supply them with anything covered by US export rules, and the US will start from a presumption of denial.

Was Speedmatrix renting space in Malaysian data centres?
Yes. MITI said on 13 November that Speedmatrix is a tenant at data centres in Malaysia and brings its own servers and AI chips into the country. MITI also said it had never cleared Megaspeed or Speedmatrix, and that it is working with Customs to check whether any of those chips were later sent out of Malaysia. MITI did not name the data centres.

Does this hurt every Malaysian data centre?
Not on what has been published. A colocation landlord rents space, power, cooling and connections; the tenant owns the servers. YTL said on 20 November that its Johor halls serve global customers, including US hyperscalers, and that the new US remote-access rule does not touch its co-location business. Builders are still winning work on halls for US clients this week. The cost lands on whoever hosted the seven, and on every landlord that now has to show it knows who is behind each cage.

Who gets paid, and what is the stuck step?
On our map: landlords whose halls are let to US-headquartered clients keep collecting rent; the builders of those halls are paid as the work goes in; and the power company bills whatever load keeps running. The hosts of the seven firms lose a paying tenant. The stuck step is the tenant check: knowing who really owns and uses the servers in each cage, which is now a condition of staying on the right side of both governments.

Is this investment advice?
No. Education only. It maps who gets paid and which step is stuck. It is not a recommendation to buy or sell any security, and we leave out share prices, valuations, broker ratings and price targets on purpose.

Keep reading on the map

How we check this. The list of seven firms, the reason the US gives, the licence rule, the presumption of denial, the 30-day grace period for goods already shipped and the listed Malaysian addresses come from the US Commerce Department's final rule, FR Doc. 2026-23999, filed for public inspection on 23 November 2026. The notice to data centre operators and the status of each Malaysian name come from MITI's statement of 24 November. Speedmatrix's status as a tenant, the chip permit rules and the Customs check come from MITI's statement of 13 November. YTL's position is from its own statement of 20 November. Investment figures are from MIDA's release of 17 November. The two Port Dickson subcontracts and the Selangor award are from KJTS's and Sum Technology's Bursa Malaysia announcements. The export figures are the Digital Minister's words in Parliament as reported by Bernama on 24 November. Anything we worked out ourselves is labelled “our arithmetic”. We do not know which data centres hosted the seven firms, and we do not guess. Share prices, valuations, broker ratings and price targets are left out on purpose. The references we used are listed at the end. Our editorial standards →

Not investment advice. Do your own research.


References

  1. US Department of Commerce, Bureau of Industry and Security, Additions to the Entity List, final rule, FR Doc. 2026-23999 (public inspection copy), filed 23 Nov 2026, published 25 Nov 2026. public-inspection.federalregister.gov — seven entities added under Malaysia, Singapore and Thailand; reason given as significant risk of diverting advanced computing items; licence needed for all items subject to US export rules, reviewed with a presumption of denial; 30-day savings clause for shipments already en route; listed Malaysian addresses.
  2. Ministry of Investment, Trade and Industry (MITI), The Addition of Malaysian Entities to the US Entity List, 24 Nov 2026. miti.gov.my — two Malaysian entities named; Speedmatrix a wholly owned subsidiary of Megaspeed International Pte Ltd; PT Megaspeed International not a Malaysian entity, operator or tenant per MIDA records; MIDA notice to all data centre operators not to host, lease space to or serve the seven.
  3. MITI, Statement on Megaspeed International Pte Ltd and Speedmatrix Sdn Bhd, 13 Nov 2026. miti.gov.my — never cleared Megaspeed or Speedmatrix; Speedmatrix a tenant at Malaysian data centres that brings its own servers and AI chips; no permit to import AI chips; export, re-export, transhipment and transit permits since July 2025 under the Strategic Trade Act 2010; Customs check on re-exports; Malaysia does not enforce other countries' unilateral controls.
  4. YTL Group, YTL Data Centers Unaffected by Latest U.S. Trade Controls, 20 Nov 2026. ytlcommunity.com — co-location (space, power, cooling, connectivity) in Johor for multiple global customers including US hyperscalers; says the remote-access rule targets GPU importers and compute providers to D:5 customers, not co-location.
  5. Malaysian Investment Development Authority (MIDA), Malaysia Records RM350.4 Billion in Approved Investments in the First Nine Months of 2026, 17 Nov 2026. mida.gov.my — data centre and cloud projects RM123.5 billion across 86 projects, up 44.5%, 35.2% of approvals versus 29.4% a year earlier; Johor screening council; 30% local content condition.
  6. KJTS Group Berhad, additional subcontract with Gamuda Engineering for a hyperscale data centre in Port Dickson (Bursa Malaysia announcement), 23 Nov 2026. klsescreener.com — second Port Dickson hyperscale data centre for a multinational technology company headquartered in the United States; RM68 million, RM116 million with the 19 November award; phase completions 22 April and 22 July 2028.
  7. Sum Technology Berhad, Acceptance of Letter of Award for Data Centre Project Valued at RM48 Million (Bursa Malaysia announcement), 24 Nov 2026. klsescreener.com — MEPF subcontract for a data centre in Selangor, letter of award dated 23 November 2026, provisional value about RM48 million.
  8. Bernama, Data Centre Service Exports Surged to RM11.7 Bln in 2025, 24 Nov 2026. bernama.com — Digital Minister Gobind Singh Deo in the Dewan Rakyat: data centre service exports RM11.7 billion in 2025 against RM2.8 billion in 2024; 55 centres operating; 117 projects recorded.