Keppel Builds, kt cloud Rents: Who Gets Paid While Korea’s 60 MW Ansan 2 Data Centre Waits for Customers

Keppel's data centre fund will build a 60 MW AI hall in Ansan near Seoul, and kt cloud has signed to rent all of it, ready by 2030. Builders are paid first. The fund is paid when the hall opens. kt cloud is paid only when its own customers move in.

Share
Korea AI data centre master lease: a photoreal blue-hour view of an eight-storey data centre under construction with a tower crane near Seoul, one empty floor lit amber, and a finished data h
One builds, one rents. · Illustration, not the real site. · sotkn.com

A fund run by Singapore's Keppel will build the hall, and a Korean cloud company will rent all of it. On 26 November Keppel said its third data centre fund has signed kt cloud as master tenant for 100% of a 60 MW AI data centre in Ansan, near Seoul, due to be ready by 2030. The builders get paid first. The fund gets rent when the hall opens. kt cloud gets paid last, when its own customers move in, and none is named yet. That is the stuck step.

KOREA · AI DATA CENTRES · LEASES · Data as at 27 Nov 2026 (Keppel and kt cloud releases 26 Nov; Keppel site purchase 9 Jun; CJ DART filing 21 Oct; kt cloud Ansan 1 release 22 Oct; KT 3Q26 release 10 Nov) · Next update: when kt cloud names a customer for its Ansan campus, or the rent or lease length is disclosed
Affects: AI Data Centers — Markets: Korea · Singapore · Taiwan

Education only, not advice to buy or sell any security. KRW is the Korean won; S$ is the Singapore dollar. MW measures how much power the computers in a data centre can draw. A master tenant rents a whole building and sells the space inside to its own customers. For the basics, see what is an AI data center. Our own sums are labelled.

The numbers that matter this week

Ansan 2 power, all rented by kt cloud

60 MW

Master lease for 100% of capacity · Keppel, 26 Nov 2026

Signed

kt cloud's Ansan campus, two sites

110 MW

50 MW owned (Ansan 1) + 60 MW leased (Ansan 2) · kt cloud, 26 Nov 2026

Planned

Ansan 1 build contract, paid by kt cloud

KRW 315.0bn

Billed every two months, no advance, 5% at completion · CJ Logistics DART, 21 Oct 2026

Paid now

Keppel fund's share of Ansan 2

About 73%

Rest held by Shinyoung, NH Securities, Hyundai E&C · Keppel, 9 Jun 2026

Owner

Ready for service

By 2030

Construction from Nov 2026 · Ansan 1 due 2029

Waiting

kt cloud's own customers for Ansan

Not named

Neither release names an end customer · rent and lease length not disclosed

Stuck step

Figures from Keppel (26 Nov and 9 Jun 2026), kt cloud (26 Nov and 22 Oct 2026) and CJ Logistics' DART filing (21 Oct 2026). Status chips are Second Order’s read.

On this page: What happened · What kt cloud signed · Ansan 1 vs Ansan 2 · How the builder is paid · Who gets paid · Our math · What is stuck? · Why rent near Seoul · The wider map · Dates next · What would change this · FAQ

What happened, and why does it matter?

On Thursday 26 November 2026 Keppel, the Singapore-listed asset manager, said its private fund Keppel Data Centre Fund III has secured kt cloud as master tenant for the 60 MW data centre the fund is building in Ansan. kt cloud committed to take 100% of the capacity. Ansan is a city south-west of Seoul, inside what Korea calls the Seoul metropolitan area. The same morning kt cloud, the data centre and cloud arm of KT, put out its own release in Korean calling the site Ansan 2.

The building has two basement levels and eight floors above ground, with about 52,622 square metres of floor area. Keppel said construction was expected to start in November 2026 and that the hall is targeted to be ready for service by 2030. It said the site already has its construction permits and its power approvals, and will be built to a Tier III-equivalent standard, with liquid cooling for dense GPU servers.

It matters for two reasons. First, power near Seoul is scarce, and this site already has 60 MW of it approved. Second, it shows a new way Korea's telcos are adding AI capacity. kt cloud is not paying to build this hall. A foreign fund is. kt cloud signs the lease, and the fund carries the construction bill until the doors open.

That moves the risk around. The fund now has a tenant for the whole building before the first floor is poured. kt cloud has the space, but it still has to find the customers who will pay to use it. For how a lease that has been signed but not started works, see leases not yet commenced, explained.

What exactly did kt cloud sign?

A master lease. That means kt cloud rents the whole building from the owner and then sells the space, power and services inside it to its own customers. The owner deals with one tenant. The tenant deals with many customers.

The building

SiteAnsan, Seoul metropolitan area
Power60 MW secured gross power
Size2 basements, 8 floors, about 52,622 sqm
StandardTier III-equivalent, liquid cooling

The owners

Keppel Data Centre Fund IIIAbout 73% effective stake
Korean co-investorsShinyoung, NH Securities, Hyundai E&C (27%)
Fund size, 30 Sep 2026About S$5.1bn under management
Site boughtJune 2026

The tenant and timing

Master tenantkt cloud, 100% of capacity
Construction startNovember 2026
Ready for serviceBy 2030
Rent, lease lengthNot disclosed

The two releases use slightly different words, and the difference is worth noticing. Keppel's English release says kt cloud is “committing to take up 100%” of the capacity. kt cloud's Korean release says it is pursuing Ansan 2 as a supply base and is taking part as a partner in Keppel's first Korean data centre project. Both describe the same deal. Neither gives the rent, the length of the lease, or when rent starts.

Keppel added a line that tells you how big this is for Keppel itself. It said the development is not expected to have any material impact on Keppel's net tangible assets per share or earnings per share this financial year. For Keppel, Ansan 2 is a fund investment. The fund's investors carry most of the money.

The Korean co-investors are a mix that fits a build like this: a developer, a securities firm and one of Korea's biggest construction companies. Keppel's June release did not say whether Hyundai E&C will also build Ansan 2, and the November releases do not name a builder. We do not assume it. For the usual cast on a project like this, see who builds AI data centers.

How is Ansan 2 different from kt cloud's Ansan 1?

Chart of kt cloud's Ansan campus: Ansan 1 at 50 MW owned, Ansan 2 at 60 MW leased from a Keppel fund, 110 MW together, against KT's goal of about 1 GW of AI data centres by 2031
Two Ansan halls, two ways to pay. · Education only.

kt cloud now has two halls in Ansan, about 2.5 km apart, paid for in two different ways.

Ansan 1 is kt cloud's own. It broke ground on 22 October 2026. kt cloud's release describes a 50 MW AI data centre with two basements and nine floors, about 36,878 square metres, due to be finished in 2029, with every server room ready for liquid cooling and floors built to carry heavy next-generation GPU racks. Yonhap, reporting the builder's announcement, said the 50 MW of incoming power supports 32 MW of IT load, and that kt cloud plans to use the building itself.

Ansan 2 is the Keppel fund's. It is a bit bigger at 60 MW and about 52,622 square metres, and is due by 2030 rather than 2029. kt cloud rents it. kt cloud said it will link the two sites so a customer can start in one and grow into the other, and called the pair a 110 MW AI data centre campus.

Ansan 1 (owned)

Ownerkt cloud
Power / IT load50 MW / 32 MW
Floor areaAbout 36,878 sqm
Ready2029

Ansan 2 (leased)

OwnerKeppel-led fund (about 73%)
Power60 MW secured gross
Floor areaAbout 52,622 sqm
ReadyBy 2030

Why does this matter for KT? In its third-quarter release on 10 November, KT listed six AI data centre sites to open by 2029: Bucheon in 2027; Gaebong, Gunsan and Yongin in 2028; and Ansan in 2029. On our reading, that Ansan is Ansan 1, which is due in 2029. The same slide said decisions on more sites were in progress. Ansan 2 is one of them, and it arrives as a lease rather than a build. For our earlier read of KT's site list, see Korea's AI data centres: tenants first, and for the group as a whole, see what KT does.

How does the builder get paid?

Chart of how the builder is paid on kt cloud's Ansan 1: KRW 315 billion contract, no advance, about KRW 299 billion billed every two months during works and about KRW 16 billion on completion
How the builder of Ansan 1 gets paid. · Education only.

We can see this clearly for Ansan 1, because the builder had to file it. On 21 October 2026 CJ Logistics, whose construction division won the job, told Korea's DART disclosure system it had signed a KRW 315.0 billion contract with kt cloud for the Ansan AI data centre. That figure excludes VAT. CJ said it equals 2.56% of its 2025 revenue.

The payment terms are the useful part. There is no down payment and no advance. CJ bills every two months as the work progresses. A completion payment of 5% is held back until the end. The contract runs from 21 October 2026 to 15 December 2029. Yonhap reported about 38 months of works, with CJ handling civil work, the building, landscaping and mechanical systems, and commissioning up to the stage where each piece of equipment is checked to start and run properly.

So on Ansan 1 kt cloud pays its builder steadily from now until the end of 2029, before it earns anything from the hall. That is what owning a data centre looks like in cash terms. For how big these bills usually get, see how much it costs to build an AI data center; for how long each stage takes, see how long it takes to build one.

At Ansan 2 that bill sits with the fund. Neither Keppel nor kt cloud has published the build cost, the builder or the payment terms. What we can say is that the owner of Ansan 2, not kt cloud, will be the one writing cheques to builders between now and 2030. kt cloud's cash goes out later, as rent, once there is a hall to rent.

Who gets paid, and when?

Follow the money in the order it moves. The early money goes to people who pour concrete and install equipment. The late money goes to whoever has to fill the floors.

Builders and equipment suppliers

Who: CJ Logistics at Ansan 1; the Ansan 2 builder is not named; electrical, cooling and fit-out suppliers at both.
Paid: First. At Ansan 1, every two months from October 2026 by progress, with 5% at completion. At Ansan 2, by the fund, from the start of works.

Paid now

The power grid

Who: Korea's power utility, which approved 60 MW for Ansan 2 and supplies Ansan 1.
Paid: Once servers run and draw power. The approval itself is the scarce thing near Seoul.

Approved

The owner: the Keppel-led fund

Who: Keppel Data Centre Fund III (about 73%) with Shinyoung, NH Securities and Hyundai E&C.
Paid: Rent from kt cloud once the hall is ready, by 2030. Terms not disclosed. Keppel says no material effect on its own earnings this year.

Paid later

The master tenant: kt cloud

Who: Renting 100% of Ansan 2 and building Ansan 1 itself.
Paid: Last. Only when its own customers move servers in and pay for space, power or GPU time.

Waiting
Infographic: who gets paid around kt cloud's Ansan 2, from builders and the power approval to the Keppel-led fund and kt cloud, with kt cloud's own customers as the stuck step
Who gets paid / stuck step at Ansan 2. · Education only.

The order is the point. The fund has locked in a tenant, so its risk is now mostly about building on time and on budget. kt cloud has locked in 60 MW of scarce power near Seoul, so its risk is now about selling it. For how a hall owner and a hall renter split that risk, see data center leases explained and finance lease versus operating lease.

Our arithmetic

These are our own sums from the published figures. They are labelled so you can check them. They are not company guidance.

  • Campus size: 50 MW + 60 MW = 110 MW, matching kt cloud's own figure. Ansan 2 is 60 / 110 = about 55% of the campus, so more than half of kt cloud's Ansan power will be rented, not owned (our arithmetic).
  • Against the 1 GW goal: 110 MW is about 11% of the 1 GW of AI data centres KT Group aims to supply by 2031 (our arithmetic).
  • Keppel fund's look-through: about 73% of 60 MW = about 44 MW for Keppel Data Centre Fund III; about 16 MW for the three Korean co-investors (our arithmetic, assuming the stake stays as announced in June).
  • Builder's bills at Ansan 1: 5% of KRW 315.0bn = about KRW 15.8bn held to completion, so about KRW 299bn is billed during the works. Over about 38 months that averages about KRW 7.9bn a month, or about KRW 15.8bn per two-month bill if spread evenly. Real bills follow progress, so they will not be even (our arithmetic).
  • Contract per MW of IT load: KRW 315.0bn / 32 MW = about KRW 9.8bn per MW of IT load at Ansan 1. This covers CJ's scope only, not the land, servers or every piece of electrical gear, so it is not the full cost of the hall (our arithmetic).
  • IT load as a share of power: 32 / 50 = 64% at Ansan 1. The rest of the power goes to cooling, backup and losses. Ansan 2's IT load is not published; we do not apply Ansan 1's ratio to it (our arithmetic).
  • Floor area per MW: about 52,622 / 60 = about 877 sqm per MW at Ansan 2, against about 36,878 / 50 = about 738 sqm per MW at Ansan 1 (our arithmetic).
  • Fund growth: Keppel Data Centre Fund III went from about S$2.7bn under management at end-2025 to about S$5.1bn at 30 September 2026, roughly 1.9 times (our arithmetic).
  • Time to open: from construction start in November 2026 to the end of 2030 is up to about 49 months; from the June 2026 site purchase it is up to about four and a half years (our arithmetic).

What is the stuck step?

Not power, and not permits. Keppel said Ansan 2 already has both. Not the owner's tenant either: the fund signed one for the whole building. The step that is still open is one level down. kt cloud has to sign its own customers.

Neither release names a customer for Ansan 1 or Ansan 2. kt cloud's chief executive, Kim Bong-gyun, said what matters is supplying infrastructure on time in response to customer demand, and that kt cloud will keep growing its data centre business in line with actual customer needs. That is a statement of intent, not a signed contract. So, across its two Ansan halls, kt cloud has taken on 110 MW, 50 MW owned and 60 MW rented, with no named end user yet.

There are reasons kt cloud can take that bet. Keppel's release quotes CBRE Research figures for Greater Seoul: absorption of 99.7% in 2024 and 99.4% in 2025. In plain words, almost all new space that came to market in those years was taken. Keppel's June release quoted JLL figures showing Seoul-area vacancy of 1.4% and said the whole 2025–2027 supply pipeline was already pre-leased. If that holds, filling a new hall near Seoul in 2029 and 2030 should not be hard. For the difference between selling a whole hall to one big buyer and selling racks to many, see retail versus wholesale colocation.

But those are market figures for halls already built or about to open. Ansan 2 opens by 2030, four years out. AI demand, chip designs and power prices can all move in that time. Until kt cloud names who will use the floors, the rent it owes the fund is a cost with no matching income on paper. For how a cloud company sells GPU time once a hall is full, see GPU-as-a-service explained.

Why rent near Seoul instead of building?

Because the hard part near Seoul is not the building. It is the power connection. A company with land, permits and approved power already in place is selling something rare.

Keppel's June release spelled out why. It said new data centre supply in the Seoul area is limited because recent rules restrict power supply applications for projects above 10 MW, which has cut the development pipeline. It put new Seoul-area data centre power demand at about 2.3 GW through 2030. We covered how Korea's power company sorts these requests in Korea's AI data centre grid queue, and the newer review for sites of 50 MW or less in this Wire.

Seen that way, the lease is kt cloud buying time and power rather than land and concrete. It gets 60 MW in the Seoul area without spending its own capital on another building, and without waiting in a power queue. The fund gets a strong local tenant for a site whose main value is that approved power. Outside Seoul, our 13 November read found KT saying it would build where it already had tenants. Near Seoul the logic flips: lock up the power first, find the customers after. For more on why sites cluster where power is, see where AI data centers are located and contracted power explained.

The contrast with Korea's other big projects is useful. At Wonju, a developer with a contract signed for its electrical work is still waiting on its project-finance loan before an advance can flow; see Wonju's AI data centre and its bank loan. At Ansan 2 the money question is already settled: an experienced foreign fund owns the site and has a tenant. The open question has moved to demand.

What does this say about Keppel and the wider map?

Keppel is better known to Singapore investors for its listed trust, Keppel DC REIT, which owns finished halls and collects rent; see what Keppel DC REIT does. Ansan 2 is not in that trust. It sits in a private fund that buys sites, builds and leases them. Keppel said the fund has now made three investments, and the group had 39 data centres with more than 800 MW of gross power capacity at the end of 2025, counting projects under development.

The model is familiar across Asia. Owners with cheap long-term money build the shell and the power; operators rent and sell the space. In Taiwan, Taiwan Mobile grew its AI data centre business through leases rather than its own capex; see Taiwan's telcos: rent the hall, wait for MW. In Singapore, the first hall from the 2023 government data centre tender, Equinix's SG6, opened its first phase in November; see Equinix SG6. For the listed owners and operators across the region, see Digital Core REIT, Equinix, Digital Realty and NEXTDC. The full layer is on AI Data Centers on the Stack.

One more point for KT watchers. Leasing keeps the building off kt cloud's own construction budget, but a long lease is still a commitment. Under the accounting rules most listed Korean companies use, a long lease shows up as a right-of-use asset with a matching lease liability once it starts. When Ansan 2 opens, it would normally land on the balance sheet that way rather than as capex. For how that looks, see finance lease versus operating lease; for how data centre owners raise the money, see data center financing explained; and for our read on what KT's share price assumes about its halls, see the KT Analysis.

Which dates test this read?

Calendar of dates that test the read: Keppel buys the Ansan site June 2026, CJ contract October, Ansan 1 starts October, Ansan 2 master lease November, Ansan 1 due December 2029, Ansan 2 ready by 2030, KT 1 GW by 2031
Dates that test the read. · Education only.
  • 9 Jun 2026: Keppel Data Centre Fund III secures the Ansan site, with permits and power approvals in hand.
  • 21 Oct 2026: CJ Logistics files its KRW 315.0bn contract to build kt cloud's Ansan 1.
  • 22 Oct 2026: kt cloud breaks ground on Ansan 1 (50 MW, due 2029).
  • 10 Nov 2026: KT's third-quarter release lists six sites by 2029 and says more site decisions are in progress.
  • 26 Nov 2026: Keppel signs kt cloud as master tenant for all 60 MW of Ansan 2; construction due to start this month.
  • Early 2027: KT's fourth-quarter results — the first chance to see whether the lease or any Ansan customer is mentioned.
  • 15 Dec 2029: End of CJ's Ansan 1 contract term; the 5% completion payment falls due on completion.
  • By 2030: Ansan 2 ready for service; rent to the fund would start around then.
  • 2031: KT Group's goal of 1 GW or more of AI data centres.

What would change this view?

  • kt cloud names a large customer for Ansan 1 or Ansan 2 — the stuck step would move to the build schedule and the 2030 date.
  • The rent, lease length or start date is disclosed — we could put a first number on what kt cloud owes and what the fund earns.
  • The Ansan 2 builder and contract are filed — we could see the fund's own cash bill and its timing.
  • The 2030 date moves — a slip would push the fund's rent and kt cloud's sales out together.
  • Seoul-area absorption falls well below the 99% range — filling the floors would get harder, and the master lease would look riskier for kt cloud.

Practical takeaways

  • Keppel's third data centre fund signed kt cloud for 100% of a 60 MW AI data centre in Ansan on 26 November 2026
  • Construction was due to start in November; permits and power are in hand; the hall should be ready by 2030
  • kt cloud owns the nearby 50 MW Ansan 1 and pays its builder every two months under a KRW 315.0bn contract
  • At Ansan 2 the fund pays to build and kt cloud pays rent later; rent and lease length are not disclosed
  • Near Seoul the scarce thing is approved power, which is why leasing it now makes sense for kt cloud
  • Paid first: builders. Paid later: the fund. Stuck step: kt cloud's own customers

FAQ

What did Keppel and kt cloud announce on 26 November 2026?
Keppel said its private fund, Keppel Data Centre Fund III, has signed kt cloud as master tenant for a 60 MW AI-ready data centre it is building in Ansan, inside the Seoul metropolitan area. kt cloud committed to take 100% of the capacity. Construction was due to start in November 2026, and the building is targeted to be ready for service by 2030. kt cloud calls the site Ansan 2 and will run it with its own 50 MW Ansan 1 site, about 2.5 km away, as one 110 MW campus.

What is a master tenant?
A master tenant rents a whole building from the owner and then sells the space, power and services inside it to its own customers. Here the Keppel fund owns and builds the hall, and kt cloud rents all of it. The fund's income depends on kt cloud paying rent. kt cloud's income depends on finding the end customers who fill the floors.

Who owns the Ansan 2 data centre?
When Keppel bought the site in June 2026, it said Keppel Data Centre Fund III would hold about 73% of the company that owns the land. The other 27% is held by three Korean firms: developer Shinyoung, NH Securities and Hyundai E&C. Keppel runs the fund as an asset manager. Keppel said the deal will not have a material impact on its own earnings per share this year.

How is Ansan 2 different from kt cloud's Ansan 1?
kt cloud owns Ansan 1 and is paying to build it. Builder CJ Logistics filed a KRW 315.0 billion contract for it on 21 October 2026, billed every two months as work progresses, with no advance and 5% held until completion in December 2029. Ansan 1 has 50 MW of incoming power and 32 MW of IT load. At Ansan 2 the Keppel-led fund pays for the building, and kt cloud pays rent once the hall is ready. Neither company published the rent.

Who gets paid, and what is the stuck step?
On our map: builders are paid first, as the work is done. The fund and its investors are paid rent from when the hall is ready, by 2030. kt cloud is paid last, when its own customers move servers in and pay. Neither release names an end customer for Ansan 1 or Ansan 2. That is the stuck step: the customers behind the master lease.

Is this investment advice?
No. Education only. It maps who gets paid and which step is stuck. It is not a recommendation to buy or sell any security, and we leave out share prices, valuations, broker ratings and price targets on purpose.

Keep reading on the map

How we check this. The master lease, the 60 MW size, the construction and ready-for-service dates, the permits and power approval, the building size, the Seoul-area absorption figures (which Keppel credits to CBRE Research) and the fund size come from Keppel's release of 26 November 2026. The 110 MW campus, the 2.5 km distance and the 1 GW goal come from kt cloud's Korean release of the same day. The 73% stake, the three Korean co-investors, the 10 MW power-application curbs and the vacancy figure (which Keppel credits to JLL) come from Keppel's release of 9 June 2026. Ansan 1's size and completion year come from kt cloud's release of 22 October. The builder's contract value, dates and payment terms come from CJ Logistics' filing on Korea's DART disclosure system of 21 October; the 32 MW IT load and the 38-month build are as reported by Yonhap the next day. KT's site list and kt cloud's revenue come from KT's third-quarter release filed with the US SEC. Anything we worked out ourselves is labelled “our arithmetic”. We do not know the rent, the lease length, the Ansan 2 build cost or the builder for Ansan 2, and we do not guess. Share prices, valuations, broker ratings and price targets are left out on purpose. The references we used are listed at the end. Our editorial standards →

Not investment advice. Do your own research.


References

  1. Keppel Ltd., Keppel Data Centre Fund III secures kt cloud as master tenant for 60 MW South Korea data centre (media release), 26 Nov 2026. keppel.com — kt cloud commits to 100% of the 60 MW; construction from Nov 2026, ready by 2030; permits and power approvals secured; floors and floor area; Greater Seoul absorption 99.7% and 99.4% (CBRE, Jul 2026); KDCF III FUM about S$5.1bn at 30 Sep 2026; no material impact on Keppel's NTA or EPS.
  2. kt cloud, kt cloud pursues Ansan 2 AIDC, expanding its Seoul-area base (press release, Korean), 26 Nov 2026. ktcloud.com — 60 MW Ansan 2 linked with Ansan 1 for a 110 MW campus about 2.5 km apart; partner in Keppel's first Korean data centre project; start Nov 2026, service within 2030; KT Group 1 GW by 2031.
  3. Keppel Ltd., Keppel enters South Korea's fast growing data centre market (media release), 9 Jun 2026. keppel.com — KDCF III takes about 73% of the land-owning company; Shinyoung, NH Securities and Hyundai E&C hold 27%; Seoul-area demand about 2.3 GW to 2030; curbs on power applications above 10 MW; vacancy 1.4% (JLL, Mar 2026); 2025-2027 pipeline fully pre-leased.
  4. kt cloud, kt cloud breaks ground on its own 50 MW Ansan AI data centre (press release, Korean), 22 Oct 2026. ktcloud.com — Ansan 1: owned by kt cloud, 50 MW, 36,878 sqm, two basements and nine floors, completion 2029, server rooms ready for liquid cooling.
  5. CJ Logistics (CJ대한통운), Single sales and supply contract: kt cloud Ansan AIDC new build (DART filing 20261021800299), 21 Oct 2026. dart.fss.or.kr — contract value KRW 315.0bn excluding VAT, 2.56% of 2025 revenue; 21 Oct 2026 to 15 Dec 2029; no down payment or advance; billed every two months by progress; 5% on completion.
  6. Yonhap News Agency, CJ Logistics construction wins kt cloud Ansan AI data centre job (Korean), 22 Oct 2026. yna.co.kr — 32 MW IT load against 50 MW incoming power; about 38 months of works; kt cloud will use the building itself; CJ's scope of works.
  7. KT Corporation, 3Q26 earnings release (Form 6-K exhibit, SEC), 10 Nov 2026. sec.gov — demand-driven +1 GW by about 2031; six AI data centre sites to open by 2029 with Ansan in 2029; decisions on more sites in progress; kt cloud Q3 revenue KRW 268.2bn, +7.7%.