Colocation Explained: How a Colocation Data Center Works and Who Gets Paid

Colocation means putting your own servers in someone else’s data center and paying for space, power and connections. Equinix earned 71% of its third-quarter 2026 revenue from it. Vacancy in big US markets is 1.4%. The stuck step is ready, powered space.

Share
Colocation data center: a caged aisle of server cabinets in a shared data hall, graded navy and teal, with the open cage gate lit in amber
Colocation cages in a shared data hall, photo by Virtuo Doc via Wikimedia Commons (CC BY-SA 4.0); grade and text added by Second Order. Illustrative.

EXPLAINED · Mechanism · Last reviewed: 21 Nov 2026 · Next review: when Equinix and Digital Realty report fourth-quarter 2026 results and CBRE publishes its second-half 2026 data center report

Colocation is when a company puts its own servers in a data center run by someone else, and pays for space, power, cooling and connections there.

In short. What is a colocation data center? It is a shared building where companies put their own servers, and the operator supplies space, power, cooling, security and connections. The customer owns the computers. The operator is paid a monthly charge for space or power, metered electricity, and a fee for each cable to another network. In the third quarter of 2026, colocation was 71% of Equinix’s revenue, by our arithmetic, and vacancy in the main North American markets was 1.4%, by CBRE’s count. Our read: demand is not the problem. The stuck step is ready, powered space. Operators with powered halls and many connected customers get paid first; tenants without signed space wait.

Why an investor cares: colocation is how most companies that do not build their own data centers get space for AI and cloud gear, and the operators are paid only when a cabinet is live and billed. This page sits in our AI Data Centers layer. Our hyperscale vs colocation data center page compares the two models. This page explains how colocation itself works.

What is a colocation data center? The short answer

A colocation data center is a building shared by many customers. Each customer brings its own servers, storage and network gear. The operator supplies everything around them: the floor, the power, backup generators, cooling, security and the cables to the outside world.

The word just means “located together”. Hundreds of companies sit in the same building, and that is the point. Because they are close, they can link to each other with a short cable instead of a long-distance network. That is why the busiest colocation sites are also the places where clouds, carriers and banks meet.

Colocation is not cloud. In cloud, you pay a provider for computing on servers it owns. In colocation, you own the servers. You pay only for the place they sit, the power they draw and the connections they use.

How does colocation work?

It works in sizes. The smallest unit is a cabinet, a locked rack of servers. Several cabinets inside a mesh fence make a cage. A walled room is a suite. A whole hall or building leased to one customer is what the trade calls wholesale colocation.

The customer signs a contract for space and power, moves its servers in, and the operator turns on the circuits. From then on the customer pays every month. Equinix says most of its contracts start with a term of one to five years and then renew automatically a year at a time.

The operator’s job is to keep the power and cooling running at an agreed level, every hour. Our data center tiers page covers how that level is graded, and our PUE explained page covers how much extra power the building itself uses.

Retail vs wholesale colocation, side by side

LineRetail colocationWholesale colocationOwn build (hyperscale campus)
What you getA cabinet, a cage or a small suite in a shared hallA whole hall or building, often several megawattsA campus you own and run
Who owns the serversThe customerThe customerThe owner
Typical buyerBanks, carriers, software firms, AI inference teamsCloud companies, AI labs, large enterprisesThe largest cloud companies
How it is pricedMonthly charge per cabinet or kW, metered power, fee per cross-connectMonthly charge per kW of contracted power, power passed throughNo charge; the owner pays to build and run it
Contract lengthEquinix: mostly one to five years, then yearly renewalLonger; Keppel DC REIT single-tenant buildings have 8.9 years left on averageNot a contract
Where money also comes fromInterconnection: Equinix US$465m in Q3 2026Escalators and renewals: Digital Realty cash renewals up 11.8% in Q3The services sold from the servers
Signing to revenueWeeks to months if space is readyDigital Realty: 17 months on average for Q3 2026 signingsYears: land, power, build

Figures: company filings and releases dated in How we check this. Lines are typical, not rules; many operators sell both retail and wholesale.

How does a colocation provider make money?

Three ways. A monthly charge for space or contracted power. Metered electricity, often passed through at close to cost. And a monthly fee for every cross-connect, the cable that joins one customer to another inside the building.

Equinix is the clearest example because it reports colocation as its own line. In the third quarter of 2026, colocation brought in US$1,826 million of its US$2,571 million revenue. That is 71% of the total, by our arithmetic, and it grew 11.5% on a year earlier.

Equinix, quarter to 30 Sep 2026US$ millionShare or change
Colocation1,82671.0% of revenue; up 11.5% on a year earlier (our arithmetic)
Interconnection46519.0% of recurring revenue; up 10.2% (our arithmetic)
Managed infrastructure108Down from 118 a year earlier
Other recurring43—
Non-recurring (installs, one-offs)129—
Total revenue2,571Up 11.0% (our arithmetic)

Recurring lines add to US$2,442 million. Asia-Pacific colocation was US$403 million, up 9.8% by our arithmetic.

Two numbers show how full and how pricey the space is. Equinix’s 10-Q puts its cabinet utilization at about 78%, the share of its cabinet capacity that is billed. On its call, Equinix said pricing on new deals was up 12% on a year earlier and churn, the share of revenue lost to customers leaving, was 1.7% for the quarter.

The money is also contracted ahead. Equinix reported about US$15.9 billion of revenue still to be recognised under signed contracts, and expects about 65% of it within two years. That is about US$10.3 billion, by our arithmetic. Metered power is left out of that figure, because it depends on how much customers use.

Colocation explained infographic: five steps from land and power to a billed cabinet and cross-connects, with ready powered space as the stuck step
How a colocation hall gets paid. Figures from Equinix, Digital Realty and CBRE, August to October 2026. Graphic by Second Order.

What is interconnection, and why does it matter?

Interconnection is the business of linking customers to each other inside the building. A bank can plug straight into a cloud provider, a carrier or a trading venue in the same hall. Each link is a physical cable or a software-defined connection, and each one carries a monthly fee.

For the operator, this is the sticky part. A customer with dozens of links is slow to move, because moving means rebuilding all of them. Equinix added 6,900 net interconnections in the third quarter and earned US$465 million from them, up 10.2% on a year earlier by our arithmetic. Digital Realty signed a record US$22.2 million of interconnection bookings at its share.

This is why location matters so much. A hall full of connected customers is worth more than an empty shell in a field. Our cloud region and edge data center pages cover why being close to users and clouds matters.

What do colocation customers pay per kilowatt?

Large deals are priced by power, not floor space, because power is the scarce part. The unit is dollars per kilowatt per month of contracted power.

Digital Realty gives a clean example. At its share, its new leases signed in the third quarter of 2026 under 1 MW came to US$129.6 million a year for 41.2 MW. That is about US$262 per kW per month, by our arithmetic. Deals over 1 MW came to US$474.2 million for 143.6 MW, about US$275 per kW per month. The company’s own table shows the same figures.

Bar chart: colocation price per kW per month on Digital Realty new leases in Q3 2026, by region and deal size, from US$129 in EMEA over 1 MW to US$297 in Asia Pacific over 1 MW
Digital Realty new leases, third quarter of 2026, at its share. Regions differ in site mix, so bars are not like for like. Chart by Second Order.

Do not read too much into small versus large here. In this quarter, big Asia Pacific deals priced highest, at about US$297, and big EMEA deals lowest, at about US$129. The mix of sites, power density and terms changes from quarter to quarter. The safer read is that prices are rising: CBRE said asking prices in the main North American markets rose between 4.3% and 8.3% in the first half of 2026, depending on deal size.

How is AI changing colocation?

AI servers draw far more power per rack, and that shows up in the cabinets. On its call, Equinix said customers leaving were using about 5 kW per cabinet on average, while new customers came in at about 7 kW. That is 40% more power per cabinet, by our arithmetic.

The training giants mostly want whole buildings, which pushes them toward wholesale deals or their own campuses. Inference, the work of answering users, wants to sit near users and clouds, which favours connected colocation sites. Digital Realty said its under-1 MW plus interconnection bookings reached a record US$151.8 million at its share in the quarter, about 24% of its total bookings by our arithmetic.

Older halls were not built for this. CBRE notes that the newest GPU servers, at around 100 kW a rack, need closed-loop liquid systems, so power in older air-cooled halls ends up packed into fewer racks, leaving floor space unused. Our how much power an AI data center uses page covers the numbers.

Is there a shortage of colocation space?

In the main North American markets, yes. CBRE put primary-market vacancy at a record low of 1.4% in the first half of 2026, down from 1.6% a year earlier. Northern Virginia, the largest market, was at 0.2%.

Building is at a record too, but most of it is already taken. CBRE counted 7,481.1 MW under construction, with 80.4% preleased. That leaves about 1,466 MW unclaimed, by our arithmetic, which fits CBRE’s note that less than 1,500 MW of future capacity is available, about six months of demand at the current pace.

CBRE says power availability and delivery timelines are now the deciding factors in where deals go and what they cost. Our contracted power and how long it takes to build an AI data center pages cover why that clock is so long.

Where do hyperscalers fit?

Hyperscalers, the largest cloud companies, build their own campuses. They also lease a great deal of capacity from others, because they cannot build fast enough alone. Our hyperscaler explained page covers who they are.

Microsoft shows the scale. Its 10-Q for the quarter to 30 September 2026 lists US$364.6 billion of leases, primarily for datacenters, that were signed but had not yet started. They begin between fiscal 2027 and fiscal 2034, with terms of 1 to 20 years. That is about 2.8 times the US$128.3 billion of lease payments already on its books, by our arithmetic. The filing does not split those leases by landlord, so we cannot say how much is colocation.

On the other side of the table, Digital Realty reported a record US$2.5 billion a year of signed leases that had not started, at full share, and said its third-quarter signings take 17 months on average to begin. Signed is not paid. Our data center lease and remaining performance obligation pages cover how those promises turn into revenue.

Colocation in Singapore and Asia

Singapore is one of the tightest colocation markets in Asia, and its listed data center trusts show how the contracts work. At Keppel DC REIT, fully-fitted colocation brought in 74.4% of lease income at 30 September 2026. Those contracts had a weighted 2.8 years left to run, against 8.9 years for its single-tenant buildings. That is about 3.2 times longer for single tenants, by our arithmetic.

Short contracts cut both ways. They come up for renewal sooner, which lets the owner reset prices when space is tight. Keppel DC REIT reported portfolio occupancy of 93.0% and about 96% of its power capacity contracted. Equinix’s Asia-Pacific colocation revenue was US$403 million in the quarter, up 9.8% on a year earlier by our arithmetic.

For more on the Singapore players, see our pages on what Keppel DC REIT does, what Digital Core REIT does and Equinix SG6 and Singapore’s first data centre tender.

Who gets paid?

Our read: operators with powered, connected halls get paid first. Everyone else is paid by how close they sit to a live, billed cabinet.

  • Operators with ready, powered space. With vacancy near record lows, they set the price. Equinix’s new-deal pricing was up 12% and Digital Realty’s cash renewals were up 11.8% in the third quarter.
  • Operators with dense interconnection. Cross-connect fees grow with every new customer in the building, and they keep customers from leaving. Equinix earned US$465 million from them in one quarter.
  • Landlords with long single-tenant leases. They get steady income for years, but they reset prices less often than retail operators.
  • Waiting: tenants without signed space, and capacity that is signed but not started. A lease signed today at Digital Realty takes 17 months on average to start paying. Until then it is backlog, not revenue.

Where is the stuck step?

Our read: ready, powered space. Demand is not the problem. CBRE’s numbers show buyers taking capacity as fast as it is finished, and most of what is under construction is already leased.

The slow part is turning land and a grid promise into a hall with live circuits. Equinix’s own 10-Q says that in certain markets, growth may increasingly depend on timely delivery of new capacity and the power infrastructure behind it. Equinix plans nearly 40% more cabinets for delivery in 2026 than it first expected, which shows both the demand and the push to build.

The clocks

  • End of 2026. New contracts at Keppel DC REIT’s Gore Hill Data Centre in Sydney start, which it says will more than double that site’s revenue.
  • Early 2027. Equinix and Digital Realty report fourth-quarter 2026 results. Watch utilization, new-deal pricing and the signed-not-started backlog.
  • Early 2027. CBRE’s next North America report shows whether vacancy is still near 1.4%.
  • About 17 months after signing. Digital Realty’s third-quarter 2026 leases start, on average, around the end of 2027 or early 2028.
  • Second half of 2027. Keppel DC Singapore 8 works are due to finish.
  • Fiscal 2027 to fiscal 2034. Microsoft’s US$364.6 billion of signed datacenter leases start.

What would change the view?

  • Supply catches up. If new halls arrive faster than buyers take them, vacancy rises and pricing power fades.
  • Churn rises. If Equinix’s churn moves well above 1.7%, or new-deal pricing slows, the tight-market read weakens.
  • Backlog slips. If signed leases start later than planned, or customers walk away before they start, the revenue arrives later or not at all.
  • Hyperscalers build more themselves. If the largest buyers shift from leasing to owning, wholesale demand falls.
  • Power gets easier. Faster grid connections would loosen the stuck step and move the bottleneck elsewhere.

Common misconceptions

  • People assume colocation is the same as cloud. Actually, in colocation the customer owns the servers and pays only for space, power and connections.
  • People assume colocation is priced by floor space. Actually, large deals are priced per kilowatt of power a month, because power is the scarce part.
  • People assume a signed lease is revenue. Actually, Digital Realty’s new leases take 17 months on average to start. Until then, they earn nothing.
  • People assume hyperscalers only build their own data centers. Actually, Microsoft alone has US$364.6 billion of signed datacenter leases that have not started yet.

FAQ

What is a colocation data center?
A colocation data center is a building where many companies put their own servers and network gear, and the operator supplies the space, power, cooling, security and connections. The customer owns the computers. The operator owns or leases the building and charges for what each customer uses.

How does colocation pricing work?
Customers usually pay a monthly charge for space or contracted power, plus metered electricity, plus a monthly fee for each cross-connect to another network. Big deals are priced per kilowatt per month. Digital Realty’s new leases in the third quarter of 2026 worked out to about US$262 per kW per month for deals under 1 MW and US$275 for deals over 1 MW, by our arithmetic from its release.

What is the difference between retail and wholesale colocation?
Retail colocation sells cabinets or cages to many smaller customers on shorter contracts, with lots of connections between them. Wholesale colocation leases whole halls or buildings, often several megawatts, to one large customer on longer terms. Keppel DC REIT’s colocation contracts have a weighted 2.8 years left, against 8.9 years for its single-tenant buildings.

What is a cross-connect in colocation?
A cross-connect is a physical cable inside the data center that joins one customer’s equipment directly to another’s, such as a cloud provider or a network carrier. Operators charge a monthly fee for each one. Equinix added 6,900 net interconnections in the third quarter of 2026.

Why is colocation space so hard to find in 2026?
Because power-ready space is being taken as fast as it is built. CBRE put vacancy in the main North American markets at a record low of 1.4% in the first half of 2026, and said 80.4% of the capacity under construction was already leased.

Do hyperscalers use colocation?
Yes. Large cloud companies build their own campuses but also lease capacity from data center operators. Microsoft reported US$364.6 billion of leases, mainly for datacenters, that had been signed but not yet started as of 30 September 2026. Its filing does not say which landlords those leases are with.

Is colocation the same as cloud?
No. In cloud, you pay for computing from a provider that owns the servers. In colocation, you own the servers and pay only for the place they sit, the power they draw and the connections they use.

How long are colocation contracts?
Retail contracts are short. Equinix says most of its contracts start at one to five years and then renew a year at a time. Wholesale leases for large halls run longer, and Microsoft’s filing shows lease terms of 1 to 20 years for the capacity it has signed.

Related: hyperscale vs colocation data center; data center lease explained; what is an AI data center; where AI data centers are located; who builds AI data centers; cloud egress explained.

Stack doors

Layer: AI Data Centers. Players: Equinix and Digital Realty. Markets: Equinix’s third-quarter cabinets, Digital Realty’s signed but not billed and Keppel DC REIT’s third-quarter renewals. Analysis: Keppel DC REIT’s rebuild and the stuck step.

Get the Wire — short daily notes on where AI computing gets built and who pays for it.

Not investment advice. Do your own research.

How we check this

Equinix’s revenue lines, bookings, interconnection adds and capacity plan come from its third-quarter results release of 28 October 2026. Its cabinet utilization, contract terms, remaining performance obligations and the line on capacity and power delivery come from its Form 10-Q for the quarter to 30 September 2026, filed the same day. Equinix’s pricing on new deals, churn, cabinet densities and net cabinets billed come from its earnings call, which we read in a published transcript and quote as call remarks, not filed figures. Digital Realty’s bookings, megawatts, signing-to-start lag, backlog and renewal figures come from its third-quarter 2026 results release, filed as Exhibit 99.1 to its Form 8-K of 29 October 2026. Vacancy, construction, preleasing and price changes come from CBRE’s North America Data Center Trends H1 2026, published 27 August 2026; these are asking prices, not signed deals. Keppel DC REIT’s contract mix, lease expiry, occupancy and power figures come from its 3Q 2026 operational update of 23 October 2026. Microsoft’s lease figures come from its Form 10-Q for the quarter to 30 September 2026, filed 28 October 2026; that filing does not name its landlords. Shares, growth rates, prices per kilowatt and ratios are our arithmetic, checked in code and labelled on the page. Who gets paid and the stuck step are our read. The featured image is a CC BY-SA photograph of colocation cages in a data hall, graded by us; it does not show any company named here. This page explains how a business works. It does not rate companies as investments or give buy or sell calls. Not investment advice. Do your own research.

Last reviewed: 21 Nov 2026 · Next review: when Equinix and Digital Realty report fourth-quarter 2026 results and CBRE publishes its second-half 2026 data center report

Spot an error? Tell us and we will correct it and note the change here.

Our editorial standards →

References

  1. Equinix — Equinix Reports Third-Quarter Results and Raises 2026 Guidance (28 Oct 2026) — Revenue US$2.571bn; colocation revenue US$1.826bn and interconnection US$465m by service line; annualized gross bookings US$533m; 6,900 net interconnections added; nearly 40% more cabinets planned for 2026 delivery; full-year guidance
  2. Equinix — Form 10-Q for the quarter ended 30 September 2026 (filed 28 Oct 2026) — Cabinet utilization about 78%; contracts of one to five years that renew yearly; remaining performance obligations about US$15.9bn, about 65% within two years; metered power excluded; growth depends on timely delivery of new capacity and power
  3. Investing.com — Equinix Q3 2026 earnings call transcript (28 Oct 2026) — Call remarks: pricing on new deals up 12% year on year; churn 1.7%; customers leaving at about 5 kW per cabinet and joining at about 7 kW; net cabinets billed up 5,700; interconnection about 19% of revenue
  4. Digital Realty — Third Quarter 2026 results release, Form 8-K Exhibit 99.1 (29 Oct 2026) — Record bookings US$855m at 100% share, US$627m at its share; 0–1 MW US$129.6m at 41.2 MW and over 1 MW US$474.2m at 143.6 MW; 17-month signing-to-start lag; US$2.5bn signed-not-commenced backlog; 11.8% cash renewal increase
  5. CBRE Research — North America Data Center Trends H1 2026 (27 Aug 2026) — Primary-market vacancy 1.4%; Northern Virginia 0.2%; 7,481.1 MW under construction, 80.4% preleased; under 1,500 MW available, about six months of demand; asking prices up 4.3% to 8.3% by size
  6. Keppel DC REIT — 3Q 2026 Operational Updates presentation (23 Oct 2026) — Fully-fitted colocation 74.4% of lease income with a 2.8-year weighted lease expiry versus 8.9 years for single-tenant; occupancy 93.0%; contracted power about 96%; Keppel DC Singapore 8 works due 2H 2027
  7. Microsoft — Form 10-Q for the quarter ended 30 September 2026 (filed 28 Oct 2026) — Leases not yet commenced, primarily for datacenters, of US$364.6bn, starting between fiscal 2027 and fiscal 2034 with terms of 1 to 20 years; operating and finance lease payments already on the books

Sean